文檔簡(jiǎn)介
目錄
目錄............................................................................-1-
第一章工程概況..................................................................-1-
1.1工程概況..................................................................-1-
1.2道路工程.................................................................-1-
1.3車(chē)站工程.................................................................-3-
1.4橋梁工程.................................................................-3-
1.5場(chǎng)站工程.................................................................-3-
1.6工程施工總目標(biāo)..........................................................-4-
第二章管理組織、機(jī)構(gòu)體系.......................................................-5-
2.1施工管理組織機(jī)構(gòu).......................................................-5-
2.2項(xiàng)目部管理人員的職責(zé)分工..............................................-6-
2.2.1項(xiàng)目經(jīng)理.........................................................-6-
2.2.2項(xiàng)目副經(jīng)理.......................................................-7-
2.2.3技術(shù)負(fù)責(zé)人.......................................................-7-
2.2.4施工員崗位職責(zé)..................................................-8-
2.2.5質(zhì)檢人員崗位職責(zé)................................................-8-
2.2.6安全人員崗位職責(zé)................................................-9-
2.2.7材料人員職責(zé)....................................................-9-
2.2.8測(cè)量人員.........................................................-9-
2.2.9造價(jià)人員........................................................-10-
2.3施工組織機(jī)構(gòu)有效運(yùn)轉(zhuǎn)的保證措施......................................-10-
2.4項(xiàng)目經(jīng)理常駐現(xiàn)場(chǎng)的保證措施..........................................-11-
第三章主要施工方法.............................................................-11-
3.1測(cè)量工程...............................................................-12-
3.1.1測(cè)量技術(shù)管理...................................................-12-
3.1.2主控制網(wǎng)的復(fù)測(cè)及加密控制網(wǎng)的建立............................-12-
3.3路基施工................................................................-13-
3.3.1路基測(cè)量放樣...................................................-13-
3.3.2不良土壤開(kāi)挖施工...............................................-14-
3.3.3路基開(kāi)挖施工方法...............................................-14-
3.3.4余土外運(yùn)方案...................................................-15-
3.3.5路基填筑施工方案...............................................-15-
3.3.6路床碾壓整平...................................................-18-
3.3.7路基施工工藝框圖...............................................-19-
3.4砂礫石墊層施工........................................................-20-
3.4.1材料要求........................................................-21-
3.4.2施工工藝........................................................-21-
