路基施工方案
編制:
審核:
審批:
日期:
目錄
第一章編制依據(jù)....................................................................................................................1
1.1編制說明....................................................................................................................1
1.2編制原則....................................................................................................................2
第二章工程概況....................................................................................................................3
2.1工程建設(shè)概況............................................................................................................3
2.2設(shè)計概況....................................................................................................................4
2.2.1道路設(shè)計.........................................................................................................4
2.2.2路基結(jié)構(gòu)技術(shù)標準.........................................................................................4
2.3工程施工條件............................................................................................................5
2.3.1氣溫.................................................................................................................5
2.3.2降水量.............................................................................................................5
2.3.3風速與風向.....................................................................................................5
2.3.4地下水情況.....................................................................................................5
2.3.5地質(zhì)情況.........................................................................................................5
第三章施工總體部署............................................................................................................7
3.1總體組織安排............................................................................................................7
3.1.1項目組織機構(gòu)圖.............................................................................................7
3.1.2項目主要管理人員崗位職責.........................................................................7
3.2項目管理目標..........................................................................................................11
3.3施工段劃分和施工工藝流程..................................................................................12
3.3.1施工段劃分...................................................................................................12
3.3.2施工工藝流程...............................................................................................12
3.4工程施工重點和難點分析及應(yīng)對措施..................................................................12
3.5新技術(shù)應(yīng)用要求......................................................................................................13
第四章施工進度計劃..........................................................................................................13
