文檔簡介
片石混凝土擋土墻施工方案資料內(nèi)容僅供參考,如有不當(dāng)或者侵權(quán),請聯(lián)系本人改正或者刪除。合三路滑坡整治工程施工組織設(shè)計編制日期:二0一二年七月目錄編制說明········································編制依據(jù)及原則··································2.1編制依據(jù)·····································2.2編制原則·····································三、工程管理目標(biāo)·····································四、工程概況·········································4.1工程地理位置·································4.2施工場地周圍環(huán)境·····························4.3工程地質(zhì)·····································4.4工程范圍及規(guī)?!ぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁ?.5工程主要特點·································五、設(shè)備、人員動員周期及材料組織供應(yīng)··················5.1人員、設(shè)備動員周期····························5.2技術(shù)準(zhǔn)備······································5.3材料組織供應(yīng)··································六、施工準(zhǔn)備及臨時設(shè)施·······························6.1臨時房屋設(shè)施··································6.2水、電設(shè)施····································施工組織機構(gòu)的建立·······························7.1組織機構(gòu)設(shè)置·································7.2施工組織管理機構(gòu)的運作························八、施工計劃··········································工期進度計劃·································各施工隊伍人員構(gòu)成···························施工設(shè)備計劃·································材料供應(yīng)計劃及措施···························九、施工方法··········································9.1擋土墻構(gòu)造····································9.2填土施工要求··································9.3施工工藝流程··································9.4衡重式擋土墻施工······························十、工程質(zhì)量保證措施···································10.1技術(shù)保證措施·································10.2質(zhì)量管理措施·································10.3施工組織措施·································十一、安全保證措施:····································11.1安全施工主要措施·····························11.2安全保證體系·································十二、文明施工,加強環(huán)?!ぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁ?2.1文明施工·····································12.2施工現(xiàn)場環(huán)境保護····························12.3綠化工作措施·································十三、施工進度保證措施:································13.1一般保證措施·································13.2組織保證措施·································13.3技術(shù)保證措施·································13.4.經(jīng)濟保證措施··································13.5.合同保證措施··································十四、雨季施工技術(shù)措施·································十五、采用新工藝新技術(shù)成本節(jié)約措施·····················十六、施工現(xiàn)場平面布置圖·······························16.1施工總平面布置································16.2施工總平面布置······························· 施工組織設(shè)計編制說明在編制本標(biāo)的工程施工組織設(shè)計的過程中,我們仔細(xì)閱讀了招標(biāo)文件。在認(rèn)真閱讀和充分理解設(shè)計意圖的基礎(chǔ)上,結(jié)合我公司的施工經(jīng)驗,根據(jù)施工場地狀況,以信守合同、確保質(zhì)量工期、安全文明生產(chǎn)、持續(xù)注重環(huán)保、合理控制工程造價為指導(dǎo)思想,經(jīng)過細(xì)心研究形成了本施工組織設(shè)計主要內(nèi)容,其中闡述了本工程實施時的施工設(shè)備、施工計劃安排、施工技術(shù)方案、施工組織實施方法及順序,確保工程質(zhì)量和工期的主要措施,以及安全、文明、環(huán)境保護措施。在編制過程中,擇優(yōu)選擇施工方案,做到科學(xué)合理、經(jīng)濟方便,為工程施工統(tǒng)籌安排提供技術(shù)支持。編制依據(jù)及原則2.1編制依據(jù)1、擋土墻工程招標(biāo)文件、設(shè)計圖紙及有關(guān)參考資料。2、我公司的施工現(xiàn)場考察及標(biāo)前有關(guān)會議精神。3、《公路工程技術(shù)標(biāo)準(zhǔn)》(JTGB01-);《公路路基設(shè)計規(guī)范》(JTGD30-);《建筑邊坡工程技術(shù)規(guī)范》(GB50330-202);《建筑地基基礎(chǔ)設(shè)計規(guī)范》(GB50007-);《公路水泥混凝土路面設(shè)計規(guī)范》(JTGD40-);及現(xiàn)行國家和相關(guān)標(biāo)準(zhǔn)及規(guī)范。2.2編制原則1、根據(jù)工程特點、自然條件及工期要求,在確保工程質(zhì)量與施工安全的前提下,采用科學(xué)合理的施工作業(yè)方法,籌劃人力安排,調(diào)配所需的機械設(shè)備,以滿足施工生產(chǎn)的需要,確保人力、物力充分發(fā)揮作用,使績效最大化。2、詳細(xì)辨別各分項工程之間的施工順序和相互制約關(guān)系,認(rèn)真研究,統(tǒng)籌安排,理清控制因素與被控制因素,形成連貫合理的施工工藝流程。3、對施工的重點工序和難點工序進行科學(xué)分析、采用成熟的施工技術(shù)和經(jīng)驗,做到切實可行、合理經(jīng)濟。4、根據(jù)各級政府部門質(zhì)量、安全、文明施工、環(huán)境保護要求,建立各項保證體系前制定完善的保證措施,確保施工生產(chǎn)各項管理目標(biāo)的順利實現(xiàn)。5、充分利用我公司人力資源、機具設(shè)備、可動員資源以及工程區(qū)域內(nèi)可利用的社會資源。三、工程管理目標(biāo)工期目標(biāo):90天質(zhì)量目標(biāo):工程一次驗收合格率100%,合同履約率達100%。安全目標(biāo):執(zhí)行國家頒布的各種施工安全規(guī)程,杜絕傷亡、重大交通、火災(zāi)、機損等事故。環(huán)境目標(biāo):保護環(huán)境,文明施工。根據(jù)國家有關(guān)政策,保護好沿線自然生態(tài)環(huán)境,滅塵降噪,減少污染。掛牌上崗、文明施工。四、工程概況4.1工程地理位置合三路為雙流至簡陽三岔湖一旅游公路,按三級公路標(biāo)準(zhǔn)修建;本次滑坡(含路基垮塌)3處工點主要集中在白三路K8+365~K9+133路段范圍內(nèi)。