文檔簡(jiǎn)介
./第1題〔單選/1分:項(xiàng)目整體管理知識(shí)領(lǐng)域中,最后一個(gè)過(guò)程是______?Thelastprocessinintegrationmanagementis____?
制定項(xiàng)目章程Developprojectcharter
制定項(xiàng)目初步范圍說(shuō)明書(shū)Developpreliminaryprojectscopestatement
制定項(xiàng)目管理計(jì)劃Developprojectmanagementpla
項(xiàng)目收尾Closeproject
第2題〔單選/1分:甲乙雙方的項(xiàng)目經(jīng)理之間的關(guān)系更類(lèi)似于<>
TherelationshipbetweenprojectmanagersofPartyAandPartyBissimilartothatbetween<>
丈夫和妻子<Husbandandwife>
買(mǎi)方和賣(mài)方<Buyerandseller>
競(jìng)爭(zhēng)對(duì)手<Competitors<rivals>>
主動(dòng)和被動(dòng)<Activeandpassive>
第3題〔單選/1分:作為項(xiàng)目經(jīng)理,為使下屬做好他們的工作,需要<>
Tomakehis/hersubordinatestodotheirjobwell,theprojectmanagershould<>
激勵(lì)<Encourage>
安排他愿意做的工作<Assigntheworktheyarewillingtodo>
安排他能夠勝任的工作<Assigntheworkforwhichtheyarecompetent>
發(fā)展私人友誼<Developtheprivatefriendship>
第4題〔單選/1分:質(zhì)量基準(zhǔn)〔更新是____的輸出之一?QualityBaseline<updated>istheoutputof_____.
質(zhì)量規(guī)劃QualityPlanning
實(shí)施質(zhì)量保證Executequalityassurance
實(shí)施質(zhì)量控制Executequalitycontrol
產(chǎn)品質(zhì)量管理ProductQualityManagement
第5題〔單選/1分:控制發(fā)生在<>
Controlhappens.<>
整個(gè)項(xiàng)目周期<Inthewholeprojectperiod>
項(xiàng)目周期每一階段結(jié)束時(shí),以評(píng)估是否符合項(xiàng)目目標(biāo)<Attheendofeachstageoftheprojectperiodtoevaluatethecompliancewiththeprojectobjective>
每一計(jì)劃過(guò)程的結(jié)束階段<Attheendofeachplanprocess>
在執(zhí)行過(guò)程及其他過(guò)程需要時(shí)<Intheexecutionprocessorwhenitisnecessaryinotherprocesses>
第6題〔單選/1分:調(diào)整任務(wù)的時(shí)間安排以使得資源不被過(guò)分使用,這被稱(chēng)之為:<>
Adjustthescheduleoftaskssoastoavoidoveruseofresources,whichisreferredtoas:<>
資源平衡<Balanceduseofresources>
配對(duì)選擇<Partnershipselection>
多屬性效用理論<Multi-propertyutilitytheory>
資源浪費(fèi)<Wasteofresources>
第7題〔單選/1分:在某些情況下,合同結(jié)束是指:<>
Insomecircumstances,thecontractendingrefersto<>
在雙方的協(xié)議下合同結(jié)束<Undertheagreementbybothparties>
在發(fā)送貨物或服務(wù)后合同結(jié)束<Aftersendinggoodsorservices>
在成功的執(zhí)行后合同結(jié)束<Aftersuccessfullyexecutingthecontract>
在保證獲得最后的支付時(shí)<Uponreceivingthefinalpayment>
第8題〔單選/1分:在談判中通常出現(xiàn)的溝通問(wèn)題是:<>
Thecommunicationproblemsthatusuallyappearinthenegotiationare<>
談判的一方錯(cuò)誤的理解另一方的表述<Onepartymisunderstandstheotherparty’sstatement>
談判的一方放棄談判<Onepartyquitsthenegotiation>
談判的一方企圖使另一方迷惑<Onepartytriestoconfusetheotherparty>
談判的一方在聽(tīng)到另一方的陳述后忙于思考接著該說(shuō)什么<Onepartyisbusythinkingwhattosaynextafterhearingtheotherparty’sstatement>
第9題〔單選/1分:工作結(jié)果是<>
Theworkresultis.<>
為了實(shí)現(xiàn)項(xiàng)目目標(biāo)實(shí)行的所有活動(dòng)的輸出<Outputofallactivitiesthatareexercisedtorealizetheprojectobjective>
成功完成項(xiàng)目指標(biāo)<Projectindexesthataresuccessfullyachieved>
客戶(hù)正式驗(yàn)收項(xiàng)目<Formalacceptanceitemsofthecustomer>
完成合同的正式驗(yàn)收<Formalacceptanceofcontractcompletion>
第10題〔單選/1分:質(zhì)量管理計(jì)劃說(shuō)明以下各項(xiàng),除了<>
Thequalitymanagementplandoesnotcover<>
執(zhí)行質(zhì)量策略的方法<Methodofexecutingqualitypolicies>
項(xiàng)目的質(zhì)量體系<Qualitysystemoftheproject>
組織機(jī)構(gòu),職責(zé),程序,流程,和進(jìn)行項(xiàng)目質(zhì)量管理所必需的資源<Organizationstructure,responsibilities,program,flow,andresourcesnecessaryforprojectqualitymanagement>
進(jìn)行成本,進(jìn)度和質(zhì)量平衡分析的程序<Programanalyzingcost,schedule,andqualitybalance>
第11題〔單選/1分:規(guī)劃會(huì)議和分析是_____的工具之一。PlanningMeetingandAnalysisisatoolof____.
風(fēng)險(xiǎn)管理規(guī)劃RiskManagementPla
風(fēng)險(xiǎn)識(shí)別RiskIdentificatio
定性風(fēng)險(xiǎn)分析QualitativeRiskAnalysis
定量風(fēng)險(xiǎn)分析QuantativeRiskAnalysis
第12題〔單選/1分:作為一個(gè)項(xiàng)目經(jīng)理,在審核一個(gè)新項(xiàng)目能否上馬時(shí),你首先會(huì)問(wèn)<>
Asaprojectmanager,youwillfirstputforwardthequestion<>whenreviewingwhetheranewprojectcanbestarted.
