玉湖100兆瓦并網(wǎng)光伏發(fā)電項(xiàng)目光伏場區(qū)A標(biāo)段
施工組織總設(shè)計(jì)
目錄
1施工組織設(shè)計(jì)概述.......................................................1
2工程概況...............................................................1
2.1工程規(guī)模.........................................................1
2.2工程設(shè)計(jì)單位.....................................................2
2.3工程監(jiān)理單位.....................................................2
2.4廠址條件.........................................................2
2.5交通運(yùn)輸.........................................................2
2.6水文氣象.........................................................2
2.7工程地質(zhì).........................................................2
2.8工程范圍.........................................................3
2.9本工程的管理目標(biāo)和要求...........................................5
3總體施工組織布置及規(guī)劃.................................................6
3.1現(xiàn)場組織機(jī)構(gòu).....................................................6
3.2主要管理部門職責(zé).................................................7
3.2.1項(xiàng)目經(jīng)理職責(zé)................................................7
322項(xiàng)目副經(jīng)理職責(zé)...............................................9
323項(xiàng)目技術(shù)負(fù)責(zé)人職責(zé)..........................................10
3.2.4安全總監(jiān)職責(zé)...............................................11
3.2.5工程(技術(shù))管理部職責(zé).....................................11
3.2.6物資管理部職責(zé).............................................11
327質(zhì)量管理部職責(zé)..............................................12
3.2.8安全管理部職責(zé).............................................13
3.2.9資料(檔案)管理部職責(zé).....................................13
3.2.10綜合辦公室職責(zé)............................................14
3.2.11經(jīng)營管理部職責(zé)............................................15
3.2.12各專業(yè)負(fù)責(zé)人職責(zé)..........................................15
3.3施工組織原則....................................................16
3.3.1實(shí)行項(xiàng)目經(jīng)理負(fù)責(zé)制.........................................16
3.3.2公司對項(xiàng)目的管理模式.......................................16
3.3.3工程管理體系化.............................................16
3.3.4項(xiàng)目管理組織機(jī)構(gòu)...........................................16
3.3.5施工管理模式...............................................17
3.3.6施工接口協(xié)調(diào)與現(xiàn)場管理.....................................17
3.4辦公硬件設(shè)施.....................................................17
3.4.1辦公硬件設(shè)施...............................................17
342辦公管理信息系統(tǒng)............................................18
4主要項(xiàng)目的施工方案、方法與技術(shù)措施....................................20
4.1主要專業(yè)方案....................................................20
4.1.1土建施工方案...............................................20
4.1.2機(jī)電安裝方案...............................................34
4.1.3試驗(yàn)及調(diào)試方案.............................................53
4.1.4系統(tǒng)整體試運(yùn)行方案.........................................59
4.1.5特殊施工措施...............................................62
4.2本工程涉及的重點(diǎn)、難點(diǎn)專題方案..................................64
4.2.1植被恢復(fù)措施...............................................64
4.2.3雨季施工措施...............................................65
4.2.4冬季施工保障措施...........................................66
4.2.5大風(fēng)天施工措施.............................................68