4.2工程范圍及規(guī)模本項目裝置區(qū)域范圍內(nèi)的擋土墻施工將結(jié)合地形,根據(jù)地質(zhì)報告及埋深構(gòu)造,采用衡重式擋土墻,確定擋土墻的基槽開挖的深度和放坡,并最大限度減少土石方工程量。施工單位按照擋土墻的范圍進行施工和回填。4.3工程主要特點1、本工程土石方量大,施工作業(yè)面長,工期短,且各段分段施工采用不同類型的擋土墻施工。2、施工時要充分考慮在施工過程中對相鄰工廠生產(chǎn)和場平施工單位的影響,做好安全防范措施。3、本工程擋土墻分為衡重式C20片石擋土墻。4、施工時需組織好基槽開挖、堆放、運輸、工程測量等作業(yè),做到安全文明施工。5、在擋土墻施工過程中要與場平施工單位密切配合,確保擋土墻后填料對稱、均勻回填和場平回填質(zhì)量。五、設(shè)備、人員動員周期及材料組織供應(yīng)5.1人員、設(shè)備動員周期1、我司有成套的施工設(shè)備,有豐富的工程施工經(jīng)驗,擁有各類工程技術(shù)人員、施工管理人員和熟練的機械操作手和熟練的勞工隊伍。在簽署合同協(xié)議后在業(yè)主規(guī)定的進場時間內(nèi),組織人員、施工機械及設(shè)備進場并展開作業(yè)。進場后主要工作是清理現(xiàn)場、接通施工點的水電、通訊,安裝機械、搭建臨時房屋、水池、作好混凝土、砂漿施工配合比等。2、各種專用設(shè)備、材料進場采用汽車運輸?shù)姆绞竭M行,并安裝、調(diào)試完畢,能及時投入生產(chǎn)使用。3、在施工設(shè)備進場的同時,組織所有進入該項目的工程技術(shù)人員和工程管理人員分批進入施工現(xiàn)場,開始項目經(jīng)理部的籌建工作。4、人員安排表序號人員人數(shù)備注1管理人員42技術(shù)人員63施工人員505.2技術(shù)準(zhǔn)備人員進場后立即開展技術(shù)準(zhǔn)備工作,技術(shù)準(zhǔn)備工作分為內(nèi)業(yè)準(zhǔn)備工作和外業(yè)準(zhǔn)備工作。1、內(nèi)業(yè)準(zhǔn)備1)、審核、分析設(shè)計圖紙,提供實施性施工圖紙。2)、臨時工程的設(shè)計與施工,包括料場建設(shè)、臨時用房修建、臨時施工便道的修建等。3)、編寫實施性施工組織設(shè)計,對施工具體人員安排、機械設(shè)備配備、場地布置、施工工序、施工進度都做具體周密的說明。4)、編制質(zhì)量計劃,落實質(zhì)量管理體系、提出質(zhì)量管理標(biāo)準(zhǔn)、明確保障措施。5)、編制施工工藝標(biāo)準(zhǔn)及保證措施,一切要以技術(shù)規(guī)范、設(shè)計圖紙為準(zhǔn)則。6)、制定技術(shù)管理辦法和實施細(xì)則,盡量作到細(xì)而準(zhǔn)。7)、進行崗前培訓(xùn),著重培訓(xùn)員工的崗位職業(yè)技能、工程質(zhì)量意識、安全生產(chǎn)意識。2、外業(yè)準(zhǔn)備1)、租賃項目部辦公和生活用房。2)、平整臨時場地,清理施工現(xiàn)場。3)、測量控制體系的建立。4)、各類實驗儀器的配備。5)、各類施工設(shè)備的安裝和調(diào)試。5.3材料組織供應(yīng)1、水泥:擬采用水泥廠生產(chǎn)的合格水泥進行施工,用汽車運至施工現(xiàn)場。2、鋼材(鋼筋)擬從市區(qū)或就近購買,用汽車運至施工現(xiàn)場。3、碎石、砂:擬從沿線各料場購買,用汽車運至施工現(xiàn)場。其余小型材料就近組織購買,運抵施工現(xiàn)場。六、施工準(zhǔn)備及臨時設(shè)施6.1臨時房屋設(shè)施項目經(jīng)理部準(zhǔn)備在現(xiàn)場附近租用民房。以方便與業(yè)主、監(jiān)理、當(dāng)?shù)卣嚷?lián)系。6.2水、電設(shè)施1、施工用水、用電沿線水源豐富,在工地修建蓄水池,經(jīng)過潛水泵、輸水管送至施工點的方法解決。2、生產(chǎn)、生活用電生產(chǎn)用電采用化工園區(qū)內(nèi)的高壓電源。生活用電可取自當(dāng)?shù)鼐用裼秒娋W(wǎng)。生活用水則取自當(dāng)?shù)仫嬘盟c。在施工區(qū),生活用電可下接高壓線或自備發(fā)電機組供給,生活用水則取自當(dāng)?shù)仫嬘盟c或自備井供應(yīng)?;炷涟韬蛨龌炷劣缮袒煺居蒙袒燔囘\送至現(xiàn)場。4、交通、通訊項目經(jīng)理部安裝電話、傳真機,以便于和業(yè)主、監(jiān)理及當(dāng)?shù)卣3致?lián)系。