,,,,,,,鋼板樁,,施工記錄,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,市政施·通—5,,,,,,,,,,
,,,,,,,,,,,,,,第,,1,頁,共4頁,,,,,,,,
"工程名稱
",,,增城廣場周邊110KV高壓線下地遷改工程(土建部分),,,,,工程部位,新城大道Y18~J14電纜溝,,,靜壓機(jī)型號,,,HD1430,,,,,累計樁數(shù),鋼板樁規(guī)格(mm),,樁長(m),深度(m),垂直度%
施工單位,,,廣州工程總承包集團(tuán)有限公司,,,,,分包單位,/,,,鋼板樁型號,,,拉森Ⅳ鋼板樁,,,,,#REF!,400*150*13.1,,6,5.96,99.9
序號,施工日期,,施工記錄情況,,,,,,,,,,,,,,備注,,,,,,,,
,,,樁長(m),深度(m),垂直度%,鋼板樁規(guī)格(mm),,施工長度(m),累計長度(m),累計樁數(shù)(根),開始時間,,結(jié)束時間,,,,,,,兩邊長度,溝長度,,,,
1,2021/7/12,,6,5.97,99.4,400*150*13.1,,3.2,3.2,8,7:43,,8:06,,,,,,,242,121,,,,
2,2021/7/12,,6,5.97,99.3,400*150*13.1,,3.2,6.4,16,8:07,,8:29,,,,,,,3.2,,,,,
3,2021/7/12,,6,5.96,99.1,400*150*13.1,,3.2,9.6,24,8:30,,8:52,,,,,,,,,,,,
4,2021/7/12,,6,5.98,99.4,400*150*13.1,,3.2,12.8,32,8:53,,9:16,,,,,,,,,,,,
5,2021/7/12,,6,5.97,99.1,400*150*13.1,,3.2,16.0,40,9:17,,9:40,,,,,,,,,新城大道Y18~J14電纜溝,,,
6,2021/7/12,,6,5.99,99.1,400*150*13.1,,3.2,19.2,48,9:41,,10:04,,,,,,,,,新城大道J15~J16電纜溝,,,
7,2021/7/12,,6,5.98,99.6,400*150*13.1,,3.2,22.4,56,10:05,,10:28,,,,,,,,,新城大道J16~J16+1電纜溝(第一段),,,
8,2021/7/12,,6,5.99,99.2,400*150*13.1,,3.2,25.6,64,10:29,,10:51,,,,,,,,,新城大道J16~J16+1電纜溝(第二段),,,
9,2021/7/12,,6,5.97,99.1,400*150*13.1,,3.2,28.8,72,10:52,,11:14,,,,,,,,,新城大道J16~J16+1電纜溝(第三段),,,
10,2021/7/12,,6,5.97,99.3,400*150*13.1,,3.2,32.0,80,11:15,,11:37,,,,,,,,,新城大道J16+2~Y20+1電纜溝,,,
11,2021/7/12,,6,5.98,99.1,400*150*13.1,,3.2,35.2,88,11:38,,12:01,,,,,,,,,,,,
12,2021/7/12,,6,5.98,99.6,400*150*13.1,,3.2,38.4,96,13:06,,13:29,,,,,,,,,,,,
13,2021/7/12,,6,5.98,99.2,400*150*13.1,,3.2,41.6,104,13:30,,13:53,,,,,,,,,,,,
14,2021/7/12,,6,5.97,99.6,400*150*13.1,,3.2,44.8,112,13:54,,14:16,,,,,,,,,,,,
15,2021/7/12,,6,5.99,99.8,400*150*13.1,,3.2,48.0,120,14:17,,14:40,,,,,,,,,,,,
16,2021/7/12,,6,5.96,99.6,400*150*13.1,,3.2,51.2,128,14:41,,15:04,,,,,,,,,,,,
17,2021/7/12,,6,5.98,99.5,400*150*13.1,,3.2,54.4,136,15:05,,15:28,,,,,,,,,,,,
18,2021/7/12,,6,5.98,99.6,400*150*13.1,,3.2,57.6,144,15:29,,15:51,,,,,,,,,,,,
19,2021/7/12,,6,5.98,99.6,400*150*13.1,,3.2,60.8,152,15:52,,16:15,,,,,,,,,,,,