4.3采用先進(jìn)施工工藝、技術(shù)措施......................................69
4.3.1電纜敷設(shè)施工專項(xiàng)技術(shù)措施...................................69
4.3.2控制電纜接線施工專項(xiàng)技術(shù)措施...............................71
5施工總平面布置、力能供應(yīng)..............................................71
5.1施工區(qū)域劃分、施工道路布置......................................71
5.2施工道路及雨排水設(shè)計(jì)方案........................................72
5.2.1場區(qū)道路及施工組合場道路...................................72
5.2.2廠區(qū)排水...................................................72
5.3臨時(shí)設(shè)施布置....................................................72
531施工圍墻、大門、道路布置..................................72
5.3.2臨時(shí)設(shè)施布置方案........................................73
5.3.3臨時(shí)用地表..............................................73
5.4臨時(shí)供電、供水排水設(shè)施及布置....................................73
5.4.1施工用水...................................................73
542施工用電....................................................74
5.4.3施工用氣...................................................76
5.5施工總平面管理規(guī)劃..............................................76
6施工進(jìn)度計(jì)劃..........................................................77
6.1招標(biāo)文件工期要求................................................77
6.2主要項(xiàng)目節(jié)點(diǎn)計(jì)劃工期............................................77
6.3橫道圖、網(wǎng)絡(luò)圖及關(guān)鍵線路........................................78
6.4保證計(jì)劃完成的措施..............................................78
6.4.1管理措施...................................................78
6.4.2施工進(jìn)度控制措施...........................................79
6.4.3加大技術(shù)、勞動力資源投入...................................80
6.4.4機(jī)械設(shè)備的配置措施.........................................80
6.4.5施工組織技術(shù)措施...........................................81
6.4.6物資供應(yīng)及后勤保障措施.....................................81
6.4.7強(qiáng)有力的生產(chǎn)調(diào)度...........................................81
6.4.8嚴(yán)格、細(xì)致的工程計(jì)劃管理...................................82
6.4.9合理趕工措施...............................................83
6.4.10合同與經(jīng)營管理措施........................................84
6411工期違約責(zé)任罰則...........................................85
7勞動力計(jì)劃安排........................................................86
7.1擬投入勞動力安排、季節(jié)性施工工人保證措施勞動力配備合理、充足....86
7.2工人實(shí)名制,門禁系統(tǒng)情況(身份認(rèn)證識別)........................87
721門禁系統(tǒng)滿足要求............................................87
7.2.2系統(tǒng)配置及工作流程.........................................87
7.2.3系統(tǒng)特點(diǎn)...................................................88
7.2.4系統(tǒng)功能...................................................89
7.2.5工人實(shí)名制承諾.............................................90
7.3工人工資保障承諾和措施..........................................90
7.3.1保障工人工資支付基本措施...................................90
7.3.2工人工資保障辦法...........................................90
7.3.3工人工資發(fā)放承諾...........................................92
8施工機(jī)械配置和試驗(yàn)、檢測儀器設(shè)備..................................92
8.1施工機(jī)械總體安排情況............................................92
8.1.1主要施工機(jī)械布置方案.......................................92
8.2施工機(jī)械配置....................................................92
8.3施工機(jī)械性能先進(jìn)、保證本工程措施................................93
8.3.1主要施工機(jī)械及試驗(yàn)和檢測儀器投入計(jì)劃.......................93
8.3.2主要施工機(jī)具保證措施.......................................93