我們有能力完成這個(gè)項(xiàng)目嗎<Dowehavethecapabilitytoaccomplishtheproject?>
這個(gè)項(xiàng)目能夠盈利嗎<Istheprojectisprofitable?>
為誰(shuí)為什么要做這個(gè)項(xiàng)目<Whyshouldwedothisproject?>
做這個(gè)項(xiàng)目有沒(méi)有風(fēng)險(xiǎn)<Isthereanyriskforthisproject?>
第13題〔單選/1分:完成一項(xiàng)多任務(wù)項(xiàng)目的成功機(jī)會(huì)將會(huì)大大加強(qiáng),如果項(xiàng)目小組成員:<>
Thechanceforaccomplishingamulti-taskprojectwillbegreatlyenhancedifthememberstotheprojectteam<>
以問(wèn)題為關(guān)注焦點(diǎn)<Concernabouttheproblem>
對(duì)最高管理層的需要敏感<Besensitivetotherequirementsofthehighestmanagementlevel>
集中關(guān)注單個(gè)任務(wù)<Paymuchattentiontoasingletask>
關(guān)注客戶(hù)需求<Concernaboutcustomers'requirements>
第14題〔單選/1分:項(xiàng)目溝通管理有____個(gè)過(guò)程?____processesareinvolvedinProjectCommunicationManagement.
1
2
3
4
第15題〔單選/1分:項(xiàng)目計(jì)劃的制定應(yīng)______
Thepreparationofaprojectplanshouldbe__________
在項(xiàng)目開(kāi)始的前期階段就全部完成<Completelyfinishedintheearlystageoftheproject>
在整個(gè)項(xiàng)目實(shí)施過(guò)程中不斷反復(fù)進(jìn)行<Repeatedintheimplementationofthewholeproject>
在項(xiàng)目開(kāi)始前就全部完成<Completelyfinishedbeforethestartoftheproject>
當(dāng)前任務(wù)需要一個(gè)計(jì)劃時(shí)完成<Finishedwhenthecurrenttaskrequiresaplan>
第16題〔單選/1分:項(xiàng)目管理計(jì)劃〔更新是____的輸出之一。ProjectManagementPlan<updated>istheoutputof_____.
人力資源規(guī)劃HRplanning
項(xiàng)目團(tuán)隊(duì)組建Acquireprojectteam
項(xiàng)目團(tuán)隊(duì)建設(shè)Developprojectteam
項(xiàng)目團(tuán)隊(duì)管理Manageprojectteam
第17題〔單選/1分:在一個(gè)經(jīng)營(yíng)方案中,企業(yè)獲得2百萬(wàn)元收益的可能性是60%,遭受1.5百萬(wàn)損失的可能性是20%,那該方案的預(yù)期價(jià)值是多少?<>
Inanoperationscheme,thepossibilityfortheenterprisetogainproceedsof2million$is60%,andthepossibilityforsufferinglossesof1.5million$is20%.Whatistheexpectedvalueofthisscheme?<>
$50,000
$300,000
$500,000
$900,000
第18題〔單選/1分:在下列哪種情況下,需要附加的風(fēng)險(xiǎn)應(yīng)對(duì)措施開(kāi)發(fā)<>
Underwhichofthefollowingcasesistheadditionalriskhandlingmeasuredevelopmentrequired?<>
工作分解結(jié)構(gòu)<WBS>發(fā)生變動(dòng)<TheWBSchanges.>
成本基準(zhǔn)發(fā)生變動(dòng)<Thecostreferencechanges.>
風(fēng)險(xiǎn)事件未被預(yù)計(jì)到或者其影響此預(yù)計(jì)的要大<Theriskeventisnotpredictedoritsinfluenceismoreseriousthattheprediction.>
項(xiàng)目計(jì)劃過(guò)時(shí)<Theprojectplanisoutofdate.>
第19題〔單選/1分:假設(shè)包括風(fēng)險(xiǎn)因素是因?yàn)?<>
Assumptionsincluderiskfactorsbecause<>
假設(shè)是建立在以前獲得的經(jīng)驗(yàn)基礎(chǔ)之上的<Assumptionsarebasedonexperience.>
可能沒(méi)有過(guò)去的相關(guān)資料<Nohistorydataisavailable.>
假設(shè)是建立在限制因素上的<Assumptionsarebasedonconstraints.>
假設(shè)包括那些被認(rèn)為是正確、真實(shí)和肯定的因素<Assumptionsincludethosefactorsthatareconsideredcorrect,true,andaffirmative.>
第20題〔單選/1分:對(duì)于事業(yè)部級(jí)別項(xiàng)目,指委會(huì)主任應(yīng)由哪個(gè)崗位擔(dān)任?FortheprojectofdivisionLevel,shouldbetherightonetotakethepositionofDirectorofProjectCommittee?
國(guó)代CountryRepresentative
營(yíng)銷(xiāo)事業(yè)部/售后SVPSVPofSales/After-salesSystem
營(yíng)銷(xiāo)事業(yè)部總經(jīng)理助理AssistantofSalesSystemmanager
產(chǎn)品經(jīng)營(yíng)部<SVP>SVPofMarketingdepartment
區(qū)總RegionRepresentative
第21題〔單選/1分:檢驗(yàn)項(xiàng)目工作是否完成,需要使用:<>
Toinspectwhethertheprojectworkhasbeenfinished,weneedtouse:<>
項(xiàng)目要求<Projectrequirements>
項(xiàng)目計(jì)劃<Projectplan>
項(xiàng)目管理計(jì)劃<Projectmanagementplan>
WBS〔工作任務(wù)分解表<WBS<workbreakdownstructure>
第22題〔單選/1分:年折舊率=〔2/預(yù)計(jì)折舊年限*100%,這個(gè)公式是哪種折舊方法的公式?Annualdepreciationrate=<2/PredictedDepreciationDuration>*100%.Whichkindofdepreciationcalculationmethodisemployedbyusingthisformulate?
直線折舊LinearDepreciatio
雙倍余額折舊法Dual-BalanceDepreciatio
年數(shù)總和折舊法Depreciationbysumoftheyear
以上都不是<NoneoftheAbove
第23題〔單選/1分:____不是制定項(xiàng)目章程的輸入。____isnotaninputofDevelopProjectCharter
合同Contract
項(xiàng)目工作說(shuō)明書(shū)ProjectStatementofWork
事業(yè)環(huán)境因素Enterpriseevnironmentalfactors
工作分解結(jié)構(gòu)WBS
第24題〔單選/1分:下列哪一項(xiàng)是成本控制的輸出?<>
Whichoneofthefollowingitemsistheoutputofcostcontrol?<>
成本基線<Costbaseline>
變更請(qǐng)求<Changingrequirement>
完工估算-EAC<Estimateofcompletion-EAC>
額外計(jì)劃<Extraplan>
第25題〔單選/1分:當(dāng)一個(gè)流程被認(rèn)為在控制之中時(shí),<>
Whenaflowisconsideredundercontrol,<>
不應(yīng)實(shí)行調(diào)整<Itshouldnotbeadjusted.>
不應(yīng)進(jìn)行變更以改進(jìn)<Itshouldnotbechangedforimprovement.>
該流程顯示了由可預(yù)見(jiàn)或通常的原因引起的偏差<Theflowdisplaysthevariancescausedbypredictableorcommoncauses.>
不應(yīng)由于任何原因?qū)嵤z查或返工<Theflowshouldnotbecheckedorreworkedforanyreason.>
第26題〔單選/1分:項(xiàng)目管理計(jì)劃〔更新是____的輸出之一。ProjectManagementPlan<updated>istheoutputof_____.