20,2021/7/12,,6,5.98,99.5,400*150*13.1,,3.2,64.0,160,16:16,,16:38,,,,,,,,,,,,
施工員:,,,,,,質(zhì)檢員:,,,項目技術(shù)負(fù)責(zé)人:,,,,,日期:,年月日,,,,2021.5.27,,,,,,
,,,,,,,鋼板樁,,施工記錄,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,市政施·通—5,,,,,,,,,,
,,,,,,,,,,,,,,第,,2,頁,共4頁,,,,,,,,
"工程名稱
",,,增城廣場周邊110KV高壓線下地遷改工程(土建部分),,,,,工程部位,新城大道Y18~J14電纜溝,,,靜壓機(jī)型號,,,HD1430,,,,,累計樁數(shù),鋼板樁規(guī)格(mm),,樁長(m),深度(m),垂直度%
施工單位,,,廣州工程總承包集團(tuán)有限公司,,,,,分包單位,/,,,鋼板樁型號,,,拉森Ⅳ鋼板樁,,,,,#REF!,400*150*13.1,,6,5.97,99.5
序號,施工日期,,施工記錄情況,,,,,,,,,,,,,,備注,,,,,,,,
,,,樁長(m),深度(m),垂直度%,鋼板樁規(guī)格(mm),,施工長度(m),累計長度(m),累計樁數(shù)(根),開始時間,,結(jié)束時間,,,,,,,兩邊長度,溝長度,,,,
21,2021/7/12,,6,5.97,99.7,400*150*13.1,,3.2,67.2,168,16:39,,17:01,,,,,,,242,121,,,,
22,2021/7/12,,6,5.96,99.4,400*150*13.1,,3.2,70.4,176,17:02,,17:24,,,,,,,3.2,,,,,
23,2021/7/12,,6,5.96,99.6,400*150*13.1,,3.2,73.6,184,17:25,,17:48,,,,,,,,,,,,
24,2021/7/12,,6,5.97,99.5,400*150*13.1,,3.2,76.8,192,17:49,,18:11,,,,,,,,,,,,
25,2021/7/13,,6,5.99,99.6,400*150*13.1,,3.2,80.0,200,7:42,,8:05,,,,,,,,,,,,
26,2021/7/13,,6,5.96,99.0,400*150*13.1,,3.2,83.2,208,8:06,,8:28,,,,,,,,,,,,
27,2021/7/13,,6,5.98,99.7,400*150*13.1,,3.2,86.4,216,8:29,,8:51,,,,,,,,,,,,
28,2021/7/13,,6,5.98,99.6,400*150*13.1,,3.2,89.6,224,8:52,,9:14,,,,,,,,,,,,
29,2021/7/13,,6,5.97,99.7,400*150*13.1,,3.2,92.8,232,9:15,,9:38,,,,,,,,,,,,
30,2021/7/13,,6,5.98,99.2,400*150*13.1,,3.2,96.0,240,9:39,,10:02,,,,,,,,,,,,
31,2021/7/13,,6,5.98,99.2,400*150*13.1,,3.2,99.2,248,10:03,,10:25,,,,,,,,,,,,
32,2021/7/13,,6,5.98,99.2,400*150*13.1,,3.2,102.4,256,10:26,,10:48,,,,,,,,,,,,
33,2021/7/13,,6,5.98,99.3,400*150*13.1,,3.2,105.6,264,10:49,,11:12,,,,,,,,,,,,
34,2021/7/13,,6,5.97,99.3,400*150*13.1,,3.2,108.8,272,11:13,,11:36,,,,,,,,,,,,
35,2021/7/13,,6,5.98,99.8,400*150*13.1,,3.2,112.0,280,11:37,,11:59,,,,,,,,,,,,
36,2021/7/13,,6,5.97,99.6,400*150*13.1,,3.2,115.2,288,13:09,,13:32,,,,,,,,,,,,
37,2021/7/13,,6,5.97,99.1,400*150*13.1,,3.2,118.4,296,13:33,,13:56,,,,,,,,,,,,
38,2021/7/13,,6,5.99,99.2,400*150*13.1,,3.2,121.6,304,13:57,,14:20,,,,,,,,,,,,