3.5瀝青碎石施工............................................................-22-
3.5.1施工工藝流程...................................................-22-
3.5.2操作工藝........................................................-22-
3.6瀝青混凝土路面施工...................................................-24-
3.6.1鋪筑試驗(yàn)段.......................................................-24-
3.6.2施工準(zhǔn)備.........................................................-24-
3.6.3瀝青混凝土路面面層施工工藝..................................-25-
3.7BRT站臺(tái)施工........................................................-31-
3.7.1地基與基礎(chǔ)....................................................-31-
3.7.2主體鋼構(gòu)......................................................-32-
3.7.3主體鋼構(gòu)涂裝施工.............................................-34-
3.7.4玻瑞隔斷施工..................................................-37-
3.7.5墻面及頂棚彩板安裝...........................................-37-
3.8人行天橋施工.........................................................-38-
3.8.1工藝流程......................................................-38-
3.8.2鉆孔灌注樁基礎(chǔ)施工...........................................-38-
3.8.3墩、臺(tái)的施工..................................................-44-
3.8.4鋼管柱安裝....................................................-44-
3.8.5鋼箱梁及樓梯梯道梁拼裝.......................................-45-
3.8.6橋面鋪裝和欄桿安裝...........................................-45-
3.9人行道施工.........................................................-45-
3.9.1工序流程.....................................................-45-
3.9.2施工方法.....................................................-45-
3.10路側(cè)排水溝施工.....................................................-46-
3.10.1施工放樣.....................................................-46-
3.10.2鋼筋混凝土排水溝施工方法...................................-46-
3.11車(chē)輛隔離帶施工.....................................................-48-
3.11.1主要施工方案.................................................-48-
3.11.2施工注意事項(xiàng).................................................-50-
3.12側(cè)石施工............................................................-50-
3.12.1施工程序.....................................................-50-
3.12.2側(cè)石質(zhì)量通病的防治..........................................-51-
3.13綠化工程施工.......................................................-51-
3.14道路標(biāo)志、標(biāo)志線施工..............................................~54-
3.14.1標(biāo)志牌等交通設(shè)施施工........................................-54-
3.14.2交通標(biāo)線施工.................................................-55-
3.15照明工程施工.......................................................-56-
3.15.1路燈施工.....................................................-56-
3.15.2電纜檢查井施工..............................................-59-
3.16停車(chē)場(chǎng)及樞紐站工程...............................................-59-
3.16.1土方工程....................................................-59-