9質(zhì)量保證體系..........................................................95
9.1質(zhì)量目標(biāo)........................................................95
9.2質(zhì)量管理體系....................................................95
9.2.1質(zhì)量管理體系的建立.........................................95
9.2.2質(zhì)量管理體系的運(yùn)轉(zhuǎn).........................................96
9.3質(zhì)量管理組織機(jī)構(gòu)及職責(zé)..........................................96
9.3.1質(zhì)量管理組織機(jī)構(gòu)...........................................96
9.3.2項(xiàng)目部領(lǐng)導(dǎo)和各部門主要職責(zé).................................97
9.3.3質(zhì)量管理網(wǎng)絡(luò)...............................................98
9.4質(zhì)量管理、質(zhì)量保證措施.........................................106
9.4.1質(zhì)量管理文件..............................................106
9.4.2質(zhì)量技術(shù)保證措施..........................................107
9.4.3質(zhì)量控制保證措施..........................................108
9.5特殊條件下(雨季、冬季)保證措施...............................114
9.5.1雨季施工準(zhǔn)備..............................................114
9.5.2冬季施工措施..............................................118
9.6根治質(zhì)量通病、確保合格竣工的措施和手段.........................119
9.6.1土建工程質(zhì)量通病措施......................................119
9.6.2安裝工程質(zhì)量通病措施......................................121
9.7對招標(biāo)文件中有關(guān)質(zhì)量標(biāo)準(zhǔn)、質(zhì)量保證等方面偏差...................122
9.7.1工程項(xiàng)目施工及驗(yàn)收時(shí)應(yīng)嚴(yán)格執(zhí)行的技術(shù)文件..................123
9.7.2技術(shù)文件執(zhí)行要求..........................................125
9.8強(qiáng)制性條文執(zhí)行計(jì)劃.............................................126
9.8.1編制依據(jù)..................................................126
9.8.2組織機(jī)構(gòu)及職責(zé)............................................126
9.8.3強(qiáng)制性條文的實(shí)施..........................................127
9.8.4強(qiáng)制性條文的執(zhí)行要求......................................128
9.8.5強(qiáng)制性條文的執(zhí)行檢查......................................128
9.8.6整改閉環(huán)管理..............................................129
9.9質(zhì)量報(bào)表情況...................................................129
10安全保證體系........................................................129
10.1針對本工程完善的安全保證體系..................................129
10.1.1安全生產(chǎn)行政管理體系.....................................129
10.1.2安全生產(chǎn)技術(shù)支撐體系.....................................130
10.1.3安全生產(chǎn)實(shí)施體系.........................................130
10.1.4安全監(jiān)督體系.............................................130
10.2安全管理目標(biāo)..................................................131
10.2.1安全管理方針.............................................131
10.2.2安全管理與環(huán)境管理目標(biāo)...................................131
10.2.3安全措施.................................................132
10.3特殊安全措施..................................................136
10.3.1動火作業(yè)安全保證措施.....................................136
10.3.2臨時(shí)用電作業(yè)安全保證措施.................................137
10.3.3吊裝作業(yè)安全保證措施.....................................137
10.3.4高處作業(yè)安全保證措施....................................138
10.3.5動土作業(yè)安全保證措施....................................140
10.4習(xí)慣性違章的措施和手段........................................141
10.5安全管理協(xié)議(見合同附件)是否提出偏差........................142
10.6安全報(bào)表情況(須提供了政府主管部門或上級單位蓋章的安全報(bào)表)..…142
11現(xiàn)場文明施工........................................................142
11.1現(xiàn)場文明施工措施..............................................142
