文檔簡(jiǎn)介
目錄
第一章、編制說(shuō)明及依據(jù)........................................................9
1.1編制說(shuō)明.................................................................9
1.2編制依據(jù).................................................................9
1.2.1工程建設(shè)的有關(guān)文件..................................................9
1.2.2國(guó)家有關(guān)法律法規(guī)....................................................10
1.2.3工程施工規(guī)范、規(guī)程、標(biāo)準(zhǔn)、圖集等....................................10
1.2.3企業(yè)相關(guān)管理文件....................................................12
第二章、工程概況.............................................................13
2.1工程簡(jiǎn)介................................................................13
2.2工作內(nèi)容和施工范圍......................................................13
2.3主要施工項(xiàng)目............................................................13
2.4工程施工難點(diǎn)、施工關(guān)鍵點(diǎn)分析............................................14
2.4.1本項(xiàng)目施工特點(diǎn)難點(diǎn)分析.............................................14
2.4.2“夜間施工”難點(diǎn)的應(yīng)對(duì)措施...........................................15
2.4.3“垂直運(yùn)輸”難點(diǎn)的應(yīng)對(duì)措施...........................................15
2.4.4“工期較短”難點(diǎn)的應(yīng)對(duì)措施...........................................16
2.4.5"安全文明施工”難點(diǎn)的應(yīng)對(duì)措施.......................................17
2.4.6“成品保護(hù)”難點(diǎn)的應(yīng)對(duì)措施...........................................17
2.4.7"防火要求高”的應(yīng)對(duì)措施”..........................................20
2.4.8“部分設(shè)備利舊”的保障措施”........................................21
2.5現(xiàn)場(chǎng)和周圍環(huán)境.........................................................21
第三章、施工管理目標(biāo).........................................................22
3.1工程質(zhì)量管理目標(biāo).......................................................22
3.2工期目標(biāo)...............................................................22
3.3安全管理目標(biāo)...........................................................22
3.4環(huán)境保護(hù)目標(biāo)............................................................22
3.5現(xiàn)場(chǎng)文明施工目標(biāo)........................................................22
3.6服務(wù)目標(biāo)................................................................22
第四章、施工部署.............................................................23
4.1施工總體部署原則........................................................23
4.2施工項(xiàng)目組織機(jī)構(gòu)設(shè)置....................................................23
4.2.1組織機(jī)構(gòu)設(shè)置........................................................23
4.2.2項(xiàng)目經(jīng)理部組織機(jī)構(gòu)設(shè)置..............................................24
4.2.3項(xiàng)目部各管理部門職責(zé)................................................25
4.3進(jìn)場(chǎng)前的部署............................................................33
4.3.1材料計(jì)劃安排........................................................33
4.3.2制定施工進(jìn)度計(jì)劃....................................................33
4.3.3工地現(xiàn)場(chǎng)勘察........................................................33
4.3.4各類計(jì)劃及資料編制..................................................34
4.3.5施工手續(xù)辦理........................................................34