活動(dòng)定義Activitydefinitio
活動(dòng)排序Activitysequencing
活動(dòng)資源估算Activityresourceestimatio
制定進(jìn)度表Developschedule
第27題〔單選/1分:在項(xiàng)目溝通中起主要作用的角色是:_______
Themainroleinprojectcommunicationis_______
項(xiàng)目發(fā)起人;<Projectsponsor>
項(xiàng)目經(jīng)理;<Projectmanager>
部門(mén)經(jīng)理;<Departmentmanager>
團(tuán)隊(duì)成員<Teammembers>
第28題〔單選/1分:質(zhì)量核對(duì)表是____的輸出之一?QualityCheckListtheoutputof_____.
質(zhì)量規(guī)劃QualityPlanning
實(shí)施質(zhì)量保證Executequalityassurance
實(shí)施質(zhì)量控制Executequalitycontrol
產(chǎn)品質(zhì)量管理ProductQualityManagement
第29題〔單選/1分:類(lèi)比估算是____的工具之一。AnalogyEstimationisthetoolof____.
費(fèi)用估算Costestimatio
費(fèi)用預(yù)算Costbudgeting
費(fèi)用控制Costcontrol
自下而上的估算Upwardestimatio
第30題〔單選/1分:進(jìn)度控制與下列哪種因素?zé)o關(guān)?<>
Whichofthefollowingfactorsareindependentoftheschedulecontrol?<>
對(duì)促進(jìn)項(xiàng)目進(jìn)度產(chǎn)生變化的影響因素進(jìn)行管理,保證進(jìn)度的變化是有益的。<Managetheinfluentialfactorsthatpromotethechangeoftheprojectscheduletoensurethattheschedulechangeisbeneficial.>
確定項(xiàng)目進(jìn)度發(fā)生了變化<Determinethattheprojectscheduleischanged.>
當(dāng)變化出現(xiàn)時(shí),對(duì)實(shí)際發(fā)生的變化進(jìn)行管理<Whenachangehappens,manageit.>
根據(jù)客戶(hù)要求改變項(xiàng)目進(jìn)度<Changetheprojectscheduleasrequiredbythecustomer.>
第31題〔單選/1分:質(zhì)量管理有____個(gè)過(guò)程?____processesareinvolvedinProjectQualityManagement.
1
2
3
4
第32題〔單選/1分:用Crashing〔趕工法來(lái)壓縮項(xiàng)目周期________應(yīng)用于關(guān)鍵路徑上
Crashingwhichisusedtoshortentheprojectperiod________beappliedtocriticalpaths.
不一定<Willnotalways>
肯定應(yīng)該<Willsurely>
無(wú)法判定<Willnotsurely>
不能<Cannot>
第33題〔單選/1分:以下哪項(xiàng)是溝通計(jì)劃編制所用的技術(shù)或工具:<>
Whichofthefollowingisthetechnologyortoolusedforcompilingcommunicationplan?<>
項(xiàng)目干系人分析<Projectstakeholderanalysis>
溝通技術(shù)<Communicationtechnology>
信息查詢(xún)系統(tǒng)<Informationreferralsystem>
信息發(fā)送系統(tǒng)<Informationdeliverysystem>
第34題〔單選/1分:進(jìn)度網(wǎng)絡(luò)分析是____的工具之一。ScheduleNetworkAnalysisisatoolfor____.
活動(dòng)定義Activitydefinitio
活動(dòng)排序Activitysequencing
活動(dòng)資源估算Activityresourceestimatio
制定進(jìn)度表Developschedule
第35題〔單選/1分:團(tuán)隊(duì)績(jī)效評(píng)估是____的輸出之一。TeamPerformanceEvaluationistheoutputof_____.
人力資源規(guī)劃HRplanning
項(xiàng)目團(tuán)隊(duì)組建Acquireprojectteam
項(xiàng)目團(tuán)隊(duì)建設(shè)Developprojectteam
項(xiàng)目團(tuán)隊(duì)管理Manageprojectteam
第36題〔單選/1分:通常在什么時(shí)候進(jìn)行預(yù)算需要更新?<>
Whenthebudgetusuallyneedstoberefreshed?<>
當(dāng)項(xiàng)目經(jīng)理知道如果不進(jìn)行更新就會(huì)超支的時(shí)候<Whentheprojectmanagerknowsthatoverdrawingwouldariseifupdatingisnotdone>
項(xiàng)目范同變更得到認(rèn)可時(shí)<Whenthechangeoftheprojectcontractisrecognized>
項(xiàng)目的任何一方重新制定基線時(shí)<Whenanypartytotheprojectworksoutthebaselineagain>
在應(yīng)急或管理儲(chǔ)備金已使用時(shí)<Whentheemergencyormanagementreserveisused>
第37題〔單選/1分:自下而上的估算是____的工具之一。UpwardEstimationisthetoolof____.
費(fèi)用估算Costestimatio
費(fèi)用預(yù)算Costbudgeting
費(fèi)用控制Costcontrol
自下而上的估算Upwardestimatio
第38題〔單選/1分:項(xiàng)目章程授予項(xiàng)目經(jīng)理職權(quán)去運(yùn)用組織資源,這個(gè)文件是由誰(shuí)發(fā)出:<>
Theprojectregulationsgrantstheprojectmanagerwiththepowertoapplytheorganizationresources,whoissuesthisdocument?<>
系統(tǒng)經(jīng)理<Systemmanager>
職能經(jīng)理<Functionalmanager>
發(fā)起人<Initiator>
客戶(hù)<Customer>
第39題〔單選/1分:目標(biāo)管理不涉及下列哪項(xiàng)內(nèi)容<>
Managementbyobjectives<MBO>doesnotcover.<>
確定明確和現(xiàn)實(shí)的目標(biāo)<Establishadefinite,practicalobjective>
定期評(píng)估項(xiàng)目目標(biāo)是否完成<Regularlyevaluatewhethertheprojectobjectiveisachieved>
促進(jìn)項(xiàng)目的參與,團(tuán)隊(duì)建立和實(shí)現(xiàn)承諾<Promotetheparticipationinproject,teamestablishment,andcommitmentachievement>
為項(xiàng)目小組成員建立特殊的職業(yè)軌跡<Establishaspecialoccupationforprojectteammembers>
第40題〔單選/1分:對(duì)項(xiàng)目工程質(zhì)量直接負(fù)責(zé)的是?WhoisdirectlyresponsibleforProjectQuality?