每個施工隊用手機于與經(jīng)理部保持聯(lián)系,協(xié)調(diào)工作,保持項目部與施工隊統(tǒng)一指揮、協(xié)調(diào)。充分利用電腦、電子信箱,與外界進行信息交換與溝通,獲取對本項目有用的信息。項目部配備行政車、材料采購車、生活用車各一臺,解決各施工隊的交通、材料及平時生活問題。施工組織機構(gòu)的建立7.1組織機構(gòu)設(shè)置1、我公司高度重視本工程,一旦中標(biāo)本工程將列為我公司的重點工程,為優(yōu)質(zhì)按期完成本工程施工任務(wù),在全公司范圍內(nèi)抽調(diào)管理水平高、具有豐富施工經(jīng)驗的人員組成施工項目經(jīng)理部。項目經(jīng)理部下設(shè)六個職能部門,配備足夠數(shù)量且具有施工管理和施工經(jīng)驗的技術(shù)及各專業(yè)骨干,負(fù)責(zé)工程建設(shè)全過程的管理、組織、協(xié)調(diào),以確保各項工程管理目標(biāo)的實現(xiàn),按對項目法人的要求控制工程進度、質(zhì)量、安全和文明施工等。2、項目經(jīng)理部設(shè)項目經(jīng)理一人,總工程師一人,調(diào)度指揮一人,副經(jīng)理一人,項目部內(nèi)設(shè)施工技術(shù)科、安全質(zhì)量科、計劃財務(wù)科、物資設(shè)備科、測試中心、綜合辦公室六個職能部門。7.2施工組織管理機構(gòu)的運作1、主要管理人員配備、項目經(jīng)理部的項目經(jīng)理由本公司具有豐富施工經(jīng)驗、承擔(dān)過類似工程建設(shè)的工程師擔(dān)任,負(fù)責(zé)施工生產(chǎn)過程的組織、指揮及協(xié)調(diào)工作。項目經(jīng)理部的副經(jīng)理和總工程師按各自分管責(zé)任,指派有豐富經(jīng)驗的人員擔(dān)任。、專業(yè)技術(shù)負(fù)責(zé)人,按照相關(guān)專業(yè),配備多人配合項目總工程師做好施工技術(shù)管理工作。2、管理職能部門及工作1)、項目經(jīng)理部的管理機構(gòu)為施工技術(shù)科、安全質(zhì)量科、計劃財務(wù)科、物資設(shè)備科、測試中心、綜合辦公室六個職能部門。每個部門按責(zé)任制執(zhí)行,有條不紊開展工作。2)、項目經(jīng)理部的施工技術(shù)科、安全質(zhì)量科等部門派專人指導(dǎo)現(xiàn)場的相關(guān)工作,并與業(yè)主、監(jiān)理、設(shè)計院及有關(guān)單位、部門保持有效聯(lián)系,及時解決施工中出現(xiàn)的各種問題。八、施工計劃工期進度計劃1、本工程施工總工期為90天日歷天。2、開工日期以甲方下達的開工令為準(zhǔn),在規(guī)定的施工日歷天之內(nèi),全部工程應(yīng)完成,并經(jīng)過驗收。3、施工工期進度計劃:根據(jù)業(yè)主的要求,我公司將該工程的工期定為90天:1)、施工準(zhǔn)備期:在接到業(yè)主的中標(biāo)通知書后一周內(nèi),我公司將組織人員進入施工現(xiàn)場開始施工前期工作,作施工前的各項準(zhǔn)備工作。預(yù)計在5天內(nèi)完成。2)、施工期:在準(zhǔn)備工作完成后,將展開全面施工作業(yè),采用流水作業(yè)分隊分段施工,將按照事前制定的計劃有條不紊的進行各項工作,預(yù)計在77天內(nèi)完成。3)、施工收尾及交驗期:主體工程完工后,在最后8天內(nèi)應(yīng)加緊其余零星工程的施工和工程的全面清理工作,以達到業(yè)主要求的工程交工條件。4、我公司就上述工期節(jié)點要求,結(jié)合施工現(xiàn)場實際情況,對本工程施工計劃進行了科學(xué)合理的安排,根據(jù)我公司以往施工經(jīng)驗,我們完全有能力在甲方指定的工期內(nèi)順利完成本工程。施工設(shè)備計劃1、為滿足施工生產(chǎn),落實施工機械配置計劃,以單位主要領(lǐng)導(dǎo)掛帥,快速抽調(diào)足夠數(shù)量性能良好的機械設(shè)備運抵施工現(xiàn)場。對于個別類型的機械,數(shù)量不足的,將采取新購或租賃的辦法補齊。