第五章施工準備與資源配置計劃......................................................................................14
5.1勞動力配置計劃......................................................................................................14
5.2主要周轉(zhuǎn)材料配置計劃..........................................................................................14
I
5.3機具、設(shè)備配置計劃..............................................................................................15
5.4技術(shù)復核和隱蔽驗收計劃......................................................................................15
5.5施工試驗檢驗計劃..................................................................................................15
5.6測量計量儀器配置計劃..........................................................................................16
第六章施工方法..................................................................................................................17
6.1路基工程概況..........................................................................................................17
6.2舊路拆除施工方案和技術(shù)措施..............................................................................17
6.3填方路基施工方案和技術(shù)措施..............................................................................17
6.4挖方路基施工方案和技術(shù)措施..............................................................................20
6.5濕軟路基處理方案和技術(shù)措施..............................................................................22
6.6保證路基施工質(zhì)量的技術(shù)措施..............................................................................24
6.7質(zhì)量標準..................................................................................................................25
第七章進度管理計劃..........................................................................................................26
7.1確定施工進度控制點..............................................................................................26
7.2進度管理措施..........................................................................................................27
第x章質(zhì)量管理計劃..........................................................................................................28
8.1質(zhì)量控制目標分解..................................................................................................28
8.2確定質(zhì)量控制點......................................................................................................28
8.3質(zhì)量保證措施..........................................................................................................29
第九章職業(yè)健康安全管理計劃..........................................................................................29
9.1職業(yè)健康安全管理目標..........................................................................................29
9.2現(xiàn)場職業(yè)健康安全管理組織機構(gòu)和職責分工......................................................30
9.2.1現(xiàn)場職業(yè)健康安全管理組織機構(gòu)...............................................................30