項(xiàng)目經(jīng)理projectmanager
工程經(jīng)理engineeringmanager
外包經(jīng)理outsourcingmanager
技術(shù)經(jīng)理technicalmanager
質(zhì)量經(jīng)理QAmanager
土建經(jīng)理civilworkmanager
第41題〔單選/1分:項(xiàng)目質(zhì)量管理曾被認(rèn)為只包括檢查或質(zhì)量控制。近年來(lái)項(xiàng)目質(zhì)量管理的概念在擴(kuò)大。以下哪一項(xiàng)不代表對(duì)質(zhì)量管理的新定義:<>
Itisonceconsideredthattheprojectqualitymanagementonlyincludesinspectionorqualitycontrol.Inrecentyears,themeaningoftheconceptofprojectqualitymanagementhasbeenextended.Whichofthefollowingisnotanewdefinitionof"qualitymanagement"?<>
質(zhì)最是在產(chǎn)品或服務(wù)的設(shè)計(jì)中實(shí)現(xiàn)的,而不是由質(zhì)檢實(shí)現(xiàn)的<Qualityisensuredintheproductorservicedesign,insteadofqualitycontrol.>
質(zhì)量?jī)H是質(zhì)量保證人員的事務(wù)<Qualityisonlytheaffairofqualityassurancepersonnel.>
客戶(hù)要求一種書(shū)面方式的,有時(shí)是登記方式的質(zhì)量保證體系<Thecustomerrequiresaqualityassurancesysteminwriting,andsometimesaregisteredqualityassurancesystem.>
可以建立國(guó)家的和國(guó)際的質(zhì)量保證體系標(biāo)準(zhǔn)和指導(dǎo)原則<Standardsandguidelinescanbeestablishedfornationalandinternationalqualityassurancesystems.>
第42題〔單選/1分:以下哪項(xiàng)是項(xiàng)目經(jīng)理最重要的素質(zhì)?<>
Whichisthemostimportantqualitythataprojectmanagershouldhave?<>
監(jiān)管經(jīng)驗(yàn)<Supervisingexperience>
談判技巧<Negotiationskills>
技術(shù)背景<Technicalbackground>
與人協(xié)作的能力<Abilitytocommunicate>
第43題〔單選/1分:以下哪一項(xiàng)不是風(fēng)險(xiǎn)管理計(jì)劃的輸入:<>
Whichisnotinputoftheriskmanagementplan?____
WBS<WBS>
項(xiàng)目干系人對(duì)風(fēng)險(xiǎn)的承受限度<Riskbearinglimitoftheprojectresponsibleperson>
風(fēng)險(xiǎn)類(lèi)別<Riskcategory>
所在機(jī)構(gòu)的風(fēng)險(xiǎn)管理規(guī)定<Riskmanagementregulationoftherelevantorganization>
第44題〔單選/1分:預(yù)測(cè)技術(shù)是____的工具之一。Predictionisthetoolof____.
費(fèi)用估算Costestimatio
費(fèi)用預(yù)算Costbudgeting
費(fèi)用控制Costcontrol
自下而上的估算Upwardestimatio
第45題〔單選/1分:項(xiàng)目范圍說(shuō)明書(shū)是____的輸入之一.ProjectScopeStatementistheinputof______.
溝通規(guī)劃Communicationplanning
信息發(fā)布Informationdistributio
績(jī)效報(bào)告Performancereporting
利害關(guān)系者管理Stakeholdermanagement
第46題〔單選/1分:以下哪一項(xiàng)不屬于項(xiàng)目團(tuán)隊(duì)建設(shè)的工具和方法:_______
Whichoneofthefollowingitemsisnotwithintherangeoftoolsandmethodsforconstructingaprojectteam?_______
集中工作<Centralizedworking>
獎(jiǎng)勵(lì)<Encouragement>
培訓(xùn)<Training>
人員獲取<Personnelattainment>
第47題〔單選/1分:在進(jìn)行項(xiàng)目工期估算時(shí),下列那些將不應(yīng)考慮<>
Whenyouestimatetheprojectperiod,whichofthefollowingfactorsshouldyouneglect?<>
資源的能力<Resourcecapability>
分配到一項(xiàng)任務(wù)的資源總數(shù)<Totalresourcesassignedtoatask>
歷史資料<如有的話><Historydata<ifany>>
管理費(fèi)用<Administrationcosts>
第48題〔單選/1分:范圍規(guī)劃的輸出是_____Theoutputofscopeplanningis____.
項(xiàng)目范圍管理計(jì)劃Projectscopemanagemntplan
項(xiàng)目范圍說(shuō)明書(shū)Projectscopestatement
請(qǐng)求的變更Requestedchange
工作分解結(jié)構(gòu)WBS
第49題〔單選/1分:所有被認(rèn)可的變更應(yīng)在______中體現(xiàn)
Allrecognizablechangesshouldberepresentedin<>
績(jī)效測(cè)定基線<Performancemeasurementbaseline<PMB>>
變更管理計(jì)劃<Changemanagementplan>
質(zhì)量保證計(jì)劃<Qualityassuranceplan>
更新的項(xiàng)目計(jì)劃<NewProjectplan>
第50題〔單選/1分:WBS最底層的活動(dòng)稱(chēng)為_(kāi)_______
Lowest-levelactivitiesofWBSarecalled<>
工作包<Workpackage>
子任務(wù)<Subtask>
底層任務(wù)<Lower-leveltasks>
二級(jí)任務(wù)<Level-2tasks>
第51題〔單選/1分:在項(xiàng)目的收尾階段,最多的矛盾來(lái)自于以下哪方面:<>
Attheclosureofaproject,whichaspectwillbringaboutthemostconflicts?<>
進(jìn)度問(wèn)題<Progress>
費(fèi)用超支<Overspending>
技術(shù)問(wèn)題<Technology>
工作界而<Workinterface>
第52題〔單選/1分:質(zhì)量檢查也被稱(chēng)為<>
Qualityinspectionisalsocalled<>
控制測(cè)試<Controltest>
巡查<Patrolinspection>
統(tǒng)計(jì)取樣<Statisticssampling>
審核列表<Checklist>
第53題〔單選/1分:采購(gòu)文件是____的輸出之一。Procurementdocumentistheoutputof____.