39,2021/7/13,,6,5.98,99.1,400*150*13.1,,3.2,124.8,312,14:21,,14:43,,,,,,,,,,,,
40,2021/7/13,,6,5.99,99.3,400*150*13.1,,3.2,128.0,320,14:44,,15:07,,,,,,,,,,,,
施工員:,,,,,,質(zhì)檢員:,,,項目技術(shù)負(fù)責(zé)人:,,,,,日期:,年月日,,,,2021.5.27,,,,,,
,,,,,,,鋼板樁,,施工記錄,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,市政施·通—5,,,,,,,,,,
,,,,,,,,,,,,,,第,,3,頁,共4頁,,,,,,,,
"工程名稱
",,,增城廣場周邊110KV高壓線下地遷改工程(土建部分),,,,,工程部位,新城大道Y18~J14電纜溝,,,靜壓機(jī)型號,,,HD1430,,,,,累計樁數(shù),鋼板樁規(guī)格(mm),,樁長(m),深度(m),垂直度%
施工單位,,,廣州工程總承包集團(tuán)有限公司,,,,,分包單位,/,,,鋼板樁型號,,,拉森Ⅳ鋼板樁,,,,,#REF!,400*150*13.1,,6,5.98,99.8
序號,施工日期,,施工記錄情況,,,,,,,,,,,,,,備注,,,,,,,,
,,,樁長(m),深度(m),垂直度%,鋼板樁規(guī)格(mm),,施工長度(m),累計長度(m),累計樁數(shù)(根),開始時間,,結(jié)束時間,,,,,,,兩邊長度,溝長度,,,,
41,2021/7/13,,6,5.98,99.0,400*150*13.1,,3.2,131.2,328,15:08,,15:30,,,,,,,242,121,,,,
42,2021/7/13,,6,5.97,99.2,400*150*13.1,,3.2,134.4,336,15:31,,15:53,,,,,,,3.2,,,,,
43,2021/7/13,,6,5.99,99.7,400*150*13.1,,3.2,137.6,344,15:54,,16:16,,,,,,,,,,,,
44,2021/7/13,,6,5.96,99.4,400*150*13.1,,3.2,140.8,352,16:17,,16:40,,,,,,,,,,,,
45,2021/7/13,,6,5.98,99.2,400*150*13.1,,3.2,144.0,360,16:41,,17:03,,,,,,,,,,,,
46,2021/7/13,,6,5.98,99.7,400*150*13.1,,3.2,147.2,368,17:04,,17:27,,,,,,,,,,,,
47,2021/7/13,,6,5.97,99.1,400*150*13.1,,3.2,150.4,376,17:28,,17:50,,,,,,,,,,,,
48,2021/7/13,,6,5.97,99.6,400*150*13.1,,3.2,153.6,384,17:51,,18:14,,,,,,,,,,,,
49,2021/7/14,,6,5.97,99.3,400*150*13.1,,3.2,156.8,392,7:50,,8:12,,,,,,,,,,,,
50,2021/7/14,,6,5.96,99.7,400*150*13.1,,3.2,160.0,400,8:13,,8:36,,,,,,,,,,,,
51,2021/7/14,,6,5.98,99.5,400*150*13.1,,3.2,163.2,408,8:37,,8:59,,,,,,,,,,,,
52,2021/7/14,,6,5.96,99.4,400*150*13.1,,3.2,166.4,416,9:00,,9:23,,,,,,,,,,,,
53,2021/7/14,,6,5.98,99.4,400*150*13.1,,3.2,169.6,424,9:24,,9:47,,,,,,,,,,,,
54,2021/7/14,,6,5.98,99.1,400*150*13.1,,3.2,172.8,432,9:48,,10:10,,,,,,,,,,,,
55,2021/7/14,,6,5.97,99.5,400*150*13.1,,3.2,176.0,440,10:11,,10:33,,,,,,,,,,,,
56,2021/7/14,,6,5.99,99.1,400*150*13.1,,3.2,179.2,448,10:34,,10:57,,,,,,,,,,,,
57,2021/7/14,,6,5.97,99.3,400*150*13.1,,3.2,182.4,456,10:58,,11:21,,,,,,,,,,,,
58,2021/7/14,,7,5.96,99.0,400*150*13.2,,3.2,185.6,464,11:22,,11:45,,,,,,,,,,,,