9.2.2現(xiàn)場職業(yè)健康安全管理職責分工...............................................................30
9.3職業(yè)健康安全重大危險源......................................................................................33
9.4安全生產(chǎn)管理制度..................................................................................................33
9.4.1安全生產(chǎn)責任制度.......................................................................................33
9.4.2安全責任目標考核制度...............................................................................34
9.4.3安全施工組織設(shè)計及專項方案審批制度...................................................34
II
9.4.4安全教育培訓管理制度...............................................................................35
9.4.5安全例會管理制度.......................................................................................35
9.4.6班前安全活動管理制度...............................................................................36
9.4.7安全技術(shù)交底管理制度...............................................................................37
9.4.8重大危險源旁站制度...................................................................................37
9.4.9個人防護用具管理制度...............................................................................37
9.4.10安全標志牌管理制度.................................................................................38
9.5安全生產(chǎn)保證措施..................................................................................................38
9.5.1組織保證.......................................................................................................38
9.5.2技術(shù)保證.......................................................................................................39
9.5.3施工保證.......................................................................................................40
第十章環(huán)境管理計劃..........................................................................................................41
10.1重大環(huán)境因素清單................................................................................................41
10.2環(huán)境保護措施........................................................................................................41
第十一章成品保護管理計劃..............................................................................................42
11.1成品保護管理組織和職責分工............................................................................42
11.2成品保護計劃及保證措施....................................................................................44
第十二章應(yīng)急預案..............................................................................................................44
12.1編制目的................................................................................................................44
12.2應(yīng)急處置領(lǐng)導小組................................................................................................44
