文檔簡介
馬安高速公路第五合同段
實施性施工組織設(shè)計
岳陽市公路橋梁基建總公司
馬安高速公路第五合同段項目部
二0一五年十月
馬安高速公路第5合同段實施性施工組織設(shè)計
目錄
第一章編制依據(jù)及原則.............................................................6
1.1編制說明.........................................................................6
1.2編制依據(jù)..........................................................................6
1.3指導(dǎo)思想........................................................................6
1.4編制原則..........................................................................7
第二章工程概況....................................................................7
2.1主要技術(shù)指標(biāo)....................................................................7
2.2設(shè)計概況........................................................................8
2.2.1地理位置.....................................................................8
2.2.2路線起訖.....................................................................8
2.2.3主要結(jié)構(gòu)物及工程量...........................................................8
2.3地形地貌.........................................................................9
2.4氣象、水文........................................................................9
2.5地層巖性.........................................................................9
2.6地震情況.........................................................................9
2.7工程特點、難點和重點............................................................9
2.7.1.工程特點...................................................................9
2.7.2.工程難點..................................................................10
2.7.3.工程重點..................................................................10
第三章施工準(zhǔn)備與臨時工程.........................................................10
3.1施工準(zhǔn)備.......................................................................10
3.1.1技術(shù)準(zhǔn)備....................................................................10
3.1.2取樣試驗....................................................................10
3.1.3物資設(shè)備準(zhǔn)備................................................................11
3.1.4施工隊伍準(zhǔn)備................................................................11
3.1.5施工現(xiàn)場準(zhǔn)備................................................................11
3.2臨時工程.........................................................................11
3.2.1施工場地布置................................................................11
3.2.2項目部駐地及員工宿舍........................................................11
3.2.3施工便道...................................................................12
3.2.4施工用電...................................................................12
3.2.5施工用水...................................................................12
3.2.6生產(chǎn)用房...................................................................12
3.2.7通信設(shè)施...................................................................13
第四章總體施工組織布置及規(guī)劃....................................................13
4.1總體施工組織布置原則...........................................................13
4.2項目組織機構(gòu)及勞動力計劃.......................................................13
4.3總體施工進度計劃及工期安排.....................................................14
4.3.1施工進度計劃編制原則.......................................................14
4.3.2總工期安排.................................................................14
4.3.3各分項工程的施工安排(詳見施工進度計劃表)..................................14
第五章主要工程項目的施工方案、施工方法..........................................16
5.1路基工程.......................................................................16