采購(gòu)規(guī)劃Planpurchaseandacquisitions
發(fā)包規(guī)劃Plancontractor
詢(xún)價(jià)Inquiry
賣(mài)方選擇Selectseller
第54題〔單選/1分:如果資源部門(mén)經(jīng)理告訴你,你需要在3月份獲得的人員,一直到5月份才能到,你會(huì):_______
IfthemanagerofaresourcedepartmenttellsyouthatthepersonnelyouneedinMarchcanbeobtainedtillMay,youwill_______
接受并重新安排項(xiàng)目;<Acceptandre-arrangetheproject;>
讓你的直接領(lǐng)導(dǎo)幫忙;<Resorttoyourimmediateleadership;>
要求上級(jí)提高你的項(xiàng)目?jī)?yōu)先級(jí);<Askyoursuperiortoraisethepriorityofyourproject>
和資源部門(mén)經(jīng)理一起工作,制定應(yīng)急計(jì)劃<Worktogetherwiththemanageroftheresourcedepartmenttoworkoutanemergencyplan>
第55題〔單選/1分:下面哪一項(xiàng)不是四大風(fēng)險(xiǎn)應(yīng)對(duì)策略之一:<>
Whichofthefollowingoptionsdoesnotbelongtothefourmajorriskhandlingstrategies?_____
規(guī)避<Evasion>
減輕<Alleviation>
接受<Accept>
控制<Control>
第56題〔單選/1分:與其他人商談,達(dá)到一致的過(guò)程稱(chēng)為:<>
Theprocesstoreachagreementbyconsultingwithothersiscalled<>
雙贏<Win-win>
談判<Negotiation>
獲得贊同<Obtainapproval>
對(duì)抗<Confrontation>
第57題〔單選/1分:質(zhì)量成本是____的工具之一。QualityCostisthetoolof____.
費(fèi)用估算Costestimation
費(fèi)用預(yù)算Costbudgeting
費(fèi)用控制Costcontrol
自下而上的估算Upwardestimatio
第58題〔單選/1分:項(xiàng)目經(jīng)理使成員工作地點(diǎn)不一致的小組發(fā)揮最佳工作效率的重要方式是:<>
Themostimportantapproachaprojectmanagerusestomaximizetheworkingefficiencyoftheteamswhomembersworkindifferentplacesis<>
建立信任<Tobuildtrust>
建立獎(jiǎng)勵(lì)業(yè)績(jī)認(rèn)可制度<Toestablishanencouragementandperformancerecognitionsystem>
爭(zhēng)取獲得其他工作地點(diǎn)的職能經(jīng)理的支持<Tostriveforobtainingthesupportfromthefunctionalmanagersinotherworkingplaces>
項(xiàng)目經(jīng)理運(yùn)用權(quán)力控制項(xiàng)目所有方面<Thattheprojectmanagercontrolseveryaspectofaprojectusingitspower>
第59題〔單選/1分:在下列哪個(gè)項(xiàng)目階段會(huì)發(fā)生最嚴(yán)重的不確定性?<>
Whichofthefollowingprojectstageisvulnerabletothemostsevereuncertainty?<>
計(jì)劃階段<Planstage>
設(shè)計(jì)階段<Designstage>
執(zhí)行階段<Implementationstage>
結(jié)束階段<Completionstage>
第60題〔單選/1分:以下哪項(xiàng)不是非正式的書(shū)面溝通方式:<>
Whichofthefollowingisnottheinformalwrittencommunicationmode:<>
工程師的便條<Engineer'snote>
電子郵件<Email>
管理計(jì)劃<Managementplan>
備忘錄<Memo>
第61題〔單選/1分:測(cè)量和報(bào)告項(xiàng)目進(jìn)度表現(xiàn)的基礎(chǔ)是:<>
Thebasisofmeasuringandreportingtheprojectscheduleperformanceis.<>
項(xiàng)目進(jìn)度的基線<Baselineoftheschedule>
項(xiàng)目進(jìn)度修改建議的數(shù)量<Numberofchangesuggestionsontheprojectschedule>
事件和工作計(jì)劃與事實(shí)的區(qū)別<Differencebetweenevents/workplanandfacts>
技術(shù)基線<Technicalbaseline>
第62題〔單選/1分:進(jìn)行風(fēng)險(xiǎn)分析時(shí)對(duì)風(fēng)險(xiǎn)進(jìn)行排序,考慮什么因素?<>
Whatfactorshouldbeconsideredforsortingrisksatriskanalysis?<>
風(fēng)險(xiǎn)發(fā)生的概率<Riskoccurrenceprobability>
風(fēng)險(xiǎn)的后果<Riskresult>
風(fēng)險(xiǎn)應(yīng)對(duì)措施的成本<Costorriskhandlingmeasure>
風(fēng)險(xiǎn)概率與風(fēng)險(xiǎn)后果的共同作用<Jointeffectofriskprobabilityandriskresult>
第63題〔單選/1分:項(xiàng)目時(shí)間管理包括____個(gè)過(guò)程TimeManagementincludes___proecess.
3
4
5
6
第64題〔單選/1分:項(xiàng)目容易受到風(fēng)險(xiǎn)的影響,這是因?yàn)椋?lt;>
Theprojectiseasilyaffectedbyrisk,because:<>
墨非規(guī)則闡述到:如果一件事情可能會(huì)出問(wèn)題,它就會(huì)出問(wèn)題<Murphy’slawsetsforth:Ifaproblemmayoccurtoamatter,itwilloccursurely.>
每一個(gè)項(xiàng)目在某些方面都是特殊的<Eachprojectisspecialinsomeaspect.>
在項(xiàng)目隊(duì)伍層面上,項(xiàng)目管理工作通常是無(wú)法獲得的<Theprojectmanagementworkcannotbeobtainedusuallyintermsoftheprojectteamlayer.>
總是沒(méi)有充足的資源來(lái)完成工作<Therearealwaysnosufficientresourcesforcompletingwork.>
第65題〔單選/1分:以下哪項(xiàng)是質(zhì)量控制的輸出<>
Whichofthefollowingistheoutputofqualitycontrol?<>
統(tǒng)計(jì)取樣<Statisticssampling>
質(zhì)量管理計(jì)劃<Qualitymanagementplan>
工作結(jié)果<Workresult>
計(jì)劃調(diào)整<Planadjustment>
第66題〔單選/1分:采購(gòu)管理計(jì)劃是____的輸出之一。ProcurementManagementPlanistheoutputof____.