4.4施工部署................................................................35
4.4.1施工部署原則........................................................35
4.4.2施工順序部署原則....................................................36
4.4.3施工總體安排.......................................................36
4.4.4施工區(qū)段及流水段劃分................................................38
第五章、施工準(zhǔn)備.............................................................39
5.1現(xiàn)場(chǎng)準(zhǔn)備................................................................39
5.2技術(shù)準(zhǔn)備..............................................................39
5.2.1圖紙會(huì)審...........................................................39
5.2.2施工組織設(shè)計(jì)的編制.................................................39
5.2.3試驗(yàn)機(jī)構(gòu)的建立.....................................................40
5.2.4施工方案編制計(jì)劃...................................................40
5.3物資準(zhǔn)備...............................................................41
5.4勞動(dòng)力準(zhǔn)備.............................................................42
第六章、主要施工方案及技術(shù)保障措施...........................................43
6.1隔墻工程...............................................................43
6.1.1輕鋼骨架石膏板隔墻施工方案..........................................43
6.2樓地面工程..............................................................48
6.2.1水泥砂漿找平層施工方案..............................................48
6.2.2防靜電地板施工方案..................................................50
6.3涂飾工程................................................................51
6.3.1墻、頂面涂料施工方案................................................51
6.4吊頂工程................................................................55
6.4.1暗龍骨吊頂施工方案..................................................55
6.4.2礦棉吸音板吊頂......................................................63
6.5門窗工程..............................................................66
6.6.1玻璃門安裝施工方案.................................................66
6.6細(xì)部工程................................................................71
6.6.1窗簾盒制作與安裝施工方案............................................71
6.7鋼筋混凝土樓板澆筑施工方案..............................................76
6.8室內(nèi)拆除施工方案........................................................89
6.9給排水工程主要分項(xiàng)施工方案..............................................90
6.9.1自動(dòng)噴水滅火系統(tǒng)安裝................................................90
6.9.2自動(dòng)噴水滅火系統(tǒng)試驗(yàn)................................................93
6.10電氣安裝工程主要施工方案...............................................94
6.10.1建筑電氣安裝工程施工流程...........................................94
6.10.2管路敷設(shè)..........................................................95
6.10.3照明器具安裝.......................................................97
6.10.4開(kāi)關(guān)、插座安裝....................................................98
6.10.5電線、電纜敷設(shè)及接線...............................................98
6.10.6系統(tǒng)調(diào)試試運(yùn)行....................................................100
6.11通風(fēng)空調(diào)系統(tǒng)安裝施工方案..............................................102
6.12放線施工方案..........................................................108
6.13雨季施工方案..........................................................108