11.1.1文明施工保證體系.........................................142
11.1.2現(xiàn)場文明施工措施.........................................142
11.2現(xiàn)場文明承諾..................................................144
11.3主要文明措施考核..............................................144
11.4現(xiàn)場文明管理協(xié)議(見合同附件)是否偏差........................145
12目前在建工程情況....................................................145
12.1本單位正常情況接納工程能力....................................145
12.2目前在建工程情況..............................................146
12.3優(yōu)先保證本標(biāo)段施工的承諾......................................146
12.3.1組織措施.................................................146
12.3.2技術(shù)措施................................................146
12.3.3經(jīng)濟(jì)措施..........................................................................................................147
12.3.4違約考核.................................................147
13項(xiàng)目風(fēng)險(xiǎn)預(yù)測及防范,事故應(yīng)急預(yù)案....................................147
13.1高處墜落事故預(yù)防對策..........................................147
13.2物體打擊事故預(yù)防對策..........................................147
13.3觸電事故防預(yù)防對策............................................148
13.4火災(zāi)事故的預(yù)防對策............................................148
13.5傾倒、崩塌事故的防止對策......................................149
14對工程設(shè)計(jì)、施工的特別建議..........................................149
15綠色施工措施........................................................150
15.1環(huán)境保護(hù)措施...............................................150
15.2節(jié)材與材料資源利用措施....................................153
15.3節(jié)水與水資源利用措施......................................154
15.4節(jié)地與施工用地保護(hù)措施....................................154
15.5節(jié)能與能源利用措施........................................155
16成本控制............................................................155
16.1成本控制目標(biāo)..................................................155
16.1.1項(xiàng)目部各崗位成本控制責(zé)任.................................156
16.1.2項(xiàng)目材料員成本控制責(zé)任...................................156
16.1.3項(xiàng)目機(jī)械員成本控制責(zé)任...................................157
16.1.4項(xiàng)目施工員成本控制責(zé)任...................................157
16.1.5項(xiàng)目安全員成本控制責(zé)任...................................157
16.1.6項(xiàng)目質(zhì)檢試驗(yàn)員成本控制責(zé)任...............................157
16.1.7項(xiàng)目測量員成本控制責(zé)任...................................158
16.2成本控制措施..................................................158
16.2.1科學(xué)管理.................................................158
1622采用新技術(shù)................................................159
16.2.3優(yōu)化施工方案.............................................159
17合同管理............................................................160
18信息管理............................................................162
18.1工程信息管理策劃..............................................162
18.2工程信息管理措施..............................................164
18.2.1人員信息管理.............................................164
18.2.2機(jī)械設(shè)備管理.............................................164
1823檔案資料管理..............................................164
18.2.4報(bào)表管理.................................................164
18.2.5信息的安全與維護(hù).........................................165
18.3工程P6系統(tǒng)投入使用方案.......................................165
18.3.1P6項(xiàng)目管理遵循PDCA循環(huán)................................165