5.1.1設(shè)計概況...................................................................16
5.1.2路基施工前的準(zhǔn)備...........................................................16
5.1.3路基施工總體方案...........................................................17
5.1.4路基試驗段.................................................................17
5.1.5路基挖方...................................................................18
5.1.6路基填方...................................................................21
5.1.7特殊路基處理...............................................................34
5.1.8路基防護工程...............................................................36
馬安高速公路第5合同段實施性施工組織設(shè)計
5.1.9路基排水工程................................................................38
5.1.10路基工程中重點(關(guān)鍵)和難點分析...........................................38
5.2橋梁工程........................................................................53
5.2.1設(shè)計概況...................................................................53
5.2.2橋梁總體施工方案............................................................53
5.2.3樁基礎(chǔ)及橋臺施工............................................................54
5.2.4系梁施工....................................................................65
5.2.5墩柱、蓋梁施工..............................................................67
5.2.6橋臺搭板施工................................................................73
5.2.7梁板預(yù)制...................................................................74
5.2.8梁板安裝...................................................................93
5.2.9防撞護欄及橋梁附屬工程......................................................97
5.2.10橋面鋪裝層施工.............................................................99
5.2.11橋梁工程施工重點(關(guān)鍵)和難點分析........................................100
5.3涵洞工程.......................................................................108
5.3.1工程概況...................................................................108
5.3.2鋼筋碎蓋板涵施工...........................................................108
5.3.3涵洞工程施工重點(關(guān)鍵)和難點分析.........................................113
5.4路面底基層......................................................................120
5.5隧道工程........................................................................122
5.5.1水井坳隧道簡介.............................................................122
5.5.2施工布置及組織方案.........................................................122
5.5.3施工控制測量...............................................................123
5.5.4隧道洞口及明洞施工.........................................................124
5.5.5隧道洞身開挖...............................................................124
5.5.6施工支護...................................................................128
5.5.7防排水施工..................................................................132
5.5.8施工監(jiān)控量測...............................................................134
5.5.8洞身襯砌...................................................................136
5.5.9洞內(nèi)路面施工...............................................................138
5.5.10預(yù)埋件....................................................................138
5.5.11洞內(nèi)裝飾..................................................................139
5.5.12通風(fēng)、防塵措施............................................................139
5.5.13隧道工程施工重點(關(guān)鍵)和難點分析.......................................140
第六章工期保證體系及措施........................................................143
6.1工期保證體系..................................................................144