59,2021/7/14,,8,5.97,99.5,400*150*13.3,,3.2,188.8,472,11:46,,12:09,,,,,,,,,,,,
60,2021/7/14,,9,5.96,99.4,400*150*13.4,,3.2,192.0,480,13:19,,13:41,,,,,,,,,,,,
施工員:,,,,,,質(zhì)檢員:,,,項目技術(shù)負(fù)責(zé)人:,,,,,日期:,年月日,,,,2021.5.27,,,,,,
,,,,,,,鋼板樁,,施工記錄,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,市政施·通—5,,,,,,,,,,
,,,,,,,,,,,,,,第,,4,頁,共4頁,,,,,,,,
"工程名稱
",,,增城廣場周邊110KV高壓線下地遷改工程(土建部分),,,,,工程部位,新城大道Y18~J14電纜溝,,,靜壓機(jī)型號,,,HD1430,,,,,累計樁數(shù),鋼板樁規(guī)格(mm),,樁長(m),深度(m),垂直度%
施工單位,,,廣州工程總承包集團(tuán)有限公司,,,,,分包單位,/,,,鋼板樁型號,,,拉森Ⅳ鋼板樁,,,,,#REF!,400*150*13.1,,6,5.98,99.7
序號,施工日期,,施工記錄情況,,,,,,,,,,,,,,備注,,,,,,,,
,,,樁長(m),深度(m),垂直度%,鋼板樁規(guī)格(mm),,施工長度(m),累計長度(m),累計樁數(shù)(根),開始時間,,結(jié)束時間,,,,,,,兩邊長度,溝長度,,,,
61,2021/7/14,,6,5.97,99.5,400*150*13.1,,3.2,195.2,488,13:42,,14:04,,,,,,,242,121,,,,
62,2021/7/14,,6,5.98,99.1,400*150*13.1,,3.2,198.4,496,14:05,,14:28,,,,,,,3.2,,,,,
63,2021/7/14,,6,5.97,99.6,400*150*13.1,,3.2,201.6,504,14:29,,14:52,,,,,,,,,,,,
64,2021/7/14,,6,5.96,99.0,400*150*13.1,,3.2,204.8,512,14:53,,15:16,,,,,,,,,,,,
65,2021/7/14,,6,5.99,99.5,400*150*13.1,,3.2,208.0,520,15:17,,15:39,,,,,,,,,,,,
66,2021/7/14,,6,5.98,99.8,400*150*13.1,,3.2,211.2,528,15:40,,16:03,,,,,,,,,,,,
67,2021/7/14,,6,5.96,99.8,400*150*13.1,,3.2,214.4,536,16:04,,16:26,,,,,,,,,,,,
68,2021/7/14,,6,5.97,99.7,400*150*13.1,,3.2,217.6,544,16:27,,16:49,
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 柴油運(yùn)輸合同環(huán)保設(shè)施投入?yún)f(xié)議
- 2024年福州市羅源生態(tài)環(huán)境局招聘筆試真題
- 校醫(yī)個人工作總結(jié)1000字(32篇)
- 行政組織的人力資源戰(zhàn)略與績效關(guān)系研究試題及答案
- 農(nóng)村合作社農(nóng)產(chǎn)品供應(yīng)鏈協(xié)作合同書
- 數(shù)據(jù)庫性能監(jiān)控與調(diào)優(yōu)試題及答案
- 醫(yī)學(xué)影像技術(shù)診斷與實(shí)踐試題集
- 籃球裁判員考試試題及答案大全
- 游艇代理合同協(xié)議書
- 燈具行業(yè)的工作報告
- 材料科學(xué)基礎(chǔ)基礎(chǔ)知識點(diǎn)總結(jié)
- 防錯系統(tǒng)“紅兔子”使用作業(yè)指導(dǎo)文件PPT課件
- 醫(yī)學(xué)倫理審查申請表1
- 數(shù)控銑工圖紙(60份)(共60頁)
- 香樟栽植施工方案
- 惠州市出租車駕駛員從業(yè)資格區(qū)域科目考試題庫(含答案)
- 加工設(shè)備工時單價表
- 高脂血癥藥物治療ppt課件
- 高層建筑等電位聯(lián)結(jié)安裝技術(shù)分析探討
- 模型預(yù)測控制(課堂PPT)
- OQC出貨檢驗(yàn)規(guī)范及方法
評論
0/150
提交評論