2、主要機械設(shè)備配制序號機械名稱規(guī)格單位數(shù)量1內(nèi)燃空壓機V-3.5/3臺62混凝土振動棒ZN35臺43混凝土攪拌機J500臺24抽水機ф100mm臺35履帶式挖掘機1m3臺16自動翻斗車5t臺47鋼筋切割機HGQ40臺28鋼筋彎曲機HGW40臺29全站儀NTS-202臺210經(jīng)緯儀M310378臺211水準(zhǔn)儀M214516臺212電焊機BX1-500臺28.3各施工隊伍人員構(gòu)成1、項目經(jīng)理部在選擇施工隊伍時,注重進場隊伍的施工信譽、人員的技術(shù)素質(zhì)、配套情況及近階段的實際表現(xiàn),施工能力和施工質(zhì)量能否滿足需要。2、對進場的隊伍實施動態(tài)管理,不允許擅自擴充和隨意抽調(diào),以確保施工隊伍的素質(zhì)和人員相對穩(wěn)定。3、未經(jīng)有關(guān)質(zhì)量、安全方面培訓(xùn)的操作工人不許上崗。凡進場的隊伍必須配備一定數(shù)量的專職協(xié)調(diào)質(zhì)量、安全的管理人員。材料供應(yīng)計劃及措施1、本工程材料供應(yīng)由項目經(jīng)理部統(tǒng)一負(fù)責(zé)。材料供應(yīng)將采取統(tǒng)一采購、統(tǒng)一調(diào)運的原則進行,所有材料的供應(yīng)均應(yīng)符合業(yè)主提出的要求,并得到監(jiān)理工程師的同意。2、所有用于本工程的材料、貨物和各種類型的物品,無論是天然狀態(tài)的、經(jīng)過加工的或者是制造出來的均應(yīng)該是新的,并符合合同要求的類型和質(zhì)量。3、作為用于正式工程中的材料和制成品的樣品(包括材料樣品和工地現(xiàn)場制成品的樣品),經(jīng)監(jiān)理工程師批準(zhǔn)后,由施工單位妥善保存至監(jiān)理工程師準(zhǔn)許其自行處理時為止。4、當(dāng)技術(shù)規(guī)范或有關(guān)的參照標(biāo)準(zhǔn)要求有材料生產(chǎn)商和供應(yīng)商的測試證明書時,施工單位將提供每份證明書的原件或復(fù)印件。證明書對被證明的材料采用系列編號或參考編號,使人一目了然。證明書中包括有關(guān)參考標(biāo)準(zhǔn)和技術(shù)規(guī)定條款所要求的內(nèi)容。5、施工單位將對全部材料的取樣和測試,施工工藝,設(shè)備和量測裝置進行日常檢查,以控制其質(zhì)量并保證它們與技術(shù)規(guī)定和批準(zhǔn)的試樣相一致。6、施工單位做材料與試樣的試驗,委托由監(jiān)理工程師批準(zhǔn)的、具有相應(yīng)資質(zhì)的試驗單位來承擔(dān)。7、材料質(zhì)量是工程質(zhì)量的生命,為此必須嚴(yán)格控制材料進貨渠道,把好材料質(zhì)量關(guān),做好質(zhì)量自檢工作。九、施工組織①、施工準(zhǔn)備1.1圖紙審核及原地貌復(fù)測,發(fā)現(xiàn)圖紙有誤或現(xiàn)場與設(shè)計不符的及時上報相關(guān)人員進行復(fù)查。1.2擋墻片石選用質(zhì)地堅實、無風(fēng)化剝落及抗壓強度不低于MU30片石。1.3選用C20混凝土。1.4修建臨時施工便道、布置材料堆放場地及備料。2、施工工藝流程(見下圖)施工準(zhǔn)備測量放線流水導(dǎo)流挖除換填機械碾壓夯實基槽開挖地基承載力檢測立模加固安裝泄水孔做濾水層澆筑混凝土并人工擺片石拆除模板養(yǎng)護3、施工方案3.1施工場地準(zhǔn)備3.1.1測量放線,定出樁位中心線及開挖邊界線。3.1.2清除擋墻用地范圍內(nèi)的樹樁、雜草、垃圾等所有障礙物;在基槽周圍挖設(shè)排水溝,排除地表水。3.2開挖
3.2.1基槽開挖采用1.2m3斗容量的日立液壓挖掘機一臺進行基槽開挖,開挖長度根據(jù)現(xiàn)場地質(zhì)情況進行分段開挖,每段15或20米。機械開挖至基底設(shè)計標(biāo)高以上10cm時,重新進行測量放樣,確定開挖正確不偏位的情況下改用人工進行基底清理,確保基底符合設(shè)計及相關(guān)規(guī)范要求。3.3基礎(chǔ)施工3.3.1片石混凝土采用沿槽澆筑,澆筑過程中,選用高性能砼,嚴(yán)格控制配合比,砼中片石的摻量控制在25%范圍以內(nèi)。片石用人工擺放,分散布置。
3.3.2采用插入式50型振動棒進行振搗,砼振搗密實,振搗過程中快插慢抽。無漏振,無蜂窩麻面等。3.3.3砼澆筑完成后及時養(yǎng)護,防止由于內(nèi)外溫差過大而產(chǎn)生砼收縮開裂。3.3.4在片石砼澆筑過程中,現(xiàn)場取樣制作砼試件,標(biāo)準(zhǔn)養(yǎng)護28天后送中心試驗室檢測。3.4墻身澆筑