3.16.2鋼筋工程....................................................-60-
3.16.3模板工程....................................................-62-
3.16.4混凝土工程..................................................-63-
第四章擬投入的主要物資計(jì)劃................................................-64-
4.1擬投入主要物資計(jì)劃.................................................-65-
4.2材料計(jì)劃進(jìn)場(chǎng)原則...................................................~65-
4.3工程擬投入的主要材料計(jì)劃..........................................-66-
4.4主要材料投入保證措施..............................................~66-
4.4.1材料供應(yīng)保證措施.............................................-66-
4.4.2材料儲(chǔ)備計(jì)劃..................................................-67-
4.4.3各種資源的組織協(xié)調(diào)...........................................-67-
4.4.4材料的質(zhì)量保證措施...........................................-68-
第五章擬投入的主要施工機(jī)械、設(shè)備計(jì)劃......................................-69-
5.1機(jī)械設(shè)備的投入計(jì)劃..................................................-70-
5.2機(jī)械設(shè)備的使用制度..................................................-70-
5.3機(jī)械設(shè)備的正確操作..................................................~71-
5.4機(jī)械設(shè)備的檢查......................................................-71-
5.5機(jī)械的運(yùn)轉(zhuǎn)和交接記錄................................................-71-
5.6機(jī)械設(shè)備的保養(yǎng)......................................................-71-
5.7投入機(jī)械與施工設(shè)備清單.............................................-72-
第六章勞動(dòng)力安排計(jì)劃......................................................-72-
6.1勞動(dòng)力投入的保證措施................................................~73-
6.2勞動(dòng)力投入計(jì)劃......................................................-73-
第七章確保工程質(zhì)量的技術(shù)組織措施.........................................-73-
7.1質(zhì)量標(biāo)準(zhǔn)與承諾......................................................-74-
7.2工程質(zhì)量保證體系....................................................-74-
7.2.1施工質(zhì)量保證體系.............................................-74-
7.2.2施工質(zhì)量體系控制.............................................~75-
7.3工程質(zhì)量保證的技術(shù)措施.............................................-78-
7.3.1建立質(zhì)量檢測(cè)系統(tǒng)............................................-78-
7.3.2質(zhì)量保證的其它技術(shù)措施.....................................-78-
7.4施工進(jìn)度的質(zhì)量控制.................................................-80-
7.5分部分項(xiàng)工程質(zhì)量的控制措施........................................-80-
7.5.1測(cè)量工程質(zhì)量保證措施.......................................-80-
7.5.2為確保質(zhì)量所采取的檢測(cè)試臉措施............................~81-
7.5.3瀝青混凝土的質(zhì)量控制........................................-81-
7.5.4鋼筋工程質(zhì)量控制............................................~84-
7.5.5混凝土工程質(zhì)量控制...........................................-85-