6.13.1雨期施工總體部署..................................................108
6.13.2雨期施工的主要措施................................................109
6.13.3雨期施工原材料的儲(chǔ)存和堆放........................................110
6.13.4雨期安全文明施工措施..............................................110
第七章、質(zhì)量保證體系及措施..................................................111
7.1質(zhì)量目標(biāo)...............................................................Ill
7.2質(zhì)量管理組織機(jī)構(gòu)......................................................111
7.3質(zhì)量崗位責(zé)任制度.......................................................111
7.4工程質(zhì)量控制措施.......................................................112
7.4.1構(gòu)成裝飾工程質(zhì)量的要素.............................................112
7.4.2保證質(zhì)量的施工要素控制措施.........................................112
7.5主要分項(xiàng)工程的質(zhì)量通病及防治措施.......................................114
7.6新技術(shù)、新工藝和新材料等降低成本和提高科技含量的措施...................117
7.7成品保護(hù)...............................................................117
7.7.1成品保護(hù)辦法的基本思路.............................................117
7.7.2建立成品保護(hù)工作的組織機(jī)構(gòu).........................................118
7.7.3成品保護(hù)責(zé)任及管理措施............................................119
7.7.4成品保護(hù)主要管理措施..............................................120
7.7.5精裝修工程完工到全部工程竣工階段的成品保護(hù)措施....................121
第八章、施工進(jìn)度計(jì)劃及保證措施..............................................122
8.1工期目標(biāo)..............................................................122
8.2施工進(jìn)度計(jì)劃.........................................................122
8.3工期計(jì)劃實(shí)施的控制保證措施............................................122
8.3.1確保工期的組織措施................................................122
8.3.2確保工期的管理措施................................................124
8.4工期的技術(shù)保證措施....................................................128
8.4.1人力資源保證措施..................................................128
8.4.2材料及設(shè)備配置的保證措施..........................................128
第九章、安全體系及安全保證措施..............................................132
9.1安全防護(hù)措施...........................................................132
9.1.1安全生產(chǎn)管理原則...................................................132
9.1.2安全生產(chǎn)的目的及目標(biāo)...............................................132
9.1.3安全生產(chǎn)管理機(jī)構(gòu)...................................................132
9.1.4項(xiàng)目部安全管理職責(zé).................................................132
9.1.5施工機(jī)具控制措施...................................................133
9.1.6施工用電控制措施...................................................134
9.1.7安全防火責(zé)任制.....................................................135
9.1.8施工現(xiàn)場(chǎng)消防管理和措施.............................................138
9.1.9防護(hù)設(shè)施和勞保用品控制措施.........................................139
9.2消防、保衛(wèi)措施.........................................................140
9.2.1消防管理...........................................................140
9.2.2施工現(xiàn)場(chǎng)消防安全管理辦法...........................................142
9.2.3施工現(xiàn)場(chǎng)消防制度...................................................143
9.2.4倉(cāng)庫(kù)防火制度.......................................................143