6.2工期保證措施..................................................................144
6.2.1組織保證...................................................................144
6.2.2勞力保證...................................................................145
6.2.3材料保證...................................................................146
6.2.4機械保證...................................................................146
6.2.5技術(shù)保證...................................................................147
6.2.6資金保證...................................................................148
6.3進度監(jiān)控方法....................................................................148
6.4限期工程趕工措施..............................................................150
第七章工程質(zhì)量管理體系及保證措施..............................................150
7.1質(zhì)量目標(biāo)......................................................................150
7.2工程質(zhì)量管理體系..............................................................151
7.2.1質(zhì)量管理方針...............................................................151
7.2.2質(zhì)量管理體系...............................................................151
7.2.3質(zhì)量保證體系...............................................................151
7.2.4質(zhì)量管理組織機構(gòu)...........................................................151
7.3質(zhì)量保證措施...................................................................153
7.3.1組織保證措施...............................................................153
7.3.2制度保證措施...............................................................153
馬安高速公路第5合同段實施性施工組織設(shè)計
7.3.3技術(shù)保證措施...............................................................154
7.3.4質(zhì)量過程控制保證措施.......................................................155
7.4專項工程質(zhì)量保證措施...........................................................156
7.4.1路基工程質(zhì)量保證措施.......................................................156
7.4.2橋梁工程質(zhì)量保證措施.......................................................157
7.4.3隧道工程質(zhì)量保證措施.......................................................157
7.4.4基坑開挖質(zhì)量保證措施.......................................................160
7.4.5施工縫質(zhì)量保證措施.........................................................160
7.4.6變形縫質(zhì)量保證措施.........................................................160
7.4.7防水工程質(zhì)量保證措施.......................................................161
7.4.8隱蔽工程質(zhì)量控制及措施.....................................................161
7.4.9預(yù)埋件、預(yù)留孔洞質(zhì)量控制及措施.............................................162
7.4.10地下光纜及其他地上地下設(shè)施的保護加固措施..................................164
7.4.11排水工程質(zhì)量保證措施......................................................166
7.4.12雨污檢查井、雨水井質(zhì)量保證措施............................................166
7.4.13砌體工程的質(zhì)量控制措施....................................................167
7.5質(zhì)量通病預(yù)控措施................................................................167
7.5.1填方路基下沉的預(yù)防措施.....................................................167
7.5.2橋頭及橋梁伸縮縫處跳車的防治措施...........................................168
7.5.3小型預(yù)制構(gòu)件與防護工程表面粗糙的預(yù)防措施...................................169
7.5.4預(yù)應(yīng)力梁施工常見通病的預(yù)控措施.............................................169
7.6對供貨商的管理措施.............................................................171
7.6.1供貨商調(diào)查、評價...........................................................171
7.6.2產(chǎn)品采購..................................................................171