12.3應(yīng)急資源................................................................................................................45
12.4應(yīng)急響應(yīng)................................................................................................................45
12.5突發(fā)事件應(yīng)急預案................................................................................................47
12.5.1觸電事故應(yīng)急處置.....................................................................................47
12.5.2車輛火災事故應(yīng)急處置.............................................................................47
12.5.3火災事故應(yīng)急處置.....................................................................................47
12.5.4機械傷害事故應(yīng)急處置.............................................................................48
第十三章防疫期間施工管理計劃......................................................................................48
13.1疫情防控管理目標................................................................................................48
III
13.2疫情防控管理體系................................................................................................49
13.2.1疫情防控工作小組.....................................................................................49
13.2.2疫情防控工作小組各崗位職責.................................................................49
13.3疫情防控管理制度................................................................................................50
13.3.1疫情防控培訓教育制度.............................................................................50
13.3.2疫情防控排查制度.....................................................................................50
13.3.3疫情防控信息報告制度.............................................................................50
13.3.4應(yīng)急救援制度.............................................................................................51
13.3.5疫情防控勞動保護管理制度.....................................................................51
13.3.6衛(wèi)生管理制度.............................................................................................51
13.3.7疫情防控責任制度.....................................................................................51
13.4疫情防控措施........................................................................................................51
13.5疫情防控應(yīng)急預案................................................................................................52
13.5.1編制目的.....................................................................................................52
13.5.2應(yīng)急處置領(lǐng)導小組.....................................................................................52
13.5.3應(yīng)急資源.....................................................................................................53
13.5.4應(yīng)急響應(yīng).....................................................................................................54
IV
第一章編制依據(jù)
1.1編制說明
本施工組織設(shè)計是根據(jù)《(鳳鳴山莊至鳳凰山西路)道路改建工程及鳳凰山西路(鳳祥
路至世紀大道)道路新建工程圖紙》和《(鳳鳴山莊至鳳凰山西路)道路改建工程及鳳凰山