9.2.5消防獎(jiǎng)勵(lì)與處罰規(guī)定.................................................143
9.2.6施工現(xiàn)場(chǎng)治安保衛(wèi)防范管理...........................................144
第十章、文明施工及環(huán)境保護(hù)施工措施..........................................146
10.1管理目標(biāo)..............................................................146
10.2組織保證..............................................................146
10.3工作制度.............................................................146
10.4管理措施.............................................................147
10.4.1場(chǎng)容布置.........................................................147
10.4.2現(xiàn)場(chǎng)機(jī)械管理方面的措施............................................147
10.4.3現(xiàn)場(chǎng)衛(wèi)生管理的措施................................................147
10.4.4防止對(duì)大氣污染....................................................147
10.4.5防止噪音污染......................................................148
10.4.6廢棄物管理.......................................................148
10.4.7材料設(shè)備的管理....................................................148
10.4.8其他措施.........................................................148
10.4.9防止擾民和民擾措施................................................149
10.5綠色環(huán)保計(jì)劃及措施....................................................149
10.5.1推廣清潔施工......................................................149
10.5.2清潔施工的原則....................................................150
10.5.3清潔施工的基本途徑................................................150
10.5.4清潔施工的項(xiàng)目管理................................................150
10.5.5清潔施工材料進(jìn)場(chǎng)檢驗(yàn)..............................................151
10.5.6清潔施工保證措施..................................................151
10.5.7本工程裝飾材料使用環(huán)保型材料.....................................152
第十一章、施工現(xiàn)場(chǎng)總平面布置................................................157
11.1施工平面布置原則......................................................157
11.2施工現(xiàn)場(chǎng)平面、道路...................................................157
11.3工地材料倉(cāng)庫(kù)........................................................157
11.4室內(nèi)臨時(shí)材料堆放處..................................................157
11.5臨時(shí)加工車間.........................................................158
11.6臨時(shí)設(shè)施布置.........................................................158
11.7臨時(shí)用水的布置.......................................................158
11.8臨時(shí)用電的布置.......................................................158
11.9消防設(shè)施.............................................................159
11.11施工現(xiàn)場(chǎng)平面布置圖...................................................159
第十二章、協(xié)調(diào)配合方案......................................................160
12.1與業(yè)主、設(shè)計(jì)、監(jiān)理、物業(yè)等各方的配合..................................160
12.2與各專業(yè)分包的施工配合...............................................163
第十三章、試驗(yàn)和檢測(cè)措施....................................................165
13.1試驗(yàn)與測(cè)量管理措施...................................................165
13.1.1試驗(yàn)管理..........................................................165
13.1.2計(jì)量管理........................................................165
13.1.3測(cè)量管理.........................................................165