第八章確保安全生產(chǎn)的技術(shù)組織措施.........................................-86-
8.1安全生產(chǎn)承諾.......................................................~87-
8.2安全生產(chǎn)保證體系及安全生產(chǎn)保證體系框圖............................-87-
8.3組織保障措施........................................................-88-
8.4現(xiàn)場(chǎng)管理安全措施....................................................-89-
8.5機(jī)電安全.............................................................-89-
8.6消防系統(tǒng)安全措施....................................................-90-
8.7安全保衛(wèi)措施.........................................................-90-
8.8施工安全措施.......................................................-90-
8.8.1BRT站臺(tái)施工安全措施.........................................-90-
8.8.2深溝槽施工安全措施..........................................-91-
第九章確保工期的技術(shù)組織措施.............................................-91-
9.1工期目標(biāo)............................................................-92-
9.2工程進(jìn)度計(jì)劃.......................................................-92-
9.2.1施工現(xiàn)場(chǎng)準(zhǔn)備工作計(jì)劃.........................................-92-
9.2.2物資準(zhǔn)備工作計(jì)劃.............................................-92-
9.2.3施工技術(shù)準(zhǔn)備工作計(jì)劃.........................................-92-
9.2.4其它施工準(zhǔn)備工作計(jì)劃.........................................-93-
9.3施工組織協(xié)調(diào)........................................................-93-
9.4施工網(wǎng)絡(luò)圖..........................................................-94-
9.5施工階段劃分........................................................-94-
9.6進(jìn)度計(jì)劃的保證措施...............................................~95-
9.6.1工程進(jìn)度的監(jiān)控................................................-95-
9.6.2解決進(jìn)度拖延的措施............................................-95-
9.6.3加強(qiáng)雨期施工措施確保工程進(jìn)度.................................-96-
9.7確保工程進(jìn)度的管理體系..............................................-96-
9.8工程進(jìn)度保證的組織措施..............................................-97-
9.9保證工程進(jìn)度的主要技術(shù)措施..........................................-97-
9.10確保工程進(jìn)度的設(shè)備管理措施.........................................-98-
9.11經(jīng)濟(jì)與信息管理措施..................................................-98-
9.12配合措施.............................................................-98-
9.13實(shí)施工期計(jì)劃過(guò)程控制措施...........................................-99-
9.14克服環(huán)境及氣候?qū)て谟绊懙拇胧?...................................-99-
第十章確保文明施工的技術(shù)組織措施........................................-100-
10.1文明施工目標(biāo).....................................................-101-
10.2文明施工措施.....................................................-101-
10.2.1健全管理機(jī)構(gòu),完善管理體系................................-101-
10.2.2文明施工組織措施...........................................-101-
10.2.3現(xiàn)場(chǎng)管理規(guī)范化.............................................-102-