采購(gòu)規(guī)劃Planpurchaseandacquisitons
發(fā)包規(guī)劃Plancontraction
詢(xún)價(jià)Inquiry
賣(mài)方選擇Selectseller
第67題〔單選/1分:質(zhì)量控制圖表主要用來(lái)幫助<>
Thequalitycontrolchartisusedto.<>
監(jiān)控隨時(shí)間推移發(fā)生的流程變化<Monitortheflowthatvarieswithtime>
衡量一致程度<Measuretheconsistency>
確定是否結(jié)果一致<Determinetheconsistencyofresults>
確定是否結(jié)果與要求一致<Determinewhethertheresultsareconsistentwiththerequirements>
第68題〔單選/1分:客戶(hù)要求進(jìn)行范圍變更。為了分析變更對(duì)項(xiàng)目的影響,項(xiàng)目經(jīng)理應(yīng)該回顧工作分解結(jié)構(gòu)、變更請(qǐng)求、范圍管理計(jì)劃和_______?
Inordertoanalyzetheinfluenceontheprojectcausedbythechange,thePMshouldreviewtheworkbreakdownstructure,changerequest,scopemanagementplanand_______
績(jī)效報(bào)告<Performancereport>
職責(zé)分配矩陣<Responsibilityallocationmatrix>
帕累托圖<Paretochart>
蒙特卡洛模擬<MonteCarlosimulation>項(xiàng)目經(jīng)理應(yīng)該:
第69題〔單選/1分:關(guān)于項(xiàng)目溝通環(huán)境的陳述,哪一項(xiàng)是正確的?<>
Whichofthefollowingiscorrectaboutthestatementofcommunicationenvironment?<>
項(xiàng)目經(jīng)理對(duì)信息的發(fā)送和接收承擔(dān)主要責(zé)任<Theprojectmanagertakesprimaryresponsibilityforsendingandreceivinginformation>
有效率的會(huì)議,項(xiàng)目作戰(zhàn)室和強(qiáng)矩陣能促進(jìn)有效的溝通<Theeffectivecommunicationcanbeenhancedbyefficientmeeting,projectwarroomandstrongmatrix.>
如果一個(gè)項(xiàng)目中有12個(gè)人,則有48條潛在的溝通渠道存在<Ifthereare12personsinaproject,thentherearepotentially48communicationchannels>
大多的項(xiàng)目經(jīng)理將他們工作時(shí)間的30%用于溝通<Mostprojectmanagersspend30%oftheirworkingtimeincommunicating>
第70題〔單選/1分:資源計(jì)劃的目的是<>
Theresourceplanisaimedat<>
決定進(jìn)行項(xiàng)目工作的物質(zhì)資源<Determiningthematerialresourcesfortheproject>
估計(jì)完成項(xiàng)目所需的資源成本<Estimatingthecostoftheresourcesneededtocompletetheproject>
決定有可能得到的資源<Decidingtheresourcesthatmaybeobtained>
估計(jì)有關(guān)項(xiàng)目所用的資源的組織方式<Estimatingtheorganizingmodefortheresourcesusedbytherelatedproject>
第71題〔單選/1分:下面中的哪一項(xiàng)不是項(xiàng)目歷時(shí)估算的方法?_______
Whichofthefollowingitemsisnotthemethodofprojectdurationestimation?_______
類(lèi)比法<Analogy>
Delphi法<Delphitechnique
專(zhuān)家判定<Expertjudgment
帕累托法<Paretotechnique>
第72題〔單選/1分:項(xiàng)目人力資源管理有____個(gè)過(guò)程?____processareinvolvedinProjectHRManagement
1
2
3
4
第73題〔單選/1分:以下哪一項(xiàng)是項(xiàng)目隊(duì)伍建設(shè)的基本原則<>
Whichoneofthefollowingitemsisthebasicprincipleforbuildingaprojectteam?<>
進(jìn)行經(jīng)常性的執(zhí)行情況評(píng)估<Conductthefrequentassessmentsontheimplementation>
確保項(xiàng)目隊(duì)伍每位成員除了向項(xiàng)目經(jīng)理匯報(bào)之外同時(shí)向職能經(jīng)理匯報(bào)<Makesurethateachmembertoaprojectteamreportstothefunctionalmanagerinadditiontoreportingtotheprojectmanager>
盡早組建項(xiàng)目團(tuán)隊(duì)<Buildaprojectteamassoonaspossible>
解決成員間的政治分歧<Solvethepoliticaldivergenceamongthemembers>
第74題〔單選/1分:下列文檔都對(duì)項(xiàng)目范圍和任務(wù)進(jìn)行了描述,其描述詳細(xì)程度從粗略到細(xì)致的順序是:________
Thesequencefromroughnesstodetailofthefollowingdocumentsindescribingtheprojectscopeandtasksis<>
工作范圍說(shuō)明書(shū),立項(xiàng)報(bào)告,活動(dòng)清單,WBS<Workscopespecification,projectinitiationreport,activitylist,WBS>
立項(xiàng)報(bào)告,工作范圍說(shuō)明書(shū),活動(dòng)清單,WBS<Projectinitiationreport,workscopespecification,activitylist,WBS>
立項(xiàng)報(bào)告,工作范圍說(shuō)明書(shū),WBS,活動(dòng)清單<Projectinitiationreport,workscopespecification,WBS,activitylist>
立項(xiàng)報(bào)告,,WBS,工作范圍說(shuō)明書(shū),活動(dòng)清單<Projectinitiationreport,WBS,workscopespecification,activitylist>
第75題〔單選/1分:項(xiàng)目文檔是:<>
Projectdocumentrefersto<>
項(xiàng)目產(chǎn)品的文檔化<Documentofprojectproduct>
關(guān)于項(xiàng)目的教訓(xùn)<Experienceontheproject>
一整套有索引的項(xiàng)目記錄<Awholesetofindexedrecords>
只對(duì)組織中最重要,最復(fù)雜的項(xiàng)目進(jìn)行<Madeforthemostimportantandcomplicatedprojectsfortheorganization>
第76題〔單選/1分:質(zhì)量控制應(yīng)<>
Thequalitycontrolshould:<>
在項(xiàng)目的產(chǎn)品是完整的并無(wú)缺陷時(shí)進(jìn)行<Performedwhentheproductsoftheprojectareintact,withoutanydefect.>
在項(xiàng)目整個(gè)過(guò)程中進(jìn)行<Performedinthewholeprojectprocess>
在客戶(hù)接受前的最后階段進(jìn)行<Performedinthelaststagebeforethecustomer’sacceptance>
在質(zhì)量保證部門(mén)的要求下進(jìn)行<Performedasrequiredbythequalitydepartment>
第77題〔單選/1分:在工作范圍未改變前提下,實(shí)際成本超出了合同中所預(yù)計(jì)的成本,這稱(chēng)為:<>
Underthepreconditionthattheworkscopeisunvaried,theactualcostexceedstheoneestimatedinthecontract,whichiscalled:<>
成本逐步增加<Gradualincreaseofcost>
成本增長(zhǎng)率<Costgrowthrate>
成本超支<Costoverspending>
成本風(fēng)險(xiǎn)<Costrisk>
第78題〔單選/1分:五大管理過(guò)程組是啟動(dòng)、計(jì)劃、執(zhí)行、________、收尾
Thefivemajormanagementprocessesincludestartup,plan,execution,________,andclosing.