西路(鳳祥路至世紀大道)道路新建工程招標文件》的要求,參考國家、地方及行業(yè)的法
律、法規(guī),結(jié)合工程特點和企業(yè)施工經(jīng)驗而編制,確保本工程質(zhì)量、工期、成本、安全、
文明施工、環(huán)保等目標的實現(xiàn)。
本工程所采用國家頒布的有關(guān)法律、行政法規(guī)及地方性法規(guī)、規(guī)定包括但不限于下
表中所列法律法規(guī)。
表1.1-1主要依據(jù)法律法規(guī)和條例一覽
序
法律、法規(guī)名稱編號
號
1《中華人民共和國合同法》
2《中華人民共和國建筑法》
3《中華人民共和國安全生產(chǎn)法》
4《中華人民共和國環(huán)境保護法》
5《中華人民共和國消防法》
6《建設(shè)工程質(zhì)量管理條例》
7《建設(shè)工程安全生產(chǎn)管理條例》
8《安全生產(chǎn)許可證條例》
9《危險性較大的分部分項工程安全管理規(guī)定》
10
本工程所采用的國家和地方現(xiàn)行的工程設(shè)計、施工驗收規(guī)范、工程質(zhì)量檢驗評定標
準、工程建設(shè)標準強制性條文,包括但不限于下表所列。
表1.1-2主要標準、規(guī)范及規(guī)程
序
標準名稱標準編號
號
1《城鎮(zhèn)道路工程施工與質(zhì)量驗收規(guī)范》CJJ1-2008
2CJJ2-2008
3CJJ89-2012
1
序
標準名稱標準編號
號
4《給水排水管道工程施工及驗收規(guī)范》GB50268-2008
5《給水排水構(gòu)筑物工程施工及驗收規(guī)范》GB50141-2008
6《混凝土結(jié)構(gòu)工程施工質(zhì)量驗收規(guī)范》GB50204-2015
7《混凝土結(jié)構(gòu)工程施工規(guī)范》GB50666-2011
8《砌體結(jié)構(gòu)工程施工質(zhì)量驗收規(guī)范》GB50203-2011
9《施工現(xiàn)場臨時用電安全技術(shù)規(guī)范》JGJ46-2005
10《鋼筋焊接及驗收規(guī)程》JGJ18-2012
11DB37/T5118-2018
12《城鎮(zhèn)道路養(yǎng)護技術(shù)規(guī)范》CJJ36-2016
13《公路工程技術(shù)標準》JTGB01-2014
14《公路路基施工技術(shù)規(guī)范》JTG/T3610-2023
15《公路瀝青路面施工技術(shù)規(guī)范》JTGF40-2004
16CJJ139-2010
17《公路土工試驗規(guī)程》JTGE40-2007
18《公路工程無機結(jié)合料穩(wěn)定材料試驗規(guī)程》JTGE51-2009
19《公路工程瀝青及瀝青混合料試驗規(guī)程》JTGE20-2011
20《公路路基路面現(xiàn)場測試規(guī)程》JTGE60-2023
21《公路工程集料試驗規(guī)程》JTGE42-2005
22《公路工程質(zhì)量檢驗評定標準第一冊土建工程》JTGF80/1-2017
23《瀝青路面施工及驗收規(guī)范》GB50092-1996
24《建筑樁基技術(shù)規(guī)范》JGJ94-2008
25《建筑工程冬期施工規(guī)程》JGJ/T104-2011
26《鋼筋機械連接技術(shù)規(guī)程》JGJ107-2016
27《建筑機械使用安全技術(shù)規(guī)程》JGJ33-2012
28《危險化學品重大危險源辨識》GB18218-2018
29工程測量規(guī)范(附條文說明)GB50026-2007
30招標文件
31投標文件
32設(shè)計圖紙
1.2編制原則
以國家現(xiàn)行的規(guī)范、標準、規(guī)程為基礎(chǔ),以科學、合理、安全、節(jié)能、環(huán)保為原則,
2
圍繞本工程的關(guān)鍵線路和重點項目統(tǒng)籌安排,在確保各節(jié)點工期,按要求實現(xiàn)的同時,
其他工程項目協(xié)調(diào)有序進行,施工進度安排力求均衡生產(chǎn),合理化配置設(shè)備、人力資源,
采用先進的施工技術(shù),在確保工程質(zhì)量和進度的前提下,降低成本、提高效益,健全質(zhì)
量保證體系,文明施工。
表1.2編制原則
序號類別內(nèi)容
執(zhí)行國家法1)認真貫徹國家有關(guān)工程建設(shè)的法律、法規(guī),執(zhí)行相關(guān)規(guī)范、標
1律、法規(guī)、規(guī)準、規(guī)程。
范標準、規(guī)程2)嚴格執(zhí)行工程建設(shè)程序,確保過程受控。
1)充分考慮現(xiàn)場可用周轉(zhuǎn)場地因素,合理進行現(xiàn)場平面布置,減
少材料二次運輸,確保工程順利施工和總工期目標實現(xiàn)。
2)充分考慮、優(yōu)化土方平衡和場內(nèi)調(diào)配,減少場外運輸,降低成
本損耗,組織有節(jié)奏、均衡和連續(xù)地施工。
2科學性合理性
3)優(yōu)先選用先進的施工技術(shù)、施工工藝;認真編寫各項實施計劃,
嚴格控制質(zhì)量、進度、成本和安全施工。
4)充分利用施工機械和設(shè)備,提高施工機械化、自動化程度,改
善勞動條件,提高生產(chǎn)率。
1)堅持“安全第一、預防為主”,編制安全文明施工和生態(tài)環(huán)境保
護措施,以及嚴防建筑振動、噪聲、粉塵及垃圾污染的技術(shù)組織措
施。
3安全節(jié)能環(huán)保
2)盡可能運用工具式和組裝式施工設(shè)施,努力減少施工設(shè)施的建
造量,科學規(guī)劃施工平面,提高場地利用率。
3)堅持“四節(jié)一環(huán)?!?、“綠色施工”
第二章工程概況
2.1工程建設(shè)概況
表2.1工程建設(shè)概況
工程名稱工程性質(zhì)
建設(shè)規(guī)模1143米工程地址
道路工程、排水工程、綜合
項目承包范
建設(shè)單位管線工程、橋梁工程、照明
圍
及交通工程等內(nèi)容
主要分包工
設(shè)計單位土方工程等
程
勘察單位合質(zhì)量100%。
3
監(jiān)理單位同工期180天
要
總承包單位中建x局第一建設(shè)有限公司求安全杜絕死亡及重傷事故
工程主要功
支路
能或用途
2.2設(shè)計概況
鳳祥路改建工程,項目設(shè)計范圍南起鳳鳴山莊大門南100米處,與已改建完成路段
順接,北至鳳凰山西路,道路全長860m,道路紅線寬度20,實施寬度15m
鳳凰山西路建設(shè)工程,西南起鳳祥路,橫跨韓侖河,東北至世紀大道,道路全長