7.6.3質(zhì)量跟蹤...................................................................172
7.7缺陷期對工程的維護方案.........................................................172
7.8創(chuàng)優(yōu)目標(biāo)及保證措施............................................................172
7.8.1創(chuàng)優(yōu)目標(biāo).................................................................172
7.8.2創(chuàng)優(yōu)組織機構(gòu)..............................................................172
7.8.3創(chuàng)優(yōu)工作程序..............................................................173
7.8.4創(chuàng)優(yōu)保證體系..............................................................174
7.8.5創(chuàng)優(yōu)保證措施..............................................................174
第八章安全生產(chǎn)體系及保證措施...................................................175
8.1安全生產(chǎn)目標(biāo)..................................................................175
8.2安全管理組織機構(gòu)..............................................................175
8.3安全職責(zé)......................................................................176
8.3.1經(jīng)理安全職責(zé)...............................................................176
8.3.2副經(jīng)理安全職責(zé).............................................................176
8.3.3總工程師安全職責(zé)...........................................................177
8.3.4工程部安全職責(zé).............................................................177
8.3.5設(shè)備物資部安全職責(zé).........................................................178
8.3.6合約部安全職責(zé).............................................................178
8.3.7辦公室安全職責(zé).............................................................178
8.3.8工區(qū)主任安全職責(zé)...........................................................178
8.3.9工班長安全職責(zé).............................................................179
8.3.10工人安全崗位職責(zé)..........................................................180
8.4安全生產(chǎn)管理體系...............................................................180
8.5安全生產(chǎn)保證體系...............................................................181
8.6安全生產(chǎn)保證措施...............................................................181
8.6.1施工安全組織保證措施.......................................................181
8.6.2施工安全保證措施...........................................................183
8.7消防............................................................................185
8.8裝卸磴與運輸安全措施...........................................................186
8.9防坍塌技術(shù)措施..................................................................186
8.10隧道軟弱破碎圍巖段施工........................................................186
馬安高速公路第5合同段實施性施工組織設(shè)計
8.11檔案室安全管理措施...........................................................187
第九章冬雨季施工保證措施......................................................187
9.1冬季施工措施..................................................................188
9.1.1冬季施工準(zhǔn)備...............................................................188
9.1.2冬季施工技術(shù)措施...........................................................188
9.2雨季施工措施....................................................................189
9.2.1雨季施工準(zhǔn)備...............................................................189
9.2.2雨季施工技術(shù)措施..........................................................190
第十章農(nóng)民工資、材料等款項的支付保證措施....................................191
10.1農(nóng)民工工資支付保證措施.......................................................191
10.2材料款支付保證措施...........................................................191
第十一章材料質(zhì)量檢驗措施........................................................192