3.4.1基礎(chǔ)澆筑完成后,根據(jù)設(shè)計圖及現(xiàn)場高程放出擋墻澆筑邊線。3.4.2模板安裝.(1)模板采用膠合木模板,禁止使用有缺角、破損的模板。(2)保證混凝土結(jié)構(gòu)和構(gòu)件各部分設(shè)計形狀尺寸和相互間位置正確;(3)具有足夠的強度、剛度和穩(wěn)定性,能承受新澆筑混凝土的重力側(cè)壓力及施工中可能產(chǎn)生的各項負(fù)荷。(4)模板的接縫不得漏漿;在澆筑砼前,木模板應(yīng)澆水濕潤,但模板內(nèi)不應(yīng)有積水(5)模板與砼的接觸面應(yīng)清理干凈并涂刷脫膜劑,但不得影響模板結(jié)構(gòu)性能。模板使用后應(yīng)按規(guī)定修整保存。(6)模板之間粘貼雙面不干膠帶,以減小模板縫防止漏漿,以保證砼面的觀感質(zhì)量。(7)模板采用M14×500螺栓與預(yù)埋鋼筋拉結(jié)配D48×3.5鋼架管橫、豎龍骨加固,并配以大號蝶形卡緊固,對拉螺桿按1000×500的間距布置,設(shè)置時將泄水孔位置與螺桿緊貼布置,以防扔填片石碰壞PVC管.緊貼模板的豎向龍骨間距不得大于300㎜。3.4.3澆筑砼(1)混凝土澆筑前應(yīng)做好如下準(zhǔn)備工作:a)制定澆筑工藝,明確結(jié)構(gòu)分段分塊的間隔澆筑順序,先澆筑基礎(chǔ)混凝土,由于墻身較高,因此決定墻身混凝土分兩次澆筑完成,施工縫接茬采用片石連接,片石規(guī)格不得小于15cm,間距不得小于15cm,且距模板邊緣的距離不得小于25cm。b)根據(jù)結(jié)構(gòu)截面尺寸大小研究確定必要的防溫防裂措施。c)施工前應(yīng)仔細(xì)檢查模版、預(yù)埋件的緊固程度。(2)澆筑混凝土?xí)r應(yīng)符合下列要求:a)混凝土應(yīng)分層進行澆筑,不得隨意留置施工縫。b)混凝土澆筑應(yīng)連續(xù)進行。當(dāng)因故間歇時,其間歇時間應(yīng)小于前層混凝土的初凝時間或能重塑的時間。不同混凝土的允許間歇時間應(yīng)根據(jù)環(huán)境溫度、水泥性能。水膠比和外加劑類型等條件經(jīng)過試驗確定。d)新澆混凝土與鄰接的已硬化混凝土或巖土介質(zhì)間的溫差不得大于15℃。f)在澆筑混凝土過程中或澆筑完成時,如混凝土表面泌水較多,須在不擾動已澆筑混凝土的條件下,采取措施減少泌水。g)澆筑混凝土期間,應(yīng)設(shè)專人檢查模板穩(wěn)定情況,發(fā)現(xiàn)有松動、變形、移位時應(yīng)及時處理。h)澆筑混凝土?xí)r,應(yīng)填寫混凝土施工記錄。i)自高處向模板內(nèi)傾卸混凝土?xí)r,為防止混凝土離析,一般應(yīng)滿足下列要求:從高處直接傾卸時,混凝土傾落高度不宜超過2m,以不發(fā)生離析為度。g)在混凝土施工縫處接續(xù)澆筑新混凝土?xí)r,一般應(yīng)滿足下列要求:抗?jié)B要求的混凝土結(jié)構(gòu),施工縫宜做成凹型、凸型。(3)混凝土振搗a)混凝土澆筑過程中,應(yīng)隨時對混凝土進行振搗并使其均勻密實。振搗宜采用插入式振搗器垂直點振b).混凝土振搗過程中,應(yīng)避免重復(fù)振搗,防止過振。應(yīng)加強檢查模板支撐的穩(wěn)定性和接縫的密合情況,防止在振搗混凝土過程中產(chǎn)生漏漿。c).采用機械振搗混凝土?xí)r,應(yīng)符合下列規(guī)定:1)采用插入式振搗器振搗混凝土?xí)r,插入式振搗器的移動間距不宜大于振搗器作用半徑的1.5倍,且插入下層混凝土內(nèi)的深度宜未50~100mm,與側(cè)模應(yīng)保持50~100mm的距離。2)當(dāng)振搗完畢需要變換振搗棒在混凝土拌和物中的水平位置時,應(yīng)邊振動邊豎向緩慢提出振動棒,不得將振動棒放在拌和物內(nèi)平拖。不得用振動棒驅(qū)趕混凝土。3)表面振動器的移動距離應(yīng)能覆蓋已振動部分的邊緣。4)應(yīng)避免碰撞模板、鋼筋及其它預(yù)埋件。5)每一振點的振搗延續(xù)時間宜為20~30s,以混凝土不再沉落、不出現(xiàn)氣泡、表面呈現(xiàn)浮漿為度,防止過振、漏振。d)混凝土振搗完成后,應(yīng)及時修整、抹平混凝土裸露面,待定漿后再抹第二遍并壓光。抹面時嚴(yán)禁灑水,并應(yīng)防止過渡操作影響表面層混凝土的質(zhì)量。特別要注意施工抹面工序的質(zhì)量保證。(4)填放于混凝土中的片石應(yīng)符合以下要求:a)片石的強度等級不應(yīng)小于MU30。b)片石的最大尺寸不應(yīng)大于結(jié)構(gòu)最小尺寸的1/4,最小尺寸不應(yīng)小于15cm。c)片石在填放前應(yīng)用水沖洗干凈。d)片石應(yīng)均勻分布安放穩(wěn)妥,片石間凈間距不得小于15cm,片石與模板間的凈間距不宜小于25cm。