283.02m,道路紅線寬度25m,實施寬度25m
其主要施工范圍包括:道路工程、排水工程、綜合管線工程、橋梁工程、照明及交
通工程等內(nèi)容。
2.2.1道路設(shè)計
表2.2.1道路設(shè)計技術(shù)指標
序號分類名稱內(nèi)容
1設(shè)計速度鳳祥路:30km/h,鳳凰山西路:40km/h
2路面設(shè)計標準軸載BZZ-100KN
3設(shè)計年限15年
4路面設(shè)計基準期15年
5路面橫坡機動車道1.5%,非機動車道、人行道2%
6道路最小凈空機動車道4.5m,非機動車道、人行道2.5m
7設(shè)計抗震等級按照抗震烈度7度設(shè)防
2.2.2路基結(jié)構(gòu)技術(shù)標準
表2.2.2路基結(jié)構(gòu)設(shè)計技術(shù)指標
序號分類名稱內(nèi)容
1路基邊坡邊坡坡度1:1.5
填方路基應(yīng)優(yōu)先選用級配較好的礫類土、砂類土
等粗粒土作為填料,填料最大粒徑小于150mm。
2路基填料淤泥、凍土、有機質(zhì)土、含草皮、生活垃圾、樹
根和腐殖質(zhì)的土嚴禁作為路基填料。液限大于
50%、塑性指數(shù)大于26、含水量不適宜直接壓
4
序號分類名稱內(nèi)容
實的細粒土,不得直接作為路堤填料;需要使用
時,必須采取技術(shù)措施進行處理,滿足設(shè)計要求
后方可使用。
(1)路基施工前應(yīng)對現(xiàn)狀場地清表處理,清表厚
度不小于0.3m。
(2)將現(xiàn)狀路面結(jié)構(gòu)破除后,開挖至路床頂部
3路基處理設(shè)計標高,如原狀路基土壓實度達不到設(shè)計指標
要求,應(yīng)采用路基土超挖換填。
(3)機動車道及非機動車道路床頂面以下采用
20cm厚的8%灰土換填處理。
2.3工程施工條件
2.3.1氣溫
14.3℃,累年極高氣溫為42.5℃,極低氣溫為-19.7℃,從每年氣溫統(tǒng)計值來看,其
氣溫呈逐漸增加的趨勢。
2.3.2降水量
669.3mm,年最小降水量為320.7mm,年最大降水量為1283.4mm,累年月最大降
水量為504.5mm,一日最大降水量為298.4mm;一日最大降雪量為190mm,一年之中
降水主要集中在六、七、八月份,多以暴雨形式降落,三個月的降水量占全年降水量的
65%。
2.3.3風速與風向
濟南地區(qū)主要以南、西南風向為主,累年極大風速為33.3m/s,最大月平均風速為
16.3m/s,最小月平均風速為1.0m/s。
2.3.4地下水情況
場地內(nèi)地下水埋深較深,勘探期間,在鉆孔深度范圍內(nèi)未測得地下水。本工程在開
挖深度范圍內(nèi)可不考慮地下水對基坑開挖的影響?;A(chǔ)施工時如遇降雨,可能在基巖中
產(chǎn)生上層滯水,或在基坑中積水,可采用集水明排方案排除坑內(nèi)積水。
2.3.5地質(zhì)情況
擬建場地位于坡洪積裙,勘探深度范圍內(nèi)地層主要為填土、坡洪積成因的黏性土、
等,下伏基巖為奧陶系石灰?guī)r。在鉆探深度范圍內(nèi)地層按其沉積年代及工程性質(zhì)可分為
5
4個大層及其亞層,自上而下分述如下:
2ml
(1)素填土(Q4):褐黃色,局部黃褐色,可塑,主要由黏性土組成,含少量碎石,
植物根系,土質(zhì)不均勻。該層分布普遍。層厚:0.50~1.60m,層底標高:125.42~
167.63m。
dl+pl
(2)黃土(Q4):褐黃色,硬塑~堅硬狀態(tài),黏粒含量一般,含白色鈣質(zhì)條紋,
零星姜石,具蟲孔。該層僅在里程樁號K2+000~K2+130路段分布。層厚:1.20~
2.10m,層底深度:1.70~2.60m,層底標高:163.18~166.43m。
dl+pl
(3)粉質(zhì)黏土(Q3):淺棕黃色,可塑~硬塑,土質(zhì)較均勻,刀切面較光滑,黏
粒含量稍多,含鐵錳氧化物,零星鐵錳結(jié)核。層厚:1.30m,層底深度:3.00m,層底標
高:165.13m。
(4)中風化石灰?guī)r(O1m):該層根據(jù)巖石完整程度及巖性地不同可分為較完整中風
化石灰?guī)r、破碎中風化石灰?guī)r、極破碎中風化石灰?guī)r和強風化泥灰?guī)r。該層未揭穿,最
大揭示厚度為25.00m,最大揭示深度為25.00m。
6
第三章施工總體部署
3.1總體組織安排
3.1.1項目組織機構(gòu)圖
項目經(jīng)理:孔健
進
度執(zhí)行經(jīng)理:胡士旗
管
理
領(lǐng)
項目技術(shù)負責人:張慧
導生產(chǎn)經(jīng)理合同商務(wù)負責人
層魯凱于德來
項目副總工:井文麟
質(zhì)量安全
總監(jiān)總監(jiān)
管
理技質(zhì)安工征商物綜
層術(shù)量試全程拆測務(wù)資合
管管驗管管協(xié)量合設(shè)辦
理理室理理調(diào)部約備公
部部部部部部部室
橋路路道管交
梁基面路線通
作
工工工附綜照
業(yè)
程程程屬合明
層
施施施施施施
工工工工工工
隊隊隊隊隊隊
圖3.1.1項目組織機構(gòu)圖
3.1.2項目主要管理人員崗位職責
表3.1.2項目管理人員及職責權(quán)限
序
崗位名稱姓名職責和權(quán)限
號
1)總負責策劃和落實項目總承包管理機構(gòu)的構(gòu)成及人員
配備,部署項目人員、材料、設(shè)備、資金等主要生產(chǎn)要素
項
的供給,保證項目有充足的資源組織施工;
目
2)總負責施工過程中與建設(shè)單位、監(jiān)理保持溝通和協(xié)調(diào),
領(lǐng)項目
1孔健具體落實建設(shè)單位和監(jiān)理安排的重大的事項;
導經(jīng)理
3)制定項目部管理規(guī)章制度,明確項目部部各部門和崗
班
位職責,保證項目管理的有效實施,處理各專業(yè)隊伍之間
子
重大的管理和協(xié)調(diào)問題;
4)總負責與建設(shè)單位的溝通聯(lián)系,負責各班組施工和項
7
序
崗位名稱姓名職責和權(quán)限
號
目管理人員的總協(xié)調(diào),主持編制項目施工組織設(shè)計,組織
實施項目管理的目標與方針,落實項目工期、質(zhì)量、成本、
安全文明施工等各項管理目標。
1)負責策劃和落實項目總承包管理機構(gòu)的構(gòu)成及人員配
備,部署項目人員、材料、設(shè)備、資金等主要生產(chǎn)要素的
供給,保證項目有充足的資源組織施工;
2)施工過程中與建設(shè)單位、監(jiān)理保持溝通和協(xié)調(diào),具體
落實建設(shè)單位和監(jiān)理安排的重大的事項;