18.3.2本工程實(shí)施P6項(xiàng)目管理流程詳見下圖........................166
18.3.3項(xiàng)目管理軟件P6在本工程應(yīng)用規(guī)劃..........................167
19工程組織協(xié)調(diào)........................................................168
19.1與招標(biāo)方協(xié)調(diào)..................................................168
19.2與業(yè)主方協(xié)調(diào)..................................................168
19.3與設(shè)計(jì)單位協(xié)調(diào)................................................168
19.4與監(jiān)理協(xié)調(diào)....................................................169
19.5與其他標(biāo)段協(xié)調(diào)................................................169
20物資管理............................................................170
20.1物資目標(biāo)......................................................170
20.2物資管理組織機(jī)構(gòu)、職責(zé)........................................170
20.2.1人員配置及組織機(jī)構(gòu).......................................170
2022部門職責(zé)..................................................170
20.2.3人員職責(zé).................................................171
20.3物資管理體系..................................................172
20.3.1物資設(shè)備采購計(jì)劃管理.....................................172
20.3.2物資設(shè)備采購組織實(shí)施管理.................................173
20.3.3供應(yīng)商管理...............................................174
2034采購質(zhì)量管理..............................................174
20.3.5采購合同管理.............................................174
20.4物資管理、物資保管保證措施....................................174
20.4.1物資的交接...............................................174
20.4.2開箱檢查工作.............................................175
20.4.3物資出入庫管理...........................................178
21新型冠狀病毒感染肺炎防疫措施........................................182
21.1施工現(xiàn)場疫情防控管理措施......................................183
21.2關(guān)于緊急情況的預(yù)案............................................184
21.2.1組織機(jī)構(gòu)及職責(zé)...........................................184
21.2.2應(yīng)急響應(yīng).................................................185
21.2.3應(yīng)急啟動.................................................185
附表一項(xiàng)目管理機(jī)構(gòu)...................................................187
附表二施工總平面圖...................................................188
附表三計(jì)劃開、竣工日期和施工進(jìn)度網(wǎng)絡(luò)圖...............................189
附表四勞動力計(jì)劃表...................................................190
附表五擬投入本標(biāo)段的主要施工設(shè)備表...................................191
附表六擬配備本標(biāo)段的試驗(yàn)和檢測儀器設(shè)備表.............................192
附表七質(zhì)量事故統(tǒng)計(jì)表.................................................192
(1)2018年質(zhì)量報(bào)表...............................................192
(2)2018年質(zhì)量證明材料...........................................193
(3)2019年質(zhì)量報(bào)表...............................................193
(4)2019年質(zhì)量證明材料...........................................193
(5)2020年質(zhì)量報(bào)表...............................................193
(6)2020年質(zhì)量證明材料...........................................193
附表八安全事故統(tǒng)計(jì)表.................................................193
(1)2018年企業(yè)職工傷亡事故報(bào)表...................................193
(2)2018年安全事故統(tǒng)計(jì)表.........................................193
(3)2018年安全無事故證明.........................................193
(4)2019年企業(yè)職工傷亡事故報(bào)表...................................193
(5)2019年安全事故統(tǒng)計(jì)表.........................................193