e)最上層片石頂面應(yīng)覆蓋不小于25cm的混凝土層。f)片石采用人工擺放的方式進行,注意片石不能碰傷模板及PVC管。g)澆筑完成后,在砼初凝前,在砼接茬面栽少量片石。h)片石體積不得超過片石混凝土總體積的25%。3.5墻背回填及泄水孔,沉降縫設(shè)置3.5.1最低一排泄水孔以下用黏土進行回填,每層填土厚度15cm,回填30cm,用人工分層夯實。3.5.2當(dāng)墻身片石混凝土達到設(shè)計強度70%以上時進行擋墻墻背回填,以確保片石混凝土墻體的質(zhì)量。3.5.3墻背回填材料采用B組填料,按45cm一層分層填筑夯實。3.5.4墻身于地面以上部分,每隔2米上、下、左、右交錯設(shè)置泄水孔。應(yīng)嚴(yán)格控制泄水孔位置,保證其位置準(zhǔn)確,橫平豎直。孔內(nèi)預(yù)埋φ10cmPVC管伸入墻背10cm,端部20cm處用土工布包裹。最底排泄水孔下部及墻頂以下0.5米的范圍內(nèi)設(shè)夯填黏土防滲層。同時施工過程中嚴(yán)格控制泄水孔4%的流水坡度,并保證泄水孔向外排水順暢。3.5.5擋墻沿墻身方向結(jié)合墻高每隔15m或20m設(shè)一道伸縮縫,縫寬0.02m,擋土墻沿墻頂內(nèi)外三邊填塞瀝青麻筋,填塞深度20cm。3.6混凝土養(yǎng)護:3.6.1.混凝土養(yǎng)護期間,應(yīng)重點加強混凝土的濕度和溫度控制,及時對混凝土暴露面進行灑水養(yǎng)護,并保持暴露面持續(xù)濕潤,直至混凝土終凝為止。3.6.2.混凝土帶模養(yǎng)護期間,應(yīng)采取帶模包裹、澆水。經(jīng)過噴淋灑水措施進行保濕、潮濕養(yǎng)護,保證模板接縫處不至失水干燥。為了保證順利拆模,可在混凝土澆筑24~48h后略微松開模板,并繼續(xù)澆水養(yǎng)護至拆模后。3.6.3.在任意養(yǎng)護時間,若淋注于混凝土表面的養(yǎng)護水溫度低于混凝土表面溫度,二者間溫差不得大于15℃。3.6.4.在任意養(yǎng)護時間,若淋注于混凝土表面的養(yǎng)護水溫度低于混凝土表面溫度,二者間溫差不得大于15℃。3.6.5.混凝土養(yǎng)護期間,對混凝土的養(yǎng)護過程做詳細(xì)記錄,并建立嚴(yán)格的崗位責(zé)任制。3.7.混凝土拆模混凝土拆模時的強度應(yīng)符合設(shè)計要求。當(dāng)設(shè)計未提出要求時,應(yīng)符合下列規(guī)定:3.7.1側(cè)模應(yīng)在混凝土強度達到2.5Mpa以上,且表面季棱角不因拆模而損失,方可拆除。3.7.2混凝土的拆模時間除需考慮拆模時的混凝土強度應(yīng)滿足上一條的規(guī)定外,還應(yīng)考慮拆模時混凝土的溫度(由水泥水化熱引起)不能過高,以免混凝土接觸空氣時降溫過快而開裂,更不能在此時澆注涼水養(yǎng)護?;炷羶?nèi)部開始降溫以前以及混凝土內(nèi)部溫度最高時不得拆模。3.7.3拆模宜按立模順序逆向進行,不得損傷混凝土,并減少模板破損。當(dāng)模板與混凝土脫離后,方可拆卸、調(diào)運模板。3.7.4拆除臨時埋設(shè)與混凝土中她預(yù)埋部件時,不得損傷混凝土。3.7.5拆除模板時,不得影響或中斷混凝土的養(yǎng)護工作。3.7.6拆除后的混凝土結(jié)構(gòu)應(yīng)在混凝土達到100%的設(shè)計強度后,方可承受全部設(shè)計荷載。3.8混凝土缺陷處理3.8.1混凝土拆模后,如表面由粗糙、不平整、蜂窩、孔洞、疏松麻面和卻棱角等缺陷或不良外觀時,應(yīng)認(rèn)真分析缺陷產(chǎn)生的原因,及時報告監(jiān)理和業(yè)主,不得自行處理。3.8.2當(dāng)混凝土表面缺陷修補后,修補或填充的混凝土應(yīng)與本體混凝土表面緊密結(jié)合,在填充、養(yǎng)護、和干燥后,所有填充物應(yīng)堅固、物收縮縫或產(chǎn)生膨形區(qū),表面平整且與相鄰表面平齊,達到工程技術(shù)規(guī)范要求的相應(yīng)等級及標(biāo)準(zhǔn)的要求。修補后混凝土的耐久性能應(yīng)不低于本體混凝土。3.8.3除監(jiān)理工程師批準(zhǔn)外,用模板成型的混凝土表面不允許粉刷。3.8.4模板的拆除順序應(yīng)按設(shè)計的順序進行。設(shè)計物規(guī)定時,應(yīng)遵循先支后拆、后支先拆的順序進行。3.8.5拆模時嚴(yán)禁拋扔模板。3.8.6模板拆除后應(yīng)及時對其進行維修整理,并分類妥善保存。