11.1建立試驗檢測體系.............................................................192
11.2工程試驗與檢測................................................................192
11.2.1工程材料的試驗與檢測......................................................192
11.2.2分項、分部工程試驗檢測....................................................193
11.2.3竣工檢驗..................................................................193
11.3加強試驗檢測數(shù)據(jù)資料管理.....................................................194
第十二章環(huán)境保護、文物保護及水土保持體系及保證措施...........................194
12.1環(huán)境保護、水土保持目標(biāo).......................................................194
12.2環(huán)境保護、水土保持組織機構(gòu)....................................................194
12.3環(huán)境保護、水土保持體系........................................................194
12.4環(huán)境保護措施..................................................................195
12.4.1土地保護措施..............................................................195
12.4.2植被保護措施..............................................................195
12.4.3水資源保護措施............................................................196
12.4.4控制噪音的措施............................................................196
12.4.5控制大氣污染的措施........................................................197
12.4.6水污染控制措施............................................................197
12.4.7泥漿及固體廢棄物處理、處置................................................197
12.4.8施工場地植被恢復(fù)措施......................................................197
12.5文物保護體系及保證措施........................................................197
12.5.1文物保護體系.............................................................197
12.5.2文物保護保證措施.........................................................198
第十三章文明施工體系及保證措施................................................198
13.1文明施工目標(biāo).................................................................198
13.2文明施工保護體系及保證措施....................................................198
13.2.1文明施工保護體系.........................................................198
13.2.2文明施工保證措施.........................................................199
第十四章與業(yè)主、設(shè)計單位、監(jiān)理單位及其他相鄰施工單位的協(xié)調(diào)配合措施...........200
14.1與業(yè)主的配合協(xié)調(diào)措施.........................................................200
14.2與設(shè)計單位的配合協(xié)調(diào).........................................................200
14.3與監(jiān)理單位的配合協(xié)調(diào).........................................................200
14.4與當(dāng)?shù)卣⒅苓厗挝?、居民的配合協(xié)調(diào).........................................201
14.5與相鄰標(biāo)段的配合協(xié)調(diào).........................................................201
第十五章編制竣工驗收、竣工資料和竣工備案的管理.................................202
15.1竣工驗收管理.................................................................202
15.2竣工資料管理..................................................................203
15.3竣工備案管理..................................................................204
4
馬安高速公路第5合同段實施性施工組織設(shè)計
附表:
附表一施工總體計劃表
附表二分項工程進度率計劃(斜率圖)
附表三工程管理曲線
附表四分項工程生產(chǎn)率和施工周期表
附表五施工總平面布置圖
附表六勞動力計劃表
附表七臨時占地計劃表
附表八外供電力需求計劃表
附表九合同用款估算表
附表十施工進度控制網(wǎng)絡(luò)圖
馬安高速公路第5合同段實施性施工組織設(shè)計
第一章編制依據(jù)及原則
1.1編制說明
本施工組織設(shè)計依據(jù)本工程兩階段施工圖設(shè)計文件以及本工程施工技術(shù)特點,按有
關(guān)技術(shù)標(biāo)準(zhǔn)、有關(guān)文件精神而編制,科學(xué)指導(dǎo)現(xiàn)場的施工及有效進行質(zhì)量目標(biāo)、成本目
標(biāo)、工期目標(biāo)、安全目標(biāo)的控制。
通過認真學(xué)習(xí)和研究有關(guān)文件及圖紙資料,并在踏勘了施工現(xiàn)場后,分析了各種影
響施工的因素,明確了施工范圍及目標(biāo),充分了解了本工程施工的特點和難點;在施工
組織設(shè)計的編制中,力求符合實際情況,具有較強的技術(shù)可行性和實際過程中的可操作
性,充分體現(xiàn)我單位在本工程領(lǐng)域施工的技術(shù)優(yōu)勢。