實(shí)施<Implementation>
測(cè)試<Test>
控制<Control>
評(píng)審<Review>
第79題〔單選/1分:項(xiàng)目費(fèi)用管理有____個(gè)過(guò)程?____processesareinvolvedinProjectCostManagement.
1
2
3
4
第80題〔單選/1分:規(guī)劃設(shè)計(jì)經(jīng)理應(yīng)屬于哪個(gè)子團(tuán)隊(duì)?Whichsub-teamshouldPlan&DesignManagerbelongto?
合同交付子團(tuán)隊(duì)Sub-teamofcontractconsignment
技術(shù)方案子團(tuán)隊(duì)Sub-teamoftechnicalsolutio
市場(chǎng)商務(wù)團(tuán)隊(duì)Sub-teamofbusinessaffairs
項(xiàng)目管理核心團(tuán)隊(duì)coreteamofprojectmanagement
成本控制團(tuán)隊(duì)teamofcostcontro
外包子團(tuán)隊(duì)sub-teamofoutsourcingmanagement
第81題〔單選/1分:成本預(yù)算的目的是<>
Thepurposeofthecostbudgetis<>
決定完成項(xiàng)目工作所需資源的成本,并把它們分配到適當(dāng)?shù)慕M織圖表中<Todecidethecostoftheresourcesneededbytheprojectwork,andallocatethemtoanappropriateorganizationchart>
監(jiān)控成本狀況以發(fā)現(xiàn)與計(jì)劃的偏離<Tomonitorthecoststatustodiscoveritsdeviationfromtheplan>
將總成本分配到每個(gè)工作項(xiàng)目上來(lái)確立成本基線,并以此為依據(jù)測(cè)算項(xiàng)目績(jī)效<Toallocatethetotalcosttoeachworkprojecttodeterminethecostbaseline,onthebasisofwhichtheprojectperformancecanbemeasured>
將資金成本限制在最小<Tolimitthecapitalcosttotheminimum>
第82題〔單選/1分:項(xiàng)目干系人管理的主要目標(biāo)是:<>
Theprojectstakeholdermanagementisto<>
找出所有的潛在客戶(hù),確保進(jìn)行完整的項(xiàng)目需求分析<Findallpotentialcustomersandensurethattheprojectrequirementanalysisis
就干系人關(guān)心的問(wèn)題提出一系列答案,以應(yīng)對(duì)他們對(duì)項(xiàng)目的批評(píng)<Giveanswerstothequestionsputforwardbystakeholderstocopewiththeircriticismontheproject.>
積極控制干系人可能對(duì)項(xiàng)目影響<Proactivelycontroltheeffectworkofstakeholderstotheproject>
如果項(xiàng)目進(jìn)度延期或項(xiàng)目投資超出預(yù)算,保持與干系人的良好關(guān)系<Iftheprojectisdelayedortheprojectinvestmentexceedsthebudget,keepagoodrelationshipwithstakeholders.>
第83題〔單選/1分:下列活動(dòng)中,那些不便用項(xiàng)目管理的方式做?<>
Whichofthefollowingactivitiesistheprojectmanagementnotapplicableto?<>
在有生之年環(huán)游全球<Worldtravelintherestlifetime>
在畢業(yè)前尋找一份工作<Seekingajobbeforegraduation>
二個(gè)月內(nèi)完成家庭裝修<Completionofhousedecorationwithintwomonths>
三個(gè)月內(nèi)開(kāi)發(fā)一項(xiàng)新的技術(shù)應(yīng)用<Developinganewtechnicalapplicationwithinthreemonths>
第84題〔單選/1分:在下列哪一個(gè)階段項(xiàng)目發(fā)起人對(duì)項(xiàng)目的范圍、質(zhì)量、時(shí)間和成本有最大的影響力:<>
Inwhichstagetheprojectsponsorhasthegreatestinfluenceontheprojectscope,quality,time,andcost?<>
啟動(dòng)階段<Startupstage>
計(jì)劃階段<Planningstage>
實(shí)施階段<Implementationstage>
收尾階段<Closingstage>
第85題〔單選/1分:在以下哪種項(xiàng)目組織中,項(xiàng)目經(jīng)理將可能對(duì)項(xiàng)目資源進(jìn)行最嚴(yán)格的控制<>
Inwhichoneofthefollowingprojectorganizations,theprojectmanagerwillbeabletoimposethestrictestcontrolovertheprojectresources?<>
強(qiáng)矩陣組織<Strongmatrixorganization>
項(xiàng)目型組織<Project-typeorganization>
項(xiàng)目協(xié)調(diào)組織<Projectcoordinationorganization>
弱矩陣組織<Weakmatrixorganization>
第86題〔單選/1分:你認(rèn)識(shí)到了質(zhì)量控制對(duì)于你的項(xiàng)目的重要性。然而,你同時(shí)也知道質(zhì)量控制有相關(guān)的成本而項(xiàng)目的預(yù)算是有限的。一個(gè)降低質(zhì)量控制成本的方法是<>
Youhaverealizedtheimportanceofqualitycontroltoyourproject.Meanwhile,youknowthatqualitycontrolbringsaboutarelatedcost,andthattheprojectbudgetislimited.Onemethodofreducingqualitycontrolcostisto<>
使用統(tǒng)計(jì)樣本<Applystatisticssampling>
對(duì)全程進(jìn)行監(jiān)督<Monitoringthewholeprocess>
使用趨勢(shì)分析<Applythetrendanalysis>
第87題〔單選/1分:項(xiàng)目經(jīng)理要盡量參加項(xiàng)目談判的目的主要是
Theprojectmanagershouldtrytoparticipateinthenegotiationasmuchaspossiblewithaprimarypurposeasto
了解價(jià)格和付款方式<Knowaboutthepriceandmodeofpayment>
了解談判各方的承諾<Knowthecommitmentsmadebypartiestothenegotiation>
了解談判過(guò)程中發(fā)生的變化<Knowthechangesoccurredduringthenegotiation>
B和C<BandC>
第88題〔單選/1分:下列哪個(gè)因素不是進(jìn)度控制的輸入<>
Whichofthefollowingfactorsisnottheinputofschedulecontrol?<>