(6)2019年安全無事故證明.........................................193
(7)2020年企業(yè)職工傷亡事故報(bào)表...................................193
(8)2020年安全無事故證明.........................................193
(9)2020年安全事故統(tǒng)計(jì)表.........................................193
附表九臨時(shí)用地表.....................................................193
1施工組織設(shè)計(jì)概述
本施工組織設(shè)計(jì)根據(jù)招標(biāo)文件及相關(guān)的澄清內(nèi)容,并針對本工程的施工特點(diǎn)等從項(xiàng)
目概況、施工目標(biāo)、進(jìn)度控制、勞動力安排與機(jī)械配置、質(zhì)保體系、安保體系、施工總
平面布置、成本控制、合同管理、信息管理和組織協(xié)調(diào)等方面進(jìn)行了詳細(xì)的編寫,與之
相對應(yīng)的章節(jié)內(nèi)容如下:
(1)項(xiàng)目概況:具體內(nèi)容詳見施工組織設(shè)計(jì)第2章“項(xiàng)目概況”部分內(nèi)容。
(2)施工目標(biāo):具體內(nèi)容詳見施工組織設(shè)計(jì)第2章中2.9“本工程的管理目標(biāo)和要
求”部分內(nèi)容。
(3)進(jìn)度控制:具體內(nèi)容詳見施工組織設(shè)計(jì)第2章中2.9“本工程的管理目標(biāo)和要
求”部分內(nèi)容。。
(4)勞動力安排與機(jī)械配置:具體內(nèi)容詳見施工組織設(shè)計(jì)第7章“勞動力計(jì)劃安
排”及第8章“施工機(jī)械配置、試驗(yàn)和檢測儀器設(shè)備”部分內(nèi)容。
(5)質(zhì)保體系:具體內(nèi)容詳見施工組織設(shè)計(jì)第9章9.1”質(zhì)量管理體系”部分內(nèi)容。
(6)安保體系:具體內(nèi)容詳見施工組織設(shè)計(jì)第10章“安全保證體系”部分內(nèi)容。
(7)施工總平面布置:具體內(nèi)容詳見施工組織設(shè)計(jì)第5章“施工平面布置、力能
供應(yīng)”部分內(nèi)容。
(8)綠色施工:具體內(nèi)容詳見施工組織設(shè)計(jì)第15章中“綠色施工主要施工方案”
部分內(nèi)容。
(9)成本控制:具體內(nèi)容詳見施工組織設(shè)計(jì)第16章“成本控制”部分內(nèi)容。
(10)合同管理:具體內(nèi)容詳見施工組織設(shè)計(jì)第17章“合同管理”部分內(nèi)容。
(11)信息管理:具體內(nèi)容詳見施工組織設(shè)計(jì)第18章“信息管理”部分內(nèi)容。
(12)組織協(xié)調(diào):具體內(nèi)容詳見施工組織設(shè)計(jì)第19章“工程組織協(xié)調(diào)”部分內(nèi)容。
(13)物資管理:具體內(nèi)容詳見施工組織設(shè)計(jì)第20章“物資管理”部分內(nèi)容。
(14)疫情防控:具體內(nèi)容詳見施工組織設(shè)計(jì)第21章“疫情防控”部分內(nèi)容。
其他內(nèi)容如施工組織機(jī)構(gòu)、主要施工方案、重難點(diǎn)專題方案、現(xiàn)場文明施工、項(xiàng)目
風(fēng)險(xiǎn)預(yù)測及預(yù)防等內(nèi)容詳見施工組織設(shè)計(jì)其他部分相關(guān)內(nèi)容。
2工程概況
2.1工程規(guī)模
本工程裝機(jī)容量130MWp。
本工程電池組件,采用540Wp單晶雙面組件、固定支架、組串式逆變器;集電線
路采用2回35電纜接入35kV開關(guān)站。
2.2工程設(shè)計(jì)單位
達(dá)峰建設(shè)集團(tuán)電力設(shè)計(jì)院有限公司
2.3工程監(jiān)理單位
正在招標(biāo)
2.4廠址條件
場址區(qū)位于:玉湖縣阿合雅鎮(zhèn)光伏產(chǎn)業(yè)園區(qū)。
場址區(qū)地勢:稍有起伏,地勢大致由西南向東北傾斜,
場址平均海拔:約為1292?1339m。
土地性質(zhì):國有未開發(fā)利用土地。
場區(qū)占地面積約1.223km2。
2.5交通運(yùn)輸
場址距離西北距玉湖縣直線距離約42km,東北距道夫市43km;北距馬口鎮(zhèn)約
12.0km,分布有S304省道;西側(cè)距210縣道約3.1km;有鄉(xiāng)村公路和土路相通,交通條
件較為便利。
2.6水文氣象
序號項(xiàng)目單位數(shù)值備注
1多年平均氣溫℃10.7
2多年極端最高氣溫℃39.4
3多年極端最低氣溫℃-26
4最大凍土深度cm103
5最大積雪深度mm9
6年平均氣壓kPa897.5
7空氣平均相對濕度%59
8多年平均風(fēng)速m/s0.9
9最大風(fēng)速m/s22
10地區(qū)含氧量%/
11冰雹日數(shù)d0.8(年均)
12沙塵暴日數(shù)d6.6(年均)
13雷暴日數(shù)d22(年均)
2.7工程地質(zhì)
地形地貌:擬建站址地貌單元較單一,主要為山前沖洪積扇中上部,多呈荒灘草場
2
景觀。場址內(nèi)地形稍有,地勢大致由西南向東北傾斜。有鄉(xiāng)鎮(zhèn)道路和土路相通,交通條
件較為便利。
地層巖性:勘察深度8.0m范圍內(nèi)地層主要以角礫為主。
水文地質(zhì):站址區(qū)域地下水埋深大于8.0m,可不考慮地下水對地基基礎(chǔ)的影響。
地基土的腐蝕性:地基土對混凝土結(jié)構(gòu)暫按強(qiáng)腐蝕性,對鋼筋混凝土結(jié)構(gòu)中的鋼筋
暫按中等腐蝕性,地基土對鋼結(jié)構(gòu)具有微腐蝕性。最終腐蝕性評價(jià)待試驗(yàn)成果出來后確
TEo
不良地質(zhì)作用:不存在采空區(qū)、泥石流、滑坡、崩塌、雪崩、地震液化、地面塌陷、
地面沉降、地裂縫及地下天然洞穴等不良地質(zhì)作用。
2.8工程范圍
1.本標(biāo)合同范圍
玉湖100兆瓦并網(wǎng)光伏發(fā)電項(xiàng)目光伏場區(qū)A標(biāo)段施工。
2.本標(biāo)合同內(nèi)容:
2.1工程施工內(nèi)容:
2.1.1本標(biāo)段工程范圍包含但不限于以下內(nèi)容:
1)建筑工程(包括但不限于)
光伏場區(qū)3回集電線路區(qū)域建筑工程:固定傾角支架基礎(chǔ)、匯流及變配電設(shè)備基礎(chǔ)
工程、集電電纜線路工程(含光伏專用直流電纜、交流電纜)、接地工程等。詳見工程
量清單。
2)安裝工程(包括但不限于)
光伏場區(qū)3回集電線路區(qū)域發(fā)電設(shè)備、材料采購及安裝:
設(shè)備采購:除光伏組件、組串式逆變器、箱式變壓器、電纜由招標(biāo)人采購;其余光
伏組件支架、視頻監(jiān)控等所有設(shè)備材料均由投標(biāo)人采購。
安裝工程:發(fā)電設(shè)備安裝、匯流及變配電設(shè)備安裝、接地、發(fā)電子方陣系統(tǒng)調(diào)試等。
詳見工程量清單。
3)其他(但不限于以下內(nèi)容):
(1)本合同所有工程的材料和設(shè)備的到貨驗(yàn)收、卸貨、保管,建設(shè)期工程保險(xiǎn);