10.2.4現(xiàn)場(chǎng)環(huán)境衛(wèi)生保證措施.......................................-104-
10.2.5防噪音保證措施.............................................-104-
10.2.6現(xiàn)場(chǎng)維護(hù)措施................................................-104-
10.3環(huán)境保護(hù)措施.....................................................-105-
第十一章工程施工重點(diǎn)和難點(diǎn)及保證措施...................................~107-
11.1人員、材料、機(jī)械大量投入........................................-108-
11.2工程交通封閉與導(dǎo)行方案..........................................-110-
11.2.1道路封閉方案................................................-110-
11.2.2交通導(dǎo)行方案..............................................-110-
11.2.3交通封閉與導(dǎo)行保證措施...................................-110-
11.3文明施工和環(huán)境保護(hù)措施..........................................-111-
11.4對(duì)已有設(shè)施、管線的加固、保護(hù)措施...............................-114-
11.5雨期施工措施.....................................................-114-
11.6土石方回填及不良土質(zhì)換填等處理措施............................-116-
11.7土方運(yùn)輸?shù)墓芾?..................................................-117-
第十二章施工總平面布置圖..................................................-118-
12.1現(xiàn)場(chǎng)布置原則與標(biāo)化管理要求.......................................-119-
12.1.1布置原則:................................................-119-
12.1.2標(biāo)化管理:科學(xué)規(guī)范、衛(wèi)生整潔............................-119-
12.2平面布置概述......................................................-119-
12.3施工現(xiàn)場(chǎng)用電平面布置.............................................-119-
12.3.1用電線路布置................................................-119-
12.3.2安全技術(shù)措施................................................-120-
12.4現(xiàn)場(chǎng)施工用水平面布置.............................................-120-
12.5現(xiàn)場(chǎng)生產(chǎn)、生活設(shè)施................................................-120-
12.5.1生活設(shè)施設(shè)置................................................-120-
12.5.2生產(chǎn)設(shè)施....................................................-121-
12.6施工現(xiàn)場(chǎng)排水、消防平面布置.......................................-121-
附表一:擬投入本項(xiàng)目的主要施工設(shè)備表......................................-121-
附表二:勞動(dòng)力計(jì)劃表.......................................................-124-
附表三:進(jìn)度計(jì)劃............................................................-125-
附表四:施工總平面圖.......................................................-126-
第一章工程概況
1.1工程概況
本工程名稱(chēng)為DOUALA市BRT工程施工項(xiàng)目,項(xiàng)目共計(jì)三個(gè)標(biāo)段,總長(zhǎng)約34.5
公里。其中第一■標(biāo)段從CarrefourDouanes為起點(diǎn)至CarrefourNdokoti,然后
沿線至Carrefour-MandeIa,共計(jì)10.5km。項(xiàng)目含道路工程、車(chē)站工程、橋
梁工程、場(chǎng)站工程等內(nèi)容。
1.2道路工程
1、一標(biāo)段全線有條件路段按照雙向6車(chē)道進(jìn)行拓寬,其中BRT專(zhuān)用車(chē)道2
根車(chē)道,社會(huì)車(chē)道4根車(chē)道,同時(shí)設(shè)置路中島式車(chē)站,設(shè)站處道路相應(yīng)拓寬改造,
紅線除天橋設(shè)置處基本按照業(yè)主提供的拆遷范圍線控制。工程內(nèi)容涉及破除舊機(jī)