13.1.4主要工作內(nèi)容......................................................166
13.2室內(nèi)環(huán)境污染控制.....................................................167
13.2.1室內(nèi)環(huán)境污染控制.................................................167
13.2.2室內(nèi)裝修裝修材料的檢測(cè)...........................................168
第十四章、資源配置..........................................................169
14.1設(shè)備資源管理..........................................................169
14.1.1主要施工機(jī)械設(shè)備配備要求..........................................169
14.1.2主要施工設(shè)備計(jì)劃.................................................170
14.2人力資源配置.........................................................171
14.2.1項(xiàng)目部人力資源配備...............................................171
14.2.2勞務(wù)人員資源配置.................................................171
14.2.3勞動(dòng)力配置計(jì)劃...................................................172
14.2.4保證勞動(dòng)力及時(shí)供應(yīng)的措施.........................................173
14.2.5勞動(dòng)力計(jì)劃.......................................................173
14.3勞務(wù)管理..............................................................174
14.3.1勞務(wù)隊(duì)伍選擇......................................................174
14.3.2勞務(wù)管理措施......................................................175
14.3.3勞務(wù)薪酬管理辦法..................................................176
14.3.4應(yīng)急預(yù)案..........................................................176
14.3.5勞務(wù)培訓(xùn)..........................................................180
14.4主要材料投入計(jì)劃及安排...............................................180
14.4.1項(xiàng)目采購(gòu)管理原則.................................................180
14.4.2采購(gòu)工作程序.....................................................180
14.4.3采購(gòu)計(jì)劃.........................................................181
14.4.4采購(gòu)實(shí)施.........................................................182
14.4.5主要材料投入計(jì)劃及安排............................................184
14.4.6主要裝飾裝修材料等級(jí)..............................................185
第十五章、保修工作管理措施..................................................186
15.1工程保修工作的管理措施................................................186
15.2工程保修承諾.........................................................187
15.2.1竣工保駕.........................................................187
15.2.2竣工保修.........................................................187
15.2.3建立工程回訪(投訴)和質(zhì)量問(wèn)題跟蹤制度.............................187
第十六章、緊急情況和突發(fā)事件的應(yīng)急預(yù)案......................................188
16.1應(yīng)急預(yù)案的制定........................................................188
16.2應(yīng)急預(yù)案的內(nèi)容.......................................................188
16.3緊急事故處理流程.....................................................192
第十七章、附圖表............................................................194
17.1計(jì)劃開(kāi)、竣工日期和施工進(jìn)度計(jì)劃表......................................195
17.2施工現(xiàn)場(chǎng)平面布置圖....................................................196
第一章、編制說(shuō)明及依據(jù)
1.1編制說(shuō)明
在認(rèn)真研究中國(guó)葛洲壩集團(tuán)國(guó)際工程有限公司遠(yuǎn)洋國(guó)際辦公樓裝飾裝修設(shè)計(jì)與施工招標(biāo)
文件、設(shè)計(jì)圖紙和工程特點(diǎn)的基礎(chǔ)上,綜合考慮我公司的管理經(jīng)驗(yàn)和施工能力,本著積極響