(2)負(fù)責(zé)水土保持及環(huán)境保護(hù)設(shè)施施工及配合驗(yàn)收,配合勞動安全與工業(yè)衛(wèi)生驗(yàn)收、環(huán)
境保護(hù)監(jiān)測與驗(yàn)收;配合消防施工安裝和檢測與驗(yàn)收、施工圖在政府職能部門的備案審
3
查;(3)配合并網(wǎng)前與電網(wǎng)有關(guān)的手續(xù)、工程相關(guān)檢測及驗(yàn)收、相關(guān)職能部門辦理工程
移交手續(xù)以及質(zhì)保期內(nèi)的質(zhì)量保證服務(wù)等;(4)建筑施工及安裝工程中甲供、乙供材料
及試樣的取樣、送檢和提供報(bào)告;(5)設(shè)備接地及常規(guī)接地裝置工程;(6)埋設(shè)件的
制作、安裝;(7)負(fù)責(zé)本工程所有電氣設(shè)備、集電線路和所有電力電纜、控制電纜交接
試驗(yàn),并提供當(dāng)?shù)毓╇姴块T認(rèn)可的交接試驗(yàn)報(bào)告;(8)施工及試運(yùn)行所必須的安全設(shè)
施、器具、標(biāo)牌;(9)負(fù)責(zé)施工過程中與當(dāng)?shù)卣畢f(xié)調(diào)臨時(shí)性及措施性補(bǔ)償?shù)裙ぷ?,?/p>
工臨時(shí)用地征用、施工場地原始地貌恢復(fù)、綠化、棄土棄渣處理、防洪設(shè)施修筑、線路
標(biāo)識牌采買及安裝,一年質(zhì)保期內(nèi)的修復(fù)維護(hù)工作(包工包料);(10)在工程量分項(xiàng)
清單中未列出的,但確實(shí)是工程范圍中應(yīng)該有的,完成本工程所要求的,均應(yīng)由投標(biāo)人
負(fù)責(zé),以及所有的施工準(zhǔn)備、安全文明施工措施等、成品保護(hù)、與移交期間檢驗(yàn)與取證、
驗(yàn)收及合同包含的所有風(fēng)險(xiǎn)、責(zé)任等,且包含并不限于此。詳見招標(biāo)技術(shù)規(guī)范及工程量
清單。
2.1.2施工外部關(guān)系協(xié)調(diào)
1)施工外部關(guān)系協(xié)調(diào),乙方負(fù)責(zé)本標(biāo)段施工外部關(guān)系協(xié)調(diào)。施工協(xié)調(diào)費(fèi)分為征地協(xié)
調(diào)費(fèi)和其他施工協(xié)調(diào)費(fèi),其中征地(包括永久征地和臨時(shí)征地)協(xié)調(diào)費(fèi)包括不限于:由
于開展征租地及地上附著物補(bǔ)償工作所需的與當(dāng)?shù)剜l(xiāng)鎮(zhèn)、村組、村民的協(xié)調(diào);
2)施工外部關(guān)系協(xié)調(diào),乙方負(fù)責(zé)本標(biāo)段施工外部關(guān)系協(xié)調(diào)。施工協(xié)調(diào)費(fèi)分為征地協(xié)
調(diào)費(fèi)和其他施工協(xié)調(diào)費(fèi),其中其他施工協(xié)調(diào)費(fèi)包括不限于:由于施工干擾所引起的村民
阻工協(xié)調(diào);由于地籍邊界不清所引起村民糾紛的協(xié)調(diào);由于設(shè)備、材料等運(yùn)輸所引起的
占壓、損壞影響到第三方的權(quán)屬物的協(xié)調(diào);施工期間造成的水土流失環(huán)保林業(yè)罰款費(fèi)用、
施工過程中發(fā)生的因征地問題阻工的協(xié)調(diào)及費(fèi)用;因施工人員、機(jī)械、環(huán)境的改變導(dǎo)致
的農(nóng)田家畜受損傷亡的協(xié)調(diào)及費(fèi)用;因施工導(dǎo)致的粉塵、噪音、交通阻塞而引發(fā)的群眾
不滿的協(xié)調(diào)及費(fèi)用;他人為索要錢財(cái)進(jìn)行的故意無理取鬧、騷擾阻撓施工的協(xié)調(diào)及費(fèi)用;
因投標(biāo)方技術(shù)、設(shè)備、人員問題,導(dǎo)致的超出設(shè)計(jì)臨時(shí)用地范圍需要增加臨時(shí)用地而進(jìn)
行的協(xié)調(diào)及費(fèi)用;需要當(dāng)?shù)厝罕娀蛘哒雒鎱f(xié)助施工而進(jìn)行的協(xié)調(diào)及費(fèi)用;其他為促
進(jìn)本工程順利進(jìn)展的協(xié)調(diào)工作及費(fèi)用等。
(2)施工過程中,由于乙方?jīng)]有按圖施工造成的超挖、超占范圍等,導(dǎo)致的問題,由
乙方自行協(xié)調(diào)賠償并妥善解決,如因此延誤工期,甲方將按照延誤時(shí)間予以考核,對上
述原因引起的賠償甲方有權(quán)直接扣減工程款補(bǔ)償給個(gè)人或相關(guān)單位。
4
2.1.3永久及臨時(shí)占用土地費(fèi)、青苗補(bǔ)償費(fèi)
永久及臨時(shí)占用土地費(fèi)、草原補(bǔ)償費(fèi)用等均有建設(shè)單位承擔(dān)。
施工單位要杜絕超出施工紅線圖的占地,例如道路等超挖,道路開挖中形成棄渣;
未經(jīng)批準(zhǔn)隨意增加渣場、取料場,臨時(shí)施工便道,塔基操作平臺等。征占臨時(shí)用地前,
范圍須經(jīng)招標(biāo)人確認(rèn),如發(fā)生未確認(rèn)先征占或確認(rèn)甲使用乙情況發(fā)生,全部責(zé)任由投標(biāo)
人自行負(fù)責(zé),對招標(biāo)人造成損失的,按損失情況的雙倍在合同中扣除。
2.2甲方有權(quán)適當(dāng)調(diào)整工程內(nèi)容及范圍。但應(yīng)書面通知承包單位,承包單位應(yīng)無條
件接受。
3.施工分界
包含A標(biāo)區(qū)域內(nèi)所有組件、逆變器、升壓箱變及附屬設(shè)施的施工安裝及調(diào)試,匯集
線路共計(jì)3條,連接共計(jì)18臺升壓箱變,3條匯集線路接入35kV相應(yīng)開關(guān)柜內(nèi),包含
電纜敷設(shè)、電纜頭及調(diào)試,以及本區(qū)域內(nèi)的土建工程,區(qū)域內(nèi)的場平、道路,區(qū)域內(nèi)支
架采購及安裝等。(詳細(xì)分界線詳見總圖分界圖)
原則上以該合同規(guī)定的施工范圍和內(nèi)容為分界,同時(shí)細(xì)則上執(zhí)行行業(yè)慣例,并服從
監(jiān)理人員的現(xiàn)場協(xié)調(diào)劃分定界(最終以相關(guān)設(shè)計(jì)圖紙標(biāo)定的節(jié)點(diǎn)為準(zhǔn))
2.9本工程的管理目標(biāo)和要求
(1)進(jìn)度目標(biāo):
本工程計(jì)劃開工日期:2021年9月20日,計(jì)劃竣工日期:2021年12月30日,計(jì)
劃工期:102日歷天。
(2)質(zhì)量目標(biāo):
工程質(zhì)量符合《東方集團(tuán)創(chuàng)基建一流指標(biāo)》、《電力建設(shè)施工質(zhì)量驗(yàn)收及評價(jià)規(guī)程》
(2012版)等有關(guān)國家、電力行業(yè)及東方標(biāo)準(zhǔn)。
專業(yè)質(zhì)量目標(biāo):
序號項(xiàng)目合格率%優(yōu)良率外備注
1土建項(xiàng)目單位工程100%98%
2安裝項(xiàng)目單位工程100%98%
3土建項(xiàng)目分部工程100%98%
4安裝項(xiàng)目分部工程100%98%
5
5土建項(xiàng)目分項(xiàng)工程100%98%