動(dòng)車(chē)道、舊人行道、舊排水溝;拆除路燈、電線桿;不良土壤置換、路基土方挖
填、遷移供水管;破損路面修復(fù)、新建機(jī)動(dòng)車(chē)道、人行道、排水溝、舊路面銃刨
加罩。
(1)破除舊機(jī)動(dòng)車(chē)道、舊人行道、舊排水溝:全線道路拓寬兩側(cè)有房屋,
拓寬部分按照破除舊機(jī)動(dòng)車(chē)道考慮。部分路段拆除中分帶綠化改建為機(jī)動(dòng)車(chē)道或
站臺(tái),破除部分按照破除舊機(jī)動(dòng)車(chē)道考慮。
(2)路燈、電線桿拆除。
(3)不良土質(zhì)置換:全線道路拓寬,涉及不良土質(zhì)路段的換填等。
(4)路基土方挖填、整理:全線道路拓寬,涉及的路基土方挖填等。
(5)遷移供水管
(6)部分路段破損路面修復(fù),以業(yè)主提供標(biāo)段1的里程樁
(Pk1+526-Pk3+686;Pk0+000-Pk2+754;Pk3+686-Pk6+230:)范圍為依據(jù),
對(duì)破損路面進(jìn)行修復(fù)。
(7)新建機(jī)動(dòng)車(chē)道:該項(xiàng)包含全線道路拓寬所涉及的工程數(shù)量
路面結(jié)構(gòu)改造方案:采用當(dāng)?shù)亓?xí)慣工程做法,方案如下:機(jī)動(dòng)車(chē)道(5cm瀝
青混凝土+15cm瀝青碎石+20cm砂礫石墊層),人行道(15cm現(xiàn)澆鋼筋混凝土板
+15cm瀝青碎石墊層)。配合的機(jī)械設(shè)備有:裝載機(jī)(ZL50)、振動(dòng)壓路機(jī)(18-25T)、
膠輪壓路機(jī)(14-28T)、瀝青攤鋪機(jī)、水穩(wěn)攤鋪機(jī)、平地機(jī)及灑水車(chē)。
道路橫斷面設(shè)計(jì)形式:普通路段(有中央分隔帶)道路橫斷面設(shè)計(jì):3.25m
(人行道)+10.75m(機(jī)動(dòng)車(chē)道)+2m(中分帶)+10.75m(機(jī)動(dòng)車(chē)道)+3.25m(人
行道)=30m,BRT與社會(huì)車(chē)輛采用硬隔離。
普通路段(無(wú)中央分隔帶)道路橫斷面設(shè)計(jì):3.25m(人行道)+10.75m(機(jī)
動(dòng)車(chē)道)+10.75m(機(jī)動(dòng)車(chē)道)+3.25m(人行道)=28m,,BRT與社會(huì)車(chē)輛采用
硬隔離。
28.00
14.00>14,00
'0.500.25
,3.25J).25+3.25x2+0.5+,5=10.753.50心3.2513.25JL3.25
/3777771
部分困難路段可取消中間隔離帶,斷面設(shè)計(jì)為2.8m(人行道)+10.2m(機(jī)
動(dòng)車(chē)道)+10.2m(機(jī)動(dòng)車(chē)道)+2.8m(人行道)=26m。
2、部分路段破損路面修復(fù),以業(yè)主提供標(biāo)段1的里程樁(Pk1+526-Pk3+686;
Pk0+000-Pk2+754;Pk3+686-Pk6+230;)范圍為依據(jù),對(duì)破損路面進(jìn)行修復(fù)。
3、舊路面錢(qián)刨加罩:路面錢(qián)刨機(jī)銃刨瀝青路面厚(1-5cm)o
4、全線設(shè)置隔離設(shè)施(隔離墩),分隔BRT專(zhuān)用車(chē)道與社會(huì)車(chē)道。
5、全線設(shè)置人行道及排水溝,涉及新建人行道、新建路緣石、破除舊人行
道,新建排水溝及蓋板、拆除舊排水溝等工程數(shù)量。
(1)新建人行道:包含全線設(shè)置路側(cè)人行道,人行道寬度包含2米凈寬人
行通道以及0.8米至1.25米的設(shè)施帶。
(2)新建路緣石:路緣石的高度;包含全線道路拓寬所涉及的工程數(shù)量。
(3)拆除人行道:包含全線道路拓寬所涉及的工程數(shù)量。
(4)新建排水溝:包含全線設(shè)置路側(cè)排水溝。(排水溝尺寸及結(jié)構(gòu)暫按
80cm*80cm矩形漿砌片石排水溝計(jì)算工程數(shù)量)。不包含市政排水溝道改造數(shù)量。
(5)拆除舊排水溝:包含全線道路拓寬所涉及的工程數(shù)量。
5、部分路段保留原有道路中央隔離帶及路燈等設(shè)施,重新布置綠化。
6.交通信號(hào)燈
1.3車(chē)站工程
第一標(biāo)段共含14組整島式站臺(tái)中途站,標(biāo)準(zhǔn)BRT站臺(tái)4*60(不含進(jìn)站緩沖
區(qū))??紤]滿(mǎn)足雙向各2輛12米及以下BRT車(chē)輛停靠需求,中途站主要建設(shè)內(nèi)
容和規(guī)模為BRT站臺(tái)及其附屬工程,涉及建筑、結(jié)構(gòu)、消防工程、站臺(tái)地坪、電
氣照明防雷、標(biāo)識(shí)系統(tǒng)、維護(hù)欄桿、固定座椅等方面內(nèi)容。
基礎(chǔ)15cm厚鋼筋混凝土地面;結(jié)構(gòu)為鋼結(jié)構(gòu),包括:鋼柱、鋼網(wǎng)架、鋼屋
面等;圍護(hù)采用全玻璃隔斷。
1.4橋梁工程
本工程擬建3座人行過(guò)街天橋。對(duì)于現(xiàn)狀橋梁及下穿鐵路通道,原則上利用
現(xiàn)有結(jié)構(gòu)寬度,按照快速公交車(chē)道設(shè)置的要求,在現(xiàn)有橋梁寬度的范圍內(nèi),僅改
造橋梁的路面鋪裝,進(jìn)行車(chē)道劃分。
新建過(guò)街天橋主橋橫跨道路,橋?qū)?.3m(主橋:0.15(欄桿)+3.0(人行道)
+0.15(欄桿)=3.3m),上部采用鋼箱梁,下部結(jié)構(gòu)立柱采用鋼管柱,樁基礎(chǔ)采
用鉆孔灌注樁,不考慮自動(dòng)扶梯和無(wú)障礙設(shè)施。
1.5場(chǎng)站工程
場(chǎng)站工程包括12000平方米用地的停車(chē)場(chǎng)工程,停車(chē)場(chǎng)內(nèi)考慮一處調(diào)度中
心,以及兩處各2500平方米的換乘樞紐工程。
Douanes停車(chē)場(chǎng)主要功能為BRT首末站及BRT停車(chē)場(chǎng),主要建筑為維修工間、
洗車(chē)控制室、加油站、垃圾房、調(diào)度候車(chē)等。工程內(nèi)容包含各建筑單體的建筑、