3)制定項目部管理規(guī)章制度,明確項目部部各部門和崗
執(zhí)行
2胡士旗位職責,保證項目管理的有效實施,處理各專業(yè)隊伍之間
經(jīng)理
重大的管理和協(xié)調(diào)問題;
4)負責與建設(shè)單位的溝通聯(lián)系,負責各班組施工和項目
管理人員的總協(xié)調(diào),主持編制項目施工組織設(shè)計,組織實
施項目管理的目標與方針,落實項目工期、質(zhì)量、成本、
安全文明施工等各項管理目標。
5)項目經(jīng)理安排的其他工作。
1)負責項目部的深化設(shè)計和技術(shù)工作;
2)協(xié)調(diào)各施工隊之間的技術(shù)問題;
3)與設(shè)計、監(jiān)理保持正常溝通,保證設(shè)計、監(jiān)理的要求
與指令在各施工隊中貫徹實施;
4)組織對關(guān)鍵技術(shù)難題進行科技攻關(guān),進行新工藝、新
項目
技術(shù)的研究,確保項目順利進行;
技術(shù)
3張慧5)及時組織技術(shù)人員解決工程施工中出現(xiàn)的技術(shù)問題;
負責
6)直接領(lǐng)導各級技術(shù)人員,施工員和有關(guān)職能部門人員
人
的技術(shù)工作,承擔項目的技術(shù)領(lǐng)導責任,領(lǐng)導并推進項目
BIM技術(shù)應(yīng)用實施,貫徹執(zhí)行技術(shù)規(guī)范、標準,制訂施工
項目的技術(shù)管理制度,組織工程的施工驗收工作,領(lǐng)導工
程安全事故的預防和處理工作,組織工程的施工安全驗收
工作等。
1)負責項目部的深化設(shè)計和技術(shù)工作;
2)協(xié)調(diào)各施工隊之間的技術(shù)問題;
3)與設(shè)計、監(jiān)理保持正常溝通,保證設(shè)計、監(jiān)理的要求
與指令在各施工隊中貫徹實施;
4)組織對關(guān)鍵技術(shù)難題進行科技攻關(guān),進行新工藝、新
項目技術(shù)的研究,確保項目順利進行;
4副總張慧5)及時組織技術(shù)人員解決工程施工中出現(xiàn)的技術(shù)問題;
工6)直接領(lǐng)導各級技術(shù)人員,施工員和有關(guān)職能部門人員
的技術(shù)工作,承擔項目的技術(shù)領(lǐng)導責任,領(lǐng)導并推進項目
BIM技術(shù)應(yīng)用實施,貫徹執(zhí)行技術(shù)規(guī)范、標準,制訂施工
項目的技術(shù)管理制度,組織工程的施工驗收工作,領(lǐng)導工
程安全事故的預防和處理工作,組織工程的施工安全驗收
工作等。
1)對工程的施工生產(chǎn)、進度計劃全面負責,確保工程施
生產(chǎn)
5魯凱工順利進行;
經(jīng)理
2)負責各專業(yè)間的協(xié)調(diào)及配合,使專業(yè)工作之間的現(xiàn)場
8
序
崗位名稱姓名職責和權(quán)限
號
施工合理有序地進行,協(xié)調(diào)各施工隊之間的矛盾,協(xié)助制
定項目工期、質(zhì)量、成本、安全文明施工等各項管理目標、
措施;
3)組織落實各專業(yè)管理人員施工日常工作的實施,組織
各分項工程的施工、驗收工作等,及時解決施工中出現(xiàn)的
各種問題;
4)負責施工現(xiàn)場總平面管理;
5)負責項目外部政府監(jiān)督機構(gòu)溝通協(xié)調(diào)工作;
6)負責現(xiàn)場施工管理總協(xié)調(diào)工作。
1)在項目經(jīng)理的領(lǐng)導下,每月按時上報計量資料,及時
完成合約商務(wù)系統(tǒng)工作;
2)每月召開商務(wù)例會,盤點當月完成產(chǎn)值和成本情況;
商務(wù)
6于德來3)每月進行勞務(wù)、材料、機械設(shè)備等對施工隊伍的計量
經(jīng)理
審核,為財務(wù)支付提供依據(jù);
4)按時上報公司和建設(shè)單位的商務(wù)合約資料,與其他系
統(tǒng)聯(lián)動,共同完成相關(guān)工作。
質(zhì)量1)由公司委派,對本工程施工質(zhì)量具有一票否決權(quán);
7王志庫
監(jiān)總監(jiān)2)
督1)由公司委派,直接領(lǐng)導安全管理部;
人安全2)對安全、文明、綠色施工進行全面管理;
8云雪
員總監(jiān)3)對外關(guān)系協(xié)調(diào);
4)組織和指導安全文明創(chuàng)優(yōu)工作。
1)負責項目的生產(chǎn)組織、進度計劃落實、施工方案的實
施、工序協(xié)調(diào)、質(zhì)量控制等工作;
專業(yè)2)負責組織各專業(yè)間的協(xié)調(diào)配合;
9工程李揚3)負責結(jié)合進度計劃及其保證措施,對資源投入、勞動
師
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
- 6. 下載文件中如有侵權(quán)或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 湖南省永州市道縣2024-2025學年八年級上學期期中生物學試題(原卷版)-A4
- 熱工基礎(chǔ)模擬習題
- 養(yǎng)老院老人生活照料制度
- 養(yǎng)老院老人健康飲食營養(yǎng)師職業(yè)發(fā)展規(guī)劃制度
- 房頂防水安全合同協(xié)議書(2篇)
- 2024年版權(quán)轉(zhuǎn)讓合同標的及服務(wù)內(nèi)容擴展
- 2024年水利工程勞務(wù)分包合同示范范本(智慧水利)2篇
- 2024年生態(tài)環(huán)境保護修復工程合同
- 2025年南昌貨運從業(yè)資格考試題庫及答案大全
- 《密碼學英文》課件
- 監(jiān)理企業(yè)技術(shù)管理制度
- 2022版義務(wù)教育物理課程標準
- 山東省日照市2023-2024學年七年級上學期期末數(shù)學試題(含答案)
- 上海華東師大二附中2025屆高一數(shù)學第一學期期末檢測試題含解析
- 新教科版六年級上冊科學全冊知識點(期末總復習資料)
- 《靜女》《涉江采芙蓉》對比閱讀教學設(shè)計 2023-2024學年統(tǒng)編版高中語文必修上冊
- 高速鐵路概論 課件 第3章 高速鐵路車站
- 2024-2030年水培蔬菜行業(yè)市場發(fā)展分析及發(fā)展趨勢與投資戰(zhàn)略研究報告
- 2024年部編版語文五年級上冊全冊單元檢測題及答案(共8套)
- 集成電路制造工藝 課件 6光刻工藝2
- 建筑邊坡工程施工質(zhì)量驗收標準
評論
0/150
提交評論