1.2編制依據(jù)
1、本工程招標(biāo)文件、合同文件,現(xiàn)有施工圖紙;施工招標(biāo)的答疑書、補遺書。
2、招標(biāo)文件規(guī)定的適用于本工程的各種施工規(guī)范。
3、交通部現(xiàn)行工、材、機定額。
4、施工現(xiàn)場調(diào)查所了解、掌握的情況和資料。
5、我單位現(xiàn)有的技術(shù)水平、施工管理水平和機械設(shè)備配備能力及類似工程的施工
經(jīng)驗。
6、本工程合同工期。
7、國家和各部委有關(guān)安全、質(zhì)量、驗收等方面的規(guī)范、標(biāo)準(zhǔn)、法規(guī)文件等。
8、本工程所涉及的地方和國家有關(guān)政策和法規(guī),特別是環(huán)境保護、水土保持方面
的政策和法規(guī)。
1.3指導(dǎo)思想
總體指導(dǎo)思想是:投標(biāo)時為業(yè)主著想,施工時對業(yè)主負責(zé),竣工時讓業(yè)主滿意;同
時在經(jīng)濟可行,技術(shù)可靠的前提下,保質(zhì)、保量、保工期。
(1)管理人員與施工隊伍:項目部由具有豐富公路施工經(jīng)驗的老同志與年富力強的
中青年組成強有力的領(lǐng)導(dǎo)班子。調(diào)集具有類似工程施工經(jīng)驗的專業(yè)隊伍,完成該工程的
施工。
(2)施工組織:采用先進的管理技術(shù),統(tǒng)籌計劃,合理安排,組織分段平行流水作
業(yè),均衡生產(chǎn),保證業(yè)主要求的工期。
(3)機械設(shè)備配套:采用先進的機械設(shè)備,科學(xué)配置生產(chǎn)要素,組建功能匹配、良
性運作的施工程序,充分發(fā)揮機械設(shè)備生產(chǎn)能力。
(4)施工工藝:根據(jù)工程特點,采用先進、成熟的施工工藝,實行樣板引路、試驗
先行、全過程監(jiān)控信息化施工。
馬安高速公路第5合同段實施性施工組織設(shè)計
(5)質(zhì)量控制:進一步推廣全面質(zhì)量管理,嚴格按照IS09002標(biāo)準(zhǔn)質(zhì)量體系進行質(zhì)
量程序控制,對施工現(xiàn)場實施施工動態(tài)管理和嚴密監(jiān)控,上道工序必須為下道工序服務(wù),
質(zhì)量具有優(yōu)先否決權(quán)。
1.4編制原則
1、指導(dǎo)思想:科學(xué)組織、合理投入、優(yōu)質(zhì)安全、快速高效、不留后患。
2、認真貫徹國家的方針政策,嚴格執(zhí)行建設(shè)程序和施工程序。
3、充分理解招標(biāo)文件,以設(shè)計圖紙為主導(dǎo),采用先進、合理、經(jīng)濟、可行的施工
方案。
4、堅持“質(zhì)量第一”,執(zhí)行“全面質(zhì)量管理”,按標(biāo)準(zhǔn)化的要求進行施工,確保工
程質(zhì)量、文明施工和安全施工。
5、合理布置施工現(xiàn)場,施工全過程環(huán)境破壞最小、占用場地最少,有較周密的環(huán)
境保護措施。
6、合理安排施工計劃,用統(tǒng)籌方法組織平行流水作業(yè)和立體交叉作業(yè),做到施工
進度安排均衡、高效。
7、采用先進、配套的施工設(shè)備和技術(shù),加強系統(tǒng)管理,努力提高勞動生產(chǎn)率。
8、做到施工工藝與施工規(guī)范、設(shè)計要求及招標(biāo)文件要求相符,并達到完善。
9、施工組織設(shè)計編制做到施工總體部署和分項工程施工組織相結(jié)合,使其具有重
點突出、內(nèi)容全面、思路清晰的特點。
10、科學(xué)合理組織施工,確保合同工期。
第二章工程概況
2.1主要技術(shù)指標(biāo)
馬安高速公路是“3+5”城市群“五縱七橫”高速公路網(wǎng)之第三橫一一平益高速的
西段,連接線益馬(在建)與官安高速公路(擬建),本項目的修建將縮短益陽至湘西、
張家界的里程約40km,是長沙至湘西的最便捷通道,對建設(shè)“兩型”交通具有重要意義。
本段為第五合同段,起止里程樁號K47+560-K58+860,路線起于東坪鎮(zhèn)橋灣里,路線近
正西走向,經(jīng)長田,在觀音沖跨越燈花、在學(xué)堂灣跨涉溪,在紅巖溪設(shè)安化互通連接安
化縣城,經(jīng)木子鄉(xiāng),在顏家坪跨越海溪,設(shè)涉溪特大橋,后設(shè)水井坳隧道,終于東坪鎮(zhèn)
城西村蓮花沖,線路長度11.291km。
馬安高速公路第5合同段實施性施工組織設(shè)計
技術(shù)標(biāo)準(zhǔn)
指標(biāo)名稱采用值
公路等級:高速公路
設(shè)計速度:100km/h
停車視距:160m
不設(shè)超高最小平曲線半徑:5500m
最大平曲線半徑:700m
凸型豎曲線最小半徑:7000m
凹型豎曲線最小半徑:5000m
整體式行車道寬度:4X3.75m
分離式行車道寬度:2X3.75m
右側(cè)硬路肩寬度:2.5m
左側(cè)硬路肩寬度:lm
土路肩寬度:0.75m
左側(cè)路緣帶寬度:0.5m
路面結(jié)構(gòu)類型:瀝青路面
汽車荷載等級:公路-I級
設(shè)計洪水頻率:路基、橋涵1/100
隧道建筑限界:凈寬11m,凈高5m
2.2設(shè)計概況
2.2.1地理位置
本工程位于湖南省西南部,屬湖南省安化縣東坪鄉(xiāng)木子管區(qū)。
2.2.2路線起訖
起止里程樁號K47+560-K58+860,路線起于東坪鎮(zhèn)橋灣里,路線近正西走向,經(jīng)長
田,在觀音沖跨越燈花、在學(xué)堂灣跨海溪,在紅巖溪設(shè)安化互通連接安化縣城,經(jīng)木子
鄉(xiāng),在顏家坪跨越海溪,設(shè)海溪特大橋,后設(shè)水井坳隧道,終于東坪鎮(zhèn)城西村蓮花沖,
線路長度11.291km。
2.2.3主要結(jié)構(gòu)物及工程量
主要工程量:
合同段路線長11.291km,路基土石方挖方:200.6萬m3,路基土石方填方238.5
萬m3;防護工程:漿砌片石95233m3,現(xiàn)澆混凝土8694m3,盲溝6427m,草植162012m2;
橋梁1820.4m/5座,管涵1121.41m/37道,蓋板涵898.45m/26道,蓋板涵通道948.28m/22
道;碎拱型通道70.51m/l道;波紋管涵322.25m/2道;隧道773.5m/l道。
8
馬安高速公路第5合同段實施性施工組織設(shè)計
2.3地形地貌
路線走廊帶以構(gòu)造剝蝕丘陵地貌為主,構(gòu)造剝蝕較為強烈,地形起伏較大。場地高
程一般在150?200nl之間。最高點高程為332.60m,最低為120m。路線主要沿山谷展布,
與沿線的山脊走向大致垂直,植被較為茂盛,多以喬木為主。
2.4氣象、水文
1、氣象
項目區(qū)為亞熱帶季風(fēng)濕潤氣候區(qū),年降雨量1672.9mm,年蒸發(fā)量1121mm,年平均
氣溫16.2度,最高氣溫41.8度,歷年平均相對濕度為8設(shè),全年主導(dǎo)風(fēng)向為北風(fēng)。
2、水文
本項目沿線水系發(fā)育,較大的常年性地表水體為資水支流。本合同段內(nèi)主要有柏溪、
株溪、槎溪。安化縣是我省暴雨中心之一,暴雨對路基、路塹工程的穩(wěn)定影響較大。地
表水主要為海溪河,地下水主要表現(xiàn)為地下松散巖類孔隙水、基巖裂隙水、巖溶水。
2.5地層巖性
通過對項目沿線及附近地區(qū)野外踏勘,并結(jié)合區(qū)域地質(zhì)資料,項目沿線及附近地區(qū)
地層主要有:第四系(Qh)、侏羅系下統(tǒng)(工)、白堊系上統(tǒng)(()、石炭系(CQ、泥盆
系中統(tǒng)棋子橋組(D2(l)元古界板溪群(Pm.)地層。
場內(nèi)灰?guī)r淺部巖溶現(xiàn)象較為發(fā)育,一般以溶溝、溶槽的形式出現(xiàn),黏土充填,發(fā)育
深度多在5?10m左右。在海溪特大橋8、10?16、22#墩均有溶洞,一般洞徑在0.80?