應(yīng)招標(biāo)文件,確保實(shí)現(xiàn)各項(xiàng)管理目標(biāo)的原則,經(jīng)過(guò)專家論證和多方案比較,編制了本工程的
施工組織設(shè)計(jì)。對(duì)施工總體進(jìn)度計(jì)劃及技術(shù)保障措施、主要分部分項(xiàng)工程施工方案及技術(shù)保
障措施、施工重點(diǎn)難點(diǎn)分析及技術(shù)保障措施、質(zhì)量保證體系及措施、安全文明施工措施、成
品保護(hù)措施、擬投入機(jī)械設(shè)備及人力資源、材料采購(gòu)計(jì)劃、協(xié)調(diào)配合方案等方面進(jìn)行了詳細(xì)
的闡述,其他方面作了一般性說(shuō)明。
本次招標(biāo)范圍包括北京市朝陽(yáng)區(qū)遠(yuǎn)洋國(guó)際中心2期F座大廳及3T1層(電梯顯示樓層為
3T2層)的辦公樓裝修及維護(hù);北京市朝陽(yáng)區(qū)金地中心A座21層、22層、23層、28層(電
梯樓層)的恢復(fù)工程。本施工組織設(shè)計(jì)為金地中心舊辦公樓裝飾裝修拆除及恢復(fù)工程。
本工程為中國(guó)葛洲壩集團(tuán)國(guó)際工程有限公司金地中心A座舊辦公樓裝飾裝修拆除及恢復(fù)
工程,地點(diǎn)在北京市朝陽(yáng)區(qū)金地中心A座。本工程建筑面積約7600平方米,本次投標(biāo)范圍為
本工程的21層、22層、23層、28層現(xiàn)裝飾裝修拆除及恢復(fù)原裝飾裝修。
根據(jù)本工程施工的特點(diǎn),本文件對(duì)各方面作了綜合闡述,為了該項(xiàng)工過(guò)程中按科學(xué)規(guī)律
組織規(guī)范施工,有計(jì)劃地開(kāi)展各分部分項(xiàng)工程的施工,及時(shí)做好程施工全各項(xiàng)施工準(zhǔn)備工作,
保證各種資源和勞動(dòng)力的及時(shí)供應(yīng);協(xié)調(diào)各工序之間的時(shí)間安排,保證施工的順利進(jìn)行,按
期保質(zhì)完成施工任務(wù)。
我們將嚴(yán)格按《質(zhì)量管理體系》、《環(huán)境管理體系》及《職業(yè)安全健康管理體系》標(biāo)準(zhǔn)的
要求,高標(biāo)準(zhǔn)、嚴(yán)要求做好施工前期準(zhǔn)備工作和施工方案的審定工作,并發(fā)揮本公司管理優(yōu)
勢(shì),強(qiáng)化計(jì)劃管理,使本工程質(zhì)量等級(jí)達(dá)到合格標(biāo)準(zhǔn)。
我公司將按照有關(guān)規(guī)定及業(yè)主的要求,按標(biāo)準(zhǔn)化工地管理,做到文明施工、文明管理,
服從業(yè)主、監(jiān)理統(tǒng)一管理和監(jiān)督,并承擔(dān)相應(yīng)的責(zé)任,建立一套綠色施工方案。
若我公司中標(biāo)承建本工程,在工程竣工后的保修期內(nèi),我們將隨時(shí)提供優(yōu)質(zhì)服務(wù),凡屬
我公司原因造成的質(zhì)量問(wèn)題,我公司將免費(fèi)進(jìn)行維修,滿足業(yè)主的一切合理要求。
1.2編制依據(jù)
1.2.1工程建設(shè)的有關(guān)文件
(1)招標(biāo)文件
招標(biāo)文件項(xiàng)目編號(hào)日期
中國(guó)葛洲壩集團(tuán)國(guó)際工程有限公司遠(yuǎn)洋國(guó)際
CGGCGJZB-2013-12013年12月
辦公樓裝飾裝修設(shè)計(jì)與施工招標(biāo)文件
(2)北京金地中心A座21層、22層、23J縣、28層原施工圖紙;
(3)中國(guó)葛洲壩集團(tuán)國(guó)際工程有限公司金地中心A座辦公區(qū)施工圖紙;
(4)金地中心寫字樓裝修手冊(cè)。
1.2.2國(guó)家有關(guān)法律法規(guī)
序號(hào)法規(guī)名稱
1《中華人民共和國(guó)建筑法》
2《中華人民共和國(guó)計(jì)量法》
3《中華人民共和國(guó)環(huán)境保護(hù)法》
4《中華人民共和國(guó)消防法》
5《中華人民共和國(guó)安全生產(chǎn)法》
6《建設(shè)工程質(zhì)量管理?xiàng)l例》
7《建設(shè)工程安全生產(chǎn)管理?xiàng)l例》
8《工程建設(shè)標(biāo)準(zhǔn)強(qiáng)制性條文》
L2.3工程施工規(guī)范、規(guī)程、標(biāo)準(zhǔn)、圖集等
(1)主要施工規(guī)范、規(guī)程、標(biāo)準(zhǔn)
序號(hào)規(guī)范、規(guī)程、標(biāo)準(zhǔn)名稱編號(hào)
1《建筑工程施工質(zhì)量驗(yàn)收統(tǒng)■?標(biāo)準(zhǔn)》GB50300-2001
2《建筑裝飾裝修工程質(zhì)量驗(yàn)收規(guī)范》GB50210-2002
3《建筑電氣工程施工質(zhì)量驗(yàn)收規(guī)范》GB50303-2002
4《建筑給水排水及采暖工程質(zhì)量驗(yàn)收規(guī)范》GB50242-2002
5《通風(fēng)與空調(diào)工程施工質(zhì)量驗(yàn)收規(guī)范》GB50243-2002
6《建筑工程內(nèi)部裝修防火施工驗(yàn)收規(guī)范》GB50354-2005
7《建筑電氣照明裝置施工與驗(yàn)收規(guī)范》GB50617-2010
8《建筑地面工程施工質(zhì)量驗(yàn)收規(guī)范》GB50209-2010
9《建筑玻璃應(yīng)用技術(shù)規(guī)范》JGJ113-2009
10《建筑照明設(shè)計(jì)標(biāo)準(zhǔn)》GB50034-2004
11《建筑設(shè)計(jì)防火規(guī)范》GB50016-2006
12《民用建筑工程室內(nèi)環(huán)境污染控制規(guī)范》GB50325-2010
13《視頻安防監(jiān)控系統(tǒng)工程設(shè)計(jì)規(guī)范》GB50395-2007
14《高層民用建筑設(shè)計(jì)防火規(guī)范》GB50045-95(2005年版)
15《入侵報(bào)警系統(tǒng)工程設(shè)計(jì)規(guī)范》GB50394-2007
16《出入口控制系統(tǒng)工程設(shè)計(jì)規(guī)范》GB50396-2007
17《有線電視系統(tǒng)工程技術(shù)規(guī)范》GB50200-94
18《火災(zāi)自動(dòng)報(bào)警系統(tǒng)設(shè)計(jì)規(guī)范》GB50116-98
19《建筑防雷設(shè)計(jì)規(guī)范》GB50057-1994(2000版)
20《建筑物電子信息系統(tǒng)防雷技術(shù)規(guī)范》GB50343-2004
21《智能建筑設(shè)計(jì)標(biāo)準(zhǔn)》GB/T50314-2006
22《綜合布線系統(tǒng)工程設(shè)計(jì)規(guī)范》GB50311-2007
23《民用建筑電氣設(shè)計(jì)規(guī)范》JGJ16-2008