6安裝項(xiàng)目分項(xiàng)工程100%98%
(3)安全目標(biāo):
控制機(jī)械傷害、火災(zāi)、車輛傷害、物體打擊、起重傷害、高處墜落、淹溺、坍塌、
觸電、污染、灼燙、爆炸、中毒和窒息等事故。;
杜絕人身死亡事故。
杜絕重大設(shè)備和機(jī)械損壞事故。
杜絕重大火災(zāi)事故。
杜絕重大交通事故。
杜絕環(huán)境污染事故和重大坍塌事故。
杜絕群體職業(yè)中毒和食物中毒事故。
杜絕調(diào)試重大責(zé)任事故。
不發(fā)生人身重傷事故。
不發(fā)生火災(zāi)事故。
控制人身輕傷事故;人身輕傷率控制在8%。以內(nèi)。
嚴(yán)格控制,力爭杜絕各種習(xí)慣性違章。
(4)投資目標(biāo):
根據(jù)工程進(jìn)度,及時(shí)編制工程用款計(jì)劃;根據(jù)工程現(xiàn)場實(shí)際施工情況,及時(shí)提出合
理的變更申請,避免造成不必要的資源浪費(fèi)。降低造價(jià),決算不超預(yù)算。
(5)工程檔案管理目標(biāo):
加強(qiáng)檔案的過程管理,竣工資料在機(jī)組移交后45天內(nèi)移交;竣工資料移交的完整
率、合格率均達(dá)到100%。
3總體施工組織布置及規(guī)劃
3.1現(xiàn)場組織機(jī)構(gòu)
6
3.2主要管理部門職責(zé)
3.2.1項(xiàng)目經(jīng)理職責(zé)
(1)制度和體系建設(shè)
1)組織制定項(xiàng)目工地的各項(xiàng)管理制度,并組織實(shí)施,保障項(xiàng)目施工的順利進(jìn)行和盈
利;
2)組織落實(shí)“安全第一、預(yù)防為主、綜合治理”的方針,監(jiān)督檢查項(xiàng)目安全、文明
施工,履行安全生產(chǎn)第一責(zé)任者職責(zé),減少安全隱患;
3)確定項(xiàng)目工地組織機(jī)構(gòu)設(shè)置和崗位職責(zé)范圍,提高員工工作效率;
4)組織建立項(xiàng)目工地的QES管理體系并監(jiān)督體系運(yùn)行,提升質(zhì)量管理水平,降低
成本;
5)組織制定項(xiàng)目工地的管理目標(biāo)、考核指標(biāo)及管理方案,并督促實(shí)施,提高員工工
作積極性和主動性;
6)負(fù)責(zé)組織制定本項(xiàng)目管理所需要的各項(xiàng)管理制度和體系。
7)組織和調(diào)配項(xiàng)目工地的人、財(cái)、物資源,滿足工程施工需要,實(shí)現(xiàn)對項(xiàng)目工程有
效的控制,全面實(shí)現(xiàn)項(xiàng)目的各項(xiàng)合同目標(biāo);主持項(xiàng)目經(jīng)理辦公會,討論并決定項(xiàng)目“三
重一大”問題,保證項(xiàng)目經(jīng)營生產(chǎn)正常有序的進(jìn)行;
8)執(zhí)行公司和項(xiàng)目的經(jīng)營管理制度,加強(qiáng)項(xiàng)目風(fēng)險(xiǎn)防控,確保項(xiàng)目高質(zhì)、有效的履
約;
9)作為項(xiàng)目安全管理的第一責(zé)任人,落實(shí)安全體系,組織調(diào)查分析重大質(zhì)量、安
全、環(huán)境事故,落實(shí)與實(shí)施防范措施,實(shí)現(xiàn)安全文明施工;
7
10)加強(qiáng)質(zhì)量管理,提升施工工藝,實(shí)現(xiàn)項(xiàng)目的質(zhì)量目標(biāo);
11)聯(lián)系和協(xié)調(diào)與業(yè)主、地方等外部關(guān)系,不斷提高顧客滿意度。
(2)項(xiàng)目生產(chǎn)管理
1)組織和調(diào)配項(xiàng)目工地的人、財(cái)、物資源,滿足工程施工需要,實(shí)現(xiàn)對項(xiàng)目工程有
效的控制,全面實(shí)現(xiàn)項(xiàng)目的各項(xiàng)合同目標(biāo);
2)參加項(xiàng)目經(jīng)理辦公會,討論并決定項(xiàng)目“三重一大”問題,保證項(xiàng)目經(jīng)營生產(chǎn)正
常有序的進(jìn)行;
3)執(zhí)行公司和項(xiàng)目的經(jīng)營管理制度,加強(qiáng)項(xiàng)目風(fēng)險(xiǎn)防控,確保項(xiàng)目高質(zhì)、有效的履
約;
4)作為項(xiàng)目安全管理的第一責(zé)任人,落實(shí)安全體系,組織調(diào)查分析重大質(zhì)量、安
全、環(huán)境事故,落實(shí)與實(shí)施防范措施,實(shí)現(xiàn)安全文明施工;
5)加強(qiáng)質(zhì)量管理,提升施工工藝,實(shí)現(xiàn)項(xiàng)目的質(zhì)量目標(biāo);
6)聯(lián)系和協(xié)調(diào)與業(yè)主、地方等外部關(guān)系,不斷提高顧客滿意度。
(3)項(xiàng)目經(jīng)營管理
1)負(fù)責(zé)按《建造合同準(zhǔn)則》要求,組織編制項(xiàng)目部施工組織策劃方案和組織項(xiàng)目實(shí)
施《建造合同準(zhǔn)則》;
2)負(fù)責(zé)項(xiàng)目的財(cái)務(wù)核算,按公司內(nèi)部財(cái)務(wù)核算的要求,準(zhǔn)確、及時(shí)做好各項(xiàng)成本費(fèi)
用的歸集,定期進(jìn)行經(jīng)濟(jì)活動分析,及時(shí)上報(bào)《建造合同準(zhǔn)則》相關(guān)報(bào)表;
3)嚴(yán)格執(zhí)行公司下達(dá)的年度工資性費(fèi)用總額計(jì)劃,按照公司薪酬制度負(fù)責(zé)項(xiàng)目部
人員的薪酬分配;
4)積極開展二次經(jīng)營,擴(kuò)大承包范圍,嚴(yán)
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 短期用工協(xié)議2025
- 跨國貨物運(yùn)輸代理合同范例
- 2025版工程總承包合同EPC模式
- 高層辦公樓建筑深度剖析
- 5《老師 您好》公開課一等獎(jiǎng)創(chuàng)新教學(xué)設(shè)計(jì)(表格式)-1
- 局部凍傷的預(yù)防與護(hù)理
- 高中化學(xué) 第2章 元素與物質(zhì)世界 第1節(jié) 元素與物質(zhì)的分類一、二教學(xué)設(shè)計(jì)1 魯科版必修1
- 電力供應(yīng)與購買合同
- 人教版小學(xué)二年級上冊數(shù)學(xué) 第6單元 第2課時(shí) 8的乘法口訣 教案
- 電商企業(yè)股份制聯(lián)合入股合同
- 2024年遼寧省初中學(xué)業(yè)水平考試物理模擬卷一
- 居住區(qū)規(guī)劃智慧樹知到期末考試答案章節(jié)答案2024年湖南師范大學(xué)
- 安全生產(chǎn)三項(xiàng)制度內(nèi)容
- 體質(zhì)健康管理典型案例
- 孩子的電子產(chǎn)品使用與管理
- 2024屆安徽省淮北市高三下學(xué)期二模英語模擬試題(有答案)
- 遼寧省本溪市2023-2024學(xué)年八年級下學(xué)期4月期中物理試題
- 中班幼兒主題墻設(shè)計(jì)方案
- 健身房市場調(diào)研報(bào)告總結(jié)與反思
- 鋼結(jié)構(gòu)施工準(zhǔn)備-鋼結(jié)構(gòu)識圖
- 《企業(yè)安全生產(chǎn)費(fèi)用提取和使用管理辦法》
評論
0/150
提交評論