2.30m左右,其中ZKYX22-4鉆孔揭示溶洞洞徑約19m,填充物為軟~可塑狀黏土,區(qū)內(nèi)
深部巖溶較發(fā)育。
2.6地震情況
地震動峰值加速度為0.05,地震反應(yīng)譜特征周期為0.35,對應(yīng)原基本烈度為VI度
區(qū)。
2.7工程特點、難點和重點
2.7.1.工程特點
本合同段工程主要具有以下特點:
線路長:主線有11.291Km,安化連接線長5.6019Km;
土石方極不平衡:本標(biāo)段起點和終點地段填缺較大,中間互通區(qū)土方填余量大,存
在跨橋、隧調(diào)土,且遠調(diào)運量較大,嚴重制約路基施工進度;
現(xiàn)有村道雖然貫通主線,但寬度、路面結(jié)構(gòu)層均不能滿足施工車輛通行,施工機械
進場較困難;
地質(zhì)情況復(fù)雜:本標(biāo)經(jīng)過巖溶地段,溶洞群布,洞徑大小不一,樁基溶洞處理工程
量大;
工程任務(wù)重,施工工程短,暴雨時長;
馬安高速公路第5合同段實施性施工組織設(shè)計
構(gòu)造物數(shù)量多,有特大橋一座,大橋二座,跨線橋二座,通涵88道,分布較密。
2.7.2.工程難點
1)路基方面
土石方分布不平衡,中間多,兩端少,跨橋、隧遠調(diào),請業(yè)主適當(dāng)考慮制約因素,
合理解決土石方遠調(diào)的困難;高填地段的、深切地段的施工方法和質(zhì)量控制;構(gòu)造物臺
背填筑方法和質(zhì)量控制;溶洞的處理等。
2)橋梁方面
樁基溶洞的處理;高墩的施工,40mT梁的預(yù)制安裝。
3)隧道工程
2.7.3.工程重點
本合同段工程的重點在涉溪特大橋的施工、652片梁板的預(yù)制安裝、
水井坳隧道工程的施工、88道通涵構(gòu)造物的施工。
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 評估學(xué)習(xí)效果的2025年國際金融理財師考試后續(xù)跟進措施試題及答案
- 考前定心2025年證券從業(yè)資格證考試試題及答案
- 微生物檢驗技師證書考試的獨特之處試題及答案
- 流調(diào)課題申報書
- 2025光伏支架技術(shù)規(guī)范
- 項目管理師考試的復(fù)習(xí)技巧與試題答案
- 江蘇省鹽城市大豐區(qū)大橋初級中學(xué)八年級音樂下冊櫻花 教學(xué)設(shè)計
- 會計信息化建設(shè)試題及答案
- 掌握財務(wù)知識的特許金融分析師試題及答案
- 題庫課題申報書
- 油田節(jié)能降耗技術(shù)-全面剖析
- 廣西欽州市欽州港經(jīng)濟技術(shù)開發(fā)區(qū)中學(xué)2025年初三第二學(xué)期第一次區(qū)模擬化學(xué)試題含解析
- 全國統(tǒng)一卷試題及答案
- 銀行防搶防暴課件
- 水電工程驗收單
- 婦科護理標(biāo)準(zhǔn)化管理
- 蘭州2025年中國農(nóng)業(yè)科學(xué)院蘭州畜牧與獸藥研究所招聘16人筆試歷年參考題庫附帶答案詳解
- 《哈哈鏡笑哈哈》名師課件2022
- 冷卻塔使用維護說明書
- 傳統(tǒng)皮影戲在小學(xué)藝術(shù)教育的應(yīng)用與創(chuàng)新實踐
- 2025年國家會展中心上海有限責(zé)任公司招聘筆試參考題庫含答案解析
評論
0/150
提交評論