24《城市建筑綜合布線系統(tǒng)工程設(shè)計(jì)規(guī)范》CECS119:2000
25《電子信息系統(tǒng)機(jī)房設(shè)計(jì)規(guī)范》GB50174-2008
26《公共節(jié)能建筑設(shè)計(jì)標(biāo)準(zhǔn)》GB50189-2005
(2)施工安全、文明施工管理規(guī)范、規(guī)程及規(guī)定
序號(hào)規(guī)范、規(guī)程、標(biāo)準(zhǔn)名稱編號(hào)
1《建設(shè)工程施工現(xiàn)場(chǎng)消防安全技術(shù)規(guī)范》GB50720-2011
2《建筑工程施工現(xiàn)場(chǎng)供用電安全規(guī)范》GB50194-93
3《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011
4《施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范》JGJ46-2005
5《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012
6《北京市建設(shè)工程施工現(xiàn)場(chǎng)環(huán)境保護(hù)標(biāo)準(zhǔn)》
7《文明安全施工管理暫行規(guī)定》(京建施法字(1999)1號(hào)文)
《施工現(xiàn)場(chǎng)安全文明施工補(bǔ)充標(biāo)準(zhǔn)》及相關(guān)安全文明施工管理
8
規(guī)定
9《北京市市容環(huán)境衛(wèi)生管理?xiàng)l例》
10《北京市人民政府關(guān)于禁止車輛運(yùn)輸匯漏遺撒的規(guī)定》
11《北京市人民政府關(guān)于加強(qiáng)垃圾渣土管理的規(guī)定》
12《北京市建設(shè)工程施工現(xiàn)場(chǎng)管理辦法》
《北京市建設(shè)工程施工現(xiàn)場(chǎng)消防管理辦法》及相16關(guān)安全消
13
防管理規(guī)定
(3)主要圖集
圖集名稱編號(hào)
建筑構(gòu)造通用圖集(工程做法)08BJ1-1
建筑構(gòu)造通用圖集(內(nèi)裝修)08BJ4-1
建筑構(gòu)造通用圖集(內(nèi)裝修一吊頂)08BJ4—3
《建筑構(gòu)造通用圖集(墻身一輕鋼龍骨石膏板)》08BJ2-5
建筑設(shè)備施工安裝通用圖集91sB2、91SB3
《封閉式母線及橋架安裝》D701-1-2
《等電位連接安裝》02D501-2
《電纜敷設(shè)》D101-1-7
(4)環(huán)保規(guī)范:
序號(hào)規(guī)范、規(guī)程、標(biāo)準(zhǔn)名稱編號(hào)
1《室內(nèi)裝飾裝修材料內(nèi)墻涂料中有害物質(zhì)限量》GB18582-2008
適用于本工程的標(biāo)準(zhǔn)包括但不限于上述,與裝飾裝修設(shè)計(jì)與施工相關(guān)的國(guó)家、行業(yè)、地
區(qū)(北京市)和物業(yè)的規(guī)程、規(guī)范、標(biāo)準(zhǔn)、規(guī)定、要求等同樣適用。若各規(guī)程、規(guī)范、標(biāo)準(zhǔn)、
規(guī)定、要求等在時(shí)間上有差異,則應(yīng)以時(shí)間后者為準(zhǔn);若在采用標(biāo)準(zhǔn)等級(jí)上有差異則應(yīng)以較
高標(biāo)準(zhǔn)等級(jí)為準(zhǔn)。
1.2.3企業(yè)相關(guān)管理文件
序號(hào)管理文件名稱
1質(zhì)量管理體系文件1509001:2008
2環(huán)境管理體系文件15014001:2004
3職業(yè)健康安全管理體系文件
第二章、工程概況
2.1工程簡(jiǎn)介
中國(guó)葛洲壩集團(tuán)國(guó)際工程有限公司遠(yuǎn)洋國(guó)際辦公樓裝飾裝修設(shè)計(jì)與施工
工程名稱
金地中心辦公樓裝飾裝修拆除及恢復(fù)工程
工程地點(diǎn)北京市朝陽(yáng)區(qū)建國(guó)路91號(hào)金地中心A座
北京市朝陽(yáng)區(qū)建國(guó)路91號(hào)金地中心A座21層、22層、23層、28層,約7600
建設(shè)規(guī)模
平方米
招標(biāo)人中國(guó)葛洲壩集團(tuán)國(guó)際工程有限公司
資金來(lái)源招標(biāo)人自籌
承包方式設(shè)計(jì)與施工總承包
本工程設(shè)計(jì)與施工質(zhì)量應(yīng)達(dá)到國(guó)家、行業(yè)、北京或?qū)I(yè)的設(shè)計(jì)標(biāo)準(zhǔn)與質(zhì)量
質(zhì)量要求
檢驗(yàn)標(biāo)準(zhǔn)
開(kāi)工日期:暫定2014年7月16日。
工期竣工日期;暫定2014年9月5日。
總工期:52天(為日歷天工期,包括法定節(jié)假日)。
2.2工作內(nèi)容和施工范圍
北京市朝陽(yáng)區(qū)建國(guó)路91號(hào)金地中心A座21層、22層、23層、28層,約7600平方米,
辦公樓裝飾裝修、設(shè)備的拆除,及廢舊材料清理出場(chǎng),并按原施工圖恢復(fù),通過(guò)金地中心物
業(yè)驗(yàn)收。拆除的舊設(shè)備招標(biāo)人要求遷移至新址辦公樓重新利用的,主要有原金地中心辦公區(qū)
的視頻會(huì)議系統(tǒng),貴賓會(huì)議室會(huì)議系統(tǒng),核心服務(wù)器,電話交換機(jī)等設(shè)備,承包單位應(yīng)將拆
卸的舊設(shè)備運(yùn)輸至新址辦公樓,并負(fù)責(zé)安裝、調(diào)試。
2.3主要施工項(xiàng)目
1、金地中心辦公區(qū)現(xiàn)有裝飾面拆除及外運(yùn);
2、金地中心辦公區(qū)的視頻會(huì)議系統(tǒng),貴賓會(huì)議室會(huì)議系統(tǒng),核心服務(wù)器,電話交換機(jī)等
設(shè)備整體拆除;承包單位應(yīng)將拆卸的舊設(shè)備運(yùn)輸至新址辦公樓,并負(fù)責(zé)安裝、調(diào)試。
3、22層23層樓梯拆除后地面樓板恢復(fù);
4、原裝飾面恢復(fù):
(1)頂棚:石膏板吊頂乳膠求;礦棉板吊頂;窗簾盒;
(2)墻面:乳膠漆;
(3)地面:抗靜電地板安裝,抗靜電地板清洗;
(4)隔墻:輕鋼龍骨石膏板;
(5)門:無(wú)框玻璃門安裝及五金。
5、格柵燈安裝,風(fēng)口安裝,VAV空調(diào)安裝;其中格柵燈利舊60%,其余按照原品牌、原
式樣采購(gòu);風(fēng)口利舊50%,其余按照原品牌、原式樣采購(gòu)。
2.4工程施工難點(diǎn)、施工關(guān)鍵點(diǎn)分析
中國(guó)葛洲壩集團(tuán)國(guó)際工程有限公司金地中心辦公樓裝飾裝修拆除及恢復(fù)工程位于北京市
朝陽(yáng)區(qū)金地中心A座,約7600平方米。按照金地中心物業(yè)管理規(guī)定,施工時(shí)間為晚八點(diǎn)至次
日早六點(diǎn)及公共假日,其他時(shí)間禁止施工;由于樓層高,拆除的大量建筑垃圾以及材料的運(yùn)