結(jié)構(gòu)、強(qiáng)弱電、給排水、暖通等方面內(nèi)容以及場(chǎng)地道路地坪、綠化、圍墻、伸縮
大門(mén)道閘、場(chǎng)地給排水、場(chǎng)地電氣、場(chǎng)地安防、標(biāo)志標(biāo)線等內(nèi)容。
總建筑面積2474rrf,其中:維修車(chē)間880rrf,洗車(chē)控制室60m)垃圾房
20調(diào)度及候車(chē)室1100rrf,加油站用房190m)門(mén)衛(wèi)24m)摩托車(chē)停車(chē)200
m!o
基礎(chǔ)為獨(dú)立基礎(chǔ)及磚基礎(chǔ),框架結(jié)構(gòu),多孔磚填充墻,墻面頂棚砂漿抹灰,
SBS防水。
2個(gè)樞紐換乘站,每個(gè)樞紐站按照1條BRT線路、2條普通公交線路??吭O(shè)
計(jì),主要建筑為BRT管理用房、常規(guī)公交調(diào)度、變配電間、BRT候車(chē)?yán)?、常?guī)公
交候車(chē)?yán)?、垃圾房等。工程?nèi)容包含各建筑單體的建筑、結(jié)構(gòu)、強(qiáng)弱電、給排水、
暖通等方面內(nèi)容以及場(chǎng)地道路地坪、綠化、圍墻、伸縮大門(mén)道閘、場(chǎng)地給排水、
場(chǎng)地電氣、場(chǎng)地安防、標(biāo)志標(biāo)線等內(nèi)容。
總建筑面積1110其中:BRT管理用房200m)常規(guī)公交調(diào)度120m)
變配電間200m。,BRT候車(chē)?yán)?20m)常規(guī)公交候車(chē)?yán)?50m)垃圾房20m%
基礎(chǔ)為獨(dú)立基礎(chǔ)及磚基礎(chǔ),框架結(jié)構(gòu),多孔磚填充墻,墻面頂棚砂漿抹灰,
SBS防水。
1.6工程施工總目標(biāo)
1、工期目標(biāo):11個(gè)月。
2、質(zhì)量目標(biāo):合格。
3、安全、文明施工目標(biāo):確保安全文明施工,符合喀麥隆現(xiàn)行相關(guān)規(guī)定及
杜阿拉市有關(guān)規(guī)定,達(dá)到安全文明標(biāo)準(zhǔn),各項(xiàng)措施周全、具體、有效,實(shí)現(xiàn)現(xiàn)場(chǎng)
文明施工目標(biāo)的承諾。
4、履約:嚴(yán)格履行招標(biāo)文件和中標(biāo)后所簽訂合同的有關(guān)條款,確保工程工
期、質(zhì)量、安全、文明施工目標(biāo)實(shí)現(xiàn)。
第二章管理組織、機(jī)構(gòu)體系
2.1施工管理組織機(jī)構(gòu)
1、我公司將針對(duì)工程嚴(yán)格實(shí)行項(xiàng)目施工,對(duì)施工項(xiàng)目進(jìn)行統(tǒng)籌安排、精心
組織、成立精干高效的直屬項(xiàng)目部,在公司總部的直接領(lǐng)導(dǎo)下做到分工明確、職
責(zé)到人,形成管理一體化的施工力量,使施工做到優(yōu)質(zhì)、快速、高效。
2、針對(duì)杜阿拉BRT項(xiàng)目的工程特點(diǎn),工程量大,工期緊,我公司將研究決
定將整體線路劃分為3個(gè)施工段同時(shí)施工。
第一段:K0-K3+550,該段線路主要道路為雙向4車(chē)道,位置是城市最繁華
的區(qū)域,人流量和車(chē)流量巨大,作業(yè)施工面非常小。該段主要包含3.55km左右
的道路擴(kuò)建,7km排水溝新建,一個(gè)停車(chē)場(chǎng)和6座公交站,本段應(yīng)為施工時(shí)間最
長(zhǎng)和難度最大的區(qū)域。
第二段:K3+550-K6+800,本段線路較為寬闊,沿街主要為企業(yè)工廠,現(xiàn)有
部分道路是雙向6車(chē)道布置,在換乘樞紐CarrefourNdokoti的位置有200余米
的農(nóng)貿(mào)市場(chǎng)段,該路段正常情況施工車(chē)輛根本無(wú)法通行,同時(shí)魚(yú)龍混雜。本段主
要施工對(duì)象為3.3km左右路面改建,6.6公里排水溝新建,2座人行天橋,4座
公交站臺(tái),1換乘樞紐站。
第三段:K6+800-終點(diǎn)站,該段路線有兩座橋梁,如果需要拓寬道路,該段
土方工程較多。本段主要施工內(nèi)容為3.7km道路改建,1座人行天橋,4座公交
車(chē)站,1座換乘樞紐站。
3、針對(duì)該項(xiàng)目我公司將選擇一名優(yōu)秀的項(xiàng)目經(jīng)理具體負(fù)責(zé)此工程的施工管
理工作,三名施工負(fù)責(zé)人針對(duì)不同施工段具體管理施工,同時(shí)選擇一名經(jīng)驗(yàn)豐富、
技術(shù)能力過(guò)硬,個(gè)人素質(zhì)高的技術(shù)負(fù)責(zé)人配合。各施工段施工管理人員在項(xiàng)目經(jīng)
理的指導(dǎo)下做到有計(jì)劃的組織施工,確保工程質(zhì)量、工期、安全等方面達(dá)到目標(biāo)
要求。
5、項(xiàng)目組織機(jī)構(gòu)圖如下:
項(xiàng)目組織機(jī)構(gòu)圖
施
項(xiàng)目主管
工
總
承技術(shù)負(fù)責(zé)人
包
總
部
質(zhì)
安
財(cái)
物
合
工
保
務(wù)
全
資
量
約
程
障
部
生
部
設(shè)
管
技
層
產(chǎn)
備
術(shù)
理
部
部
部
部
施
項(xiàng)目經(jīng)理—>技術(shù)負(fù)責(zé)人
工
總
承
施工段I負(fù)責(zé)人施工段2負(fù)責(zé)人施工段3負(fù)責(zé)人
包
現(xiàn)
場(chǎng)
管
理
質(zhì)
質(zhì)
造
造
測(cè)
質(zhì)
測(cè)
造
質(zhì)
測(cè)
造
測(cè)
檢
檢
價(jià)
價(jià)
量
檢
量
價(jià)
檢
量
價(jià)
量
層
員
員
員
員
員
員
員
員
員
員
員
員
工
作
各專(zhuān)業(yè)施工隊(duì)伍
業(yè)
層
2.2項(xiàng)目部管理人員的職責(zé)分工
2.2.1項(xiàng)目經(jīng)理
1、按照合同條款,全面具體地組織工程項(xiàng)目的施工,滿(mǎn)足業(yè)主的合同要求。