進(jìn)度計(jì)劃改變控制系統(tǒng)<Schedulechangecontrolsystem>
變更的要求<Changerequirement>
進(jìn)度管理計(jì)劃<Schedulemanagementplan>
執(zhí)行結(jié)果報(bào)告<Executionresultreport>
第89題〔單選/1分:為了提高效率,風(fēng)險(xiǎn)管理過(guò)程應(yīng)該:<>
Toimproveefficiency,theriskmanagementprocessshould:<>
主要應(yīng)用于概率階段和收尾階段,在實(shí)施階段和計(jì)劃階段酌量實(shí)施<Beappliedtotheprobabilityphaseandwind-upphase,anditshouldbeimplementedinlightoftherequirementintheimplementationphaseandplanphase.>
貫徹于項(xiàng)目的整個(gè)過(guò)程、系統(tǒng)分解的所有層次和項(xiàng)目組織的所有層次<Becarriedoutthroughthewholeprojectprocess,allthelayersofsystembreakdownandallthelayersofprojectorganization.>
包括聚集一部分項(xiàng)目干系人來(lái)識(shí)別風(fēng)險(xiǎn)并開(kāi)發(fā)風(fēng)險(xiǎn)略化策略<Gathersomeprojectresponsiblepersonstoidentifyriskanddevelopriskstrategies.>
側(cè)重于高級(jí)經(jīng)理認(rèn)為最為關(guān)鍵的風(fēng)險(xiǎn)<Putanemphasisontheriskthatisdeemedaskeybytheseniormanager.>
第90題〔單選/1分:項(xiàng)目小組的人員建設(shè)應(yīng)考慮:<>
Thepersonnelconstructionforaprojectteamshouldinvolve:<>
全面管理的技巧<Theskillsforcomprehensivemanagement>
項(xiàng)目計(jì)劃<Projectplan>
確定進(jìn)度表,使小組成員明確特定的工作任務(wù)及職責(zé)<Fixascheduletodefinethespecificjobsandresponsibilitiesfortheteammembers>
鼓勵(lì)機(jī)制和工作業(yè)績(jī)認(rèn)可制度<Setupanencouragementmechanismandaperformancerecognitionsystem>
第91題〔單選/1分:可交付成果是____的輸入之一Deliverableistheinputof____.
溝通規(guī)劃Communicationplanning
信息發(fā)布Informationdistributio
績(jī)效報(bào)告Performancereporting
利害關(guān)系者管理Stakeholdermanagement
第92題〔單選/1分:溝通管理計(jì)劃是____的輸入之一CommunicationManagementPlanistheinputof______.
溝通規(guī)劃Communicationplanning
信息發(fā)布Informationdistributio
績(jī)效報(bào)告Performancereporting
利害關(guān)系者管理Stakeholdermanagement
第93題〔單選/1分:要?jiǎng)?chuàng)造易于接受的溝通環(huán)境,項(xiàng)目經(jīng)理應(yīng)該:<>
Tocreateanacceptablecommunicationenvironment,theprojectmanagershould<>
確保所有的溝通都是清晰并易于理解的<Makesureallthecommunicationsareclearandeasytounderstand>
以他<她>喜歡的表達(dá)方式表達(dá)<Toexpressinhisorherway>
讓整個(gè)項(xiàng)目以往準(zhǔn)備項(xiàng)目溝通計(jì)劃<Letthewholeprojectpreparethecommunicationplan>
確保隊(duì)伍成員獲得他們工作所需要的信息<Makesuretheteammembersobtaintheinformationtheyneedfortheirwork>
第94題〔單選/1分:以下哪一條術(shù)語(yǔ)用來(lái)描述買(mǎi)方或賣(mài)方?jīng)]有執(zhí)行部分或全部的合同?<>
Whichofthefollowingtermsisusedtodescribethecontractthatthebuyerorsellerdoesnotexecutepartiallyorfully?<>
合同的結(jié)束<Contractending>
部分執(zhí)行<Partialexecution>
違約<Breachofcontract>
棄權(quán)<Waiver>
第95題〔單選/1分:假設(shè)條件、限制條件、例外情況、依賴(lài)條件應(yīng)在_______中清楚描述
Assumptions,constraints,exceptions,anddepen
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶(hù)所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶(hù)上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶(hù)上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶(hù)因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025年度專(zhuān)業(yè)技術(shù)人才“師帶徒”培養(yǎng)合同3篇
- 2025年度個(gè)人房產(chǎn)抵押權(quán)抵押權(quán)登記服務(wù)合同8篇
- 2025年度虛擬現(xiàn)實(shí)教育培訓(xùn)平臺(tái)開(kāi)發(fā)與運(yùn)營(yíng)合同范本4篇
- 2025年無(wú)財(cái)產(chǎn)離婚協(xié)議書(shū)范本:財(cái)產(chǎn)分配與子女撫養(yǎng)權(quán)益保障協(xié)議9篇
- 2025年水泥磚行業(yè)節(jié)能減排技術(shù)改造合同6篇
- 2025年浙江紹興諸暨市郵政分公司招聘筆試參考題庫(kù)含答案解析
- 二零二五版出租車(chē)夜間運(yùn)營(yíng)特許經(jīng)營(yíng)合同2篇
- 2025年長(zhǎng)沙穗城軌道交通有限公司招聘筆試參考題庫(kù)含答案解析
- 2025年廣東深圳市龍崗區(qū)城投集團(tuán)招聘筆試參考題庫(kù)含答案解析
- 2025年武漢金中石化工程有限公司招聘筆試參考題庫(kù)含答案解析
- GB/T 37238-2018篡改(污損)文件鑒定技術(shù)規(guī)范
- 普通高中地理課程標(biāo)準(zhǔn)簡(jiǎn)介(湘教版)
- 河道治理工程監(jiān)理通知單、回復(fù)單范本
- 超分子化學(xué)簡(jiǎn)介課件
- 高二下學(xué)期英語(yǔ)閱讀提升練習(xí)(一)
- 易制爆化學(xué)品合法用途說(shuō)明
- 【PPT】壓力性損傷預(yù)防敷料選擇和剪裁技巧
- 大氣喜慶迎新元旦晚會(huì)PPT背景
- DB13(J)∕T 242-2019 鋼絲網(wǎng)架復(fù)合保溫板應(yīng)用技術(shù)規(guī)程
- 心電圖中的pan-tompkins算法介紹
- 羊絨性能對(duì)織物起球的影響