輸是重點(diǎn)。本工程按照招標(biāo)文件的工期為52日歷天,工期較緊。金地中心為高檔寫字樓,對(duì)
施工期間的安全文明施工要求高。按照防火設(shè)計(jì)規(guī)范金地中心寫字樓屬于一類辦公建筑,對(duì)
防火等級(jí)要求高。由于金地中心辦公樓內(nèi)的視頻會(huì)議系統(tǒng),貴賓會(huì)議室會(huì)議系統(tǒng),核心服務(wù)
器,電話交換機(jī)等設(shè)備要完整無(wú)損拆卸移至新址遠(yuǎn)洋國(guó)際辦公樓使用,所以這些設(shè)備的拆卸
和保管非常重要。
2.4.1本項(xiàng)目施工特點(diǎn)難點(diǎn)分析
本項(xiàng)目施工特點(diǎn)難點(diǎn)分析列表
序號(hào)施工難點(diǎn)難點(diǎn)分析應(yīng)對(duì)措施
按照金地中心寫字樓裝修手冊(cè)的規(guī)定,施工時(shí)間為晚詳見(jiàn):2.4.2“夜
1夜間施工八點(diǎn)至次日早六點(diǎn)及公共假日,人工降效大;同時(shí)夜間施工”難點(diǎn)的
間施工,工人易犯困,容易出現(xiàn)安全事故。應(yīng)對(duì)措施
本工程樓層高,同時(shí)前期為拆除工作,大量的建筑垃詳見(jiàn):2.4.3“垂
2垂直運(yùn)輸圾和施工期間的材料需要運(yùn)輸;如何有效的利用現(xiàn)場(chǎng)直運(yùn)輸”難點(diǎn)的
的貨梯滿足施工要求。應(yīng)對(duì)措施
詳見(jiàn):2.4.4“工
按照招標(biāo)文件的工期要求52天內(nèi)完成全部拆除及垃圾
3工期較短期較短”難點(diǎn)的
外運(yùn),重新裝修,時(shí)間較緊。
應(yīng)對(duì)措施
詳見(jiàn):2.4.5
安全文明施
4北京市金地中心為高檔寫字樓,對(duì)文明施工要求較高。“安全文明施
工
工”難點(diǎn)的應(yīng)對(duì)
措施
施工期間對(duì)現(xiàn)樓內(nèi)設(shè)施及原裝飾面的保護(hù)。詳見(jiàn):2.4.6“成
5成品保護(hù)品保護(hù)”難點(diǎn)的
應(yīng)對(duì)措施
本工程為一類高層辦公樓,耐火等級(jí)為一級(jí)。因此在詳見(jiàn):2.4.7“防
6消防安全施工應(yīng)做好消防工作,確保不出現(xiàn)事故?;鹨蟾摺钡膽?yīng)
對(duì)措施”
原金地中心辦公區(qū)的視頻會(huì)議系統(tǒng),貴賓會(huì)議室會(huì)議詳見(jiàn):2.4.8“部
部分設(shè)備利
7系統(tǒng),核心服務(wù)器,電話交換機(jī)拆除后重新在遠(yuǎn)洋國(guó)分設(shè)備利舊”的
IH
際辦公樓安裝使用。原設(shè)備的拆除和保管很重要。保障措施”
我們針對(duì)這些特點(diǎn)難點(diǎn),進(jìn)行逐項(xiàng)分析,制定有針對(duì)性的應(yīng)對(duì)措施。
2.4.2“夜間施工”難點(diǎn)的應(yīng)對(duì)措施
(1)由于本項(xiàng)目工期短,需要有數(shù)量足夠、素質(zhì)高的勞動(dòng)力,我們將調(diào)遣具有較高施工
技術(shù)水平和同類工程施工經(jīng)驗(yàn)的施工隊(duì)。
(2)編制勞動(dòng)力需用量計(jì)劃,施工前根據(jù)施工進(jìn)度計(jì)劃、施工階段的劃分、各專業(yè)工種
的需要、勞動(dòng)定額,編制切實(shí)可行的勞動(dòng)力需用量計(jì)劃,并根據(jù)工程實(shí)際進(jìn)展情況,由項(xiàng)目
部勞動(dòng)力管理員根據(jù)施工進(jìn)度計(jì)劃負(fù)責(zé)對(duì)各專業(yè)施工隊(duì)勞動(dòng)力進(jìn)退場(chǎng)時(shí)間、數(shù)量提出指導(dǎo)性
計(jì)劃并及時(shí)調(diào)整,避免勞動(dòng)力資源的浪費(fèi)。
(3)由于夜間施工,造成人員降效,因此必須配備必要的后備隊(duì)伍,克服人工降效造成
的人員不足。
(4)夜間施工時(shí)將強(qiáng)現(xiàn)場(chǎng)管理力度,加強(qiáng)巡視。做好職工的后勤保障工作,在大批人員
進(jìn)場(chǎng)之后,責(zé)成有關(guān)職能部門做好后勤工作安排,解決施工人員夜間施工的飲食等問(wèn)題,安
心現(xiàn)場(chǎng)工作。
2.4.3“垂直運(yùn)輸”難點(diǎn)的應(yīng)對(duì)措施
(1)積極和金地中心物業(yè)協(xié)調(diào)貨梯的使用時(shí)間;按照施工計(jì)劃安排,提前和物業(yè)確定電
梯使用時(shí)間;
(2)電梯下行帶走建筑垃圾,電梯上行是運(yùn)輸材料,提高電梯的使用效率。
(3)使用前電梯轎廂先用大芯板進(jìn)行保護(hù),并由專業(yè)負(fù)責(zé)電梯運(yùn)行。根據(jù)施工進(jìn)度計(jì)劃
合理編制材料進(jìn)場(chǎng)計(jì)劃,并報(bào)送物業(yè)及業(yè)主各一份,便于安排。
2.4.4“工期較短”難點(diǎn)的應(yīng)對(duì)措施
(1)勞動(dòng)力配置保障措施
由于本項(xiàng)目工期短,需
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 農(nóng)藝師考試前沖刺復(fù)習(xí)技巧分享試題及答案
- 小饞貓食品測(cè)試題及答案
- 農(nóng)業(yè)職業(yè)經(jīng)理人職業(yè)發(fā)展規(guī)劃試題及答案
- 福建事業(yè)單位考試美術(shù)教育試題及答案
- 農(nóng)民合作社運(yùn)營(yíng)管理及試題及答案
- 學(xué)習(xí)策略秘書證試題及答案
- 禁毒社工站面試題及答案
- 花藝師考試創(chuàng)新與傳統(tǒng)的平衡題目試題及答案
- 2024年園藝師考試水培技術(shù)基礎(chǔ)試題及答案
- 九年級(jí)化學(xué)上冊(cè) 第三單元 課題2《原子的結(jié)構(gòu)》教學(xué)設(shè)計(jì) (新版)新人教版
- 煤礦頂板管理培訓(xùn)
- 觀察小魚尾鰭內(nèi)血液的流動(dòng)實(shí)驗(yàn)
- 高速鐵路客運(yùn)服務(wù)基礎(chǔ)知識(shí)單選題100道及答案
- 2024年河北省廊坊市公開(kāi)招聘警務(wù)輔助人員(輔警)筆試摸底測(cè)試(1)卷含答案
- 圖書管理系統(tǒng)畢業(yè)論文答辯課件
- 2025年上半年甘肅省林業(yè)和草原局事業(yè)單位招聘筆試重點(diǎn)基礎(chǔ)提升(共500題)附帶答案詳解
- 綜合應(yīng)用能力事業(yè)單位考試(醫(yī)療衛(wèi)生類E類)試卷及解答參考(2024年)
- 新高考2卷散文《放猖》
- 管樁引孔施工方案
- 高教版2023年中職教科書《語(yǔ)文》(基礎(chǔ)模塊)上冊(cè)教案全冊(cè)
- 《開(kāi)源軟件與專有軟件的競(jìng)爭(zhēng)》
評(píng)論
0/150
提交評(píng)論