2、制定項(xiàng)目管理總目標(biāo),建立完整的總項(xiàng)目管理體系,保證既定目標(biāo)的實(shí)
現(xiàn)。
3、組建精干高效的項(xiàng)目管理班子,搞好項(xiàng)目機(jī)構(gòu)的設(shè)置、人員選調(diào)及職責(zé)
分工。
4、建立嚴(yán)格的經(jīng)濟(jì)責(zé)任制、強(qiáng)化管理、推動(dòng)科技進(jìn)步,搞好成本控制,提
高綜合經(jīng)濟(jì)效益。
5、溝通項(xiàng)目?jī)?nèi)外聯(lián)系渠道,及時(shí)妥善處理好內(nèi)外關(guān)系。
6、接受建設(shè)單位、監(jiān)理單位及上級(jí)主管部門(mén)的監(jiān)督指導(dǎo)。
7、負(fù)責(zé)整個(gè)施工項(xiàng)目的環(huán)境保護(hù)、文明施工、綜合治理等監(jiān)督管理工作,
嚴(yán)格執(zhí)行杜阿拉市建筑施工管理方面的有關(guān)規(guī)章制度。
2.2.2項(xiàng)目副經(jīng)理
1、按照合同內(nèi)容,全面負(fù)責(zé)本施工段工程項(xiàng)目的施工,服務(wù)于項(xiàng)目經(jīng)理,
滿(mǎn)足業(yè)主的合同要求。
2、制定本施工段的項(xiàng)目管理目標(biāo),建立本施工段完整的項(xiàng)目管理體系,保
證既定目標(biāo)的實(shí)現(xiàn)。
4、建立本施工段嚴(yán)格的經(jīng)濟(jì)責(zé)任制、強(qiáng)化管理、推動(dòng)科技進(jìn)步,搞好成本
控制,提高綜合經(jīng)濟(jì)效益。
5、加強(qiáng)與其他施工段的溝通,促進(jìn)項(xiàng)目?jī)?nèi)聯(lián)系渠道,及時(shí)妥善處理好項(xiàng)目
內(nèi)和本施工段內(nèi)的各工作關(guān)系。
6、接受建設(shè)單位、監(jiān)理單位及上級(jí)主管部門(mén)的監(jiān)督指導(dǎo)。
7、負(fù)責(zé)本施工段施工現(xiàn)場(chǎng)的環(huán)境保護(hù)、文明施工、綜合治理等工作,嚴(yán)格
執(zhí)行杜阿拉市建筑施工管理方面的有關(guān)規(guī)章制度。
2.2.3技術(shù)負(fù)責(zé)人
1、對(duì)工程項(xiàng)目質(zhì)量負(fù)責(zé)。
2、抓好工程技術(shù)管理,建設(shè)完善的技術(shù)管理制度,確保工程質(zhì)量。
3、建立工程技術(shù)責(zé)任制:明確項(xiàng)目部各職能部的主要職責(zé),使其在各自負(fù)
責(zé)的范圍內(nèi),做好經(jīng)常性的技術(shù)業(yè)務(wù)工作,深入施工現(xiàn)場(chǎng)調(diào)查研究,總結(jié)和推廣
先進(jìn)的施工工藝、施工方法,貫徹執(zhí)行有關(guān)技術(shù)規(guī)范、標(biāo)準(zhǔn)與規(guī)程。
4、建立圖紙審查制度:在工程開(kāi)工前,組織各有關(guān)技術(shù)人員進(jìn)行圖紙會(huì)審,
檢查設(shè)計(jì)圖紙的符合性、準(zhǔn)確性等,并將圖紙會(huì)審發(fā)現(xiàn)的問(wèn)題形成記錄,交由監(jiān)
理、設(shè)計(jì)部門(mén)解答。
5、建立三級(jí)技術(shù)交底制度:通過(guò)圖紙會(huì)審,在問(wèn)題及疑問(wèn)得到明確解答后,
由技術(shù)負(fù)責(zé)人向施工
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶(hù)所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶(hù)上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶(hù)上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶(hù)因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 湖北省武漢市華一卓越聯(lián)盟2024-2025學(xué)年上學(xué)期12月九年級(jí)物理試題(含答案)
- 景觀造景標(biāo)示牌施工方案
- 樂(lè)器購(gòu)銷(xiāo)合同
- 藝術(shù)美術(shù)鑒賞能力測(cè)試卷及答案解析
- 淋浴間地磚鋪貼施工方案
- 活動(dòng)安排表格-季度工作計(jì)劃
- 2025年考勤管理面試試題及答案
- 居室空間設(shè)計(jì) 任務(wù)單和評(píng)價(jià)反饋 項(xiàng)目二 網(wǎng)絡(luò)資源
- KTB1016-CheKine ATP 含量檢測(cè)試劑盒在糖尿病胰島 β 細(xì)胞功能研究中的應(yīng)用
- 二年級(jí)下冊(cè)語(yǔ)文部編版《大象的耳朵第二課時(shí)》導(dǎo)學(xué)案學(xué)案
- 西北四省(陜西山西青海寧夏)2025屆高三下學(xué)期第一次聯(lián)考生物試題含答案
- 第五章產(chǎn)前檢查及高危妊娠監(jiān)測(cè)90課件
- 專(zhuān)利共有合同范例
- 2025年上半年山西交控集團(tuán)所屬路橋集團(tuán)交投集團(tuán)招聘800人易考易錯(cuò)模擬試題(共500題)試卷后附參考答案
- 同等學(xué)力申碩-H001356法學(xué)學(xué)科綜合知識(shí)考點(diǎn)匯編
- 外周靜脈血管解剖知識(shí)
- 《基于舞弊風(fēng)險(xiǎn)因子的輝山乳業(yè)公司財(cái)務(wù)舞弊案例探析》15000字(論文)
- 《教育強(qiáng)國(guó)建設(shè)規(guī)劃綱要(2024-2035年)》解讀與培訓(xùn)
- 2024年03月中國(guó)工商銀行湖南分行2024年度春季校園招考筆試歷年參考題庫(kù)附帶答案詳解
- 2025年青島市技師學(xué)院招考聘用48人高頻重點(diǎn)提升(共500題)附帶答案詳解
評(píng)論
0/150
提交評(píng)論