3.9腳手架搭設(shè)3.9.1采用雙排扣件式鋼管腳手架,鋼管為Φ48×3.5,Q235鋼,距1.2米,縱距1.8米,步距1.8米,每12-15米設(shè)剪刀撐一道.立桿底設(shè)墊木,面積不小于0.1m縱向掃地桿距底座下皮200mm,并需按規(guī)范要求搭設(shè)密目安全網(wǎng)。3.9.2單管立柱上的對接扣件應(yīng)交錯布置,兩個相鄰立柱接頭不應(yīng)設(shè)在同步同跨內(nèi),在高度方向錯開不小于500mm,各接頭中心距主節(jié)點的距離不應(yīng)大于步距的1/3。搭接長度≥1m,不小于兩個旋轉(zhuǎn)扣件固定端部扣件蓋板的邊緣至桿端距離不應(yīng)小于100mm。。十.安全措施1、嚴(yán)格按照”安全標(biāo)準(zhǔn)工地”實施辦法建設(shè)標(biāo)準(zhǔn)化工地,進行文明施工。2、建立健全安全生產(chǎn)崗位責(zé)任制,由專職人員進行安全技術(shù)監(jiān)督。3、施工現(xiàn)場的材料、機具堆放必須整齊,實行文明施工,對臟、亂、差的工地要嚴(yán)肅處理。4、定期或不定期抽查工地安全情況,發(fā)現(xiàn)安全隱患堅決制止。5、定期進行安全知識教育,做好安全技術(shù)交底。6、現(xiàn)場施工人員必須佩戴安全帽,必須持證上崗。十一.質(zhì)量控制措施1、組織學(xué)習(xí)各種有針對性的規(guī)則、規(guī)范,嚴(yán)格掌握工程質(zhì)量驗收標(biāo)準(zhǔn)。2、抓開挖質(zhì)量關(guān),勤測量復(fù)核??刂瞥?杜絕欠挖。3、抓好原材料及工程試驗關(guān),不合格的原材料嚴(yán)禁使用。4、抓好立模支護關(guān),控制好中線、水平、結(jié)構(gòu)尺寸。5、抓好砼的澆灌、搗固關(guān)、砼嚴(yán)格按配合比施工,搗固密實,以內(nèi)實為根本,外表平整美觀,線條接縫整齊。8、單位工程質(zhì)量8.1地基承載試驗結(jié)果與設(shè)計一致,坑底表面無松軟巖土。8.2墻趾處巖土層盡量少受施工擾動,斜面地基平整無補貼。8.3基礎(chǔ)周邊大致平順整齊或基坑壁貼緊。8.4回填分層夯實8.5沉降縫、伸縮縫位置、縫的填塞符合設(shè)計規(guī)定。8.6泄水孔位置,孔距符合設(shè)計要求,孔內(nèi)通暢。8.7反濾層及時設(shè)置、并隔水,其材料符合設(shè)計要求,厚度不小于設(shè)計規(guī)定。8.8墻面平順、整齊。墻頂及兩端面與路基邊坡連接應(yīng)密貼封嚴(yán)。十二、質(zhì)量檢驗1.基本要求(1)石料規(guī)格和質(zhì)量應(yīng)符合有關(guān)規(guī)定。(2)地基與基礎(chǔ)必須滿足圖紙要求。(3)混凝土的配合比應(yīng)符合試驗規(guī)定。(4)混凝土表面應(yīng)平整、密實、無蜂窩麻面現(xiàn)象。(5)墻背填料符合圖紙要求。(6)沉降縫、泄水孔的位置和數(shù)量應(yīng)符合圖紙要求。2.外觀鑒定(1)混凝土表面平整,無蜂窩、麻面。(2)泄水孔坡度向外,無堵塞現(xiàn)象。(3)沉降縫整齊垂直,上下貫通。十三、環(huán)保措施環(huán)境保護是為了保護和改進當(dāng)?shù)氐纳瞽h(huán)境與生態(tài)環(huán)境,防止給當(dāng)?shù)卦斐晌廴竞推渌?保障人體健康,促進生產(chǎn)。因此,必須把環(huán)境保護工作納入計劃,建立環(huán)境保護責(zé)任制度,采取有效的措施,防止生產(chǎn)建設(shè)過程中產(chǎn)生的廢水、廢渣物、粉塵、噪聲等對當(dāng)?shù)丨h(huán)境造成污染和危害。1、在集鎮(zhèn)和村莊附近施工時,噪聲較大的機械避免在夜間施工;非施工的噪聲要盡力避免。并經(jīng)過有效的管理和采取相應(yīng)的技術(shù)手段將噪聲控制到最低程度。2、施工和生產(chǎn)中的污水和廢水排放至指定地點,不得隨意亂棄,并根據(jù)具體情況修建防護設(shè)施,防止水土流失。3、沿路線兩側(cè)路界外視線500m范圍內(nèi)不開采石料,也不收購該范圍內(nèi)開采的石料或人工砂,以保護沿線的生態(tài)環(huán)境。4、工程完工后,清除所有占用場地的雜物,對原地面進行平整、恢復(fù)為耕地或植被覆蓋;所租用的臨時用地,無償?shù)鼗謴?fù)原貌或達到復(fù)墾要求。所有公路用地范圍內(nèi)的雜物,廢棄物品都清除干凈。凡損壞的水利渠道、地方道路、排水溝、沿線通訊、電力設(shè)施等將與當(dāng)?shù)赜嘘P(guān)部門協(xié)商后進行恢復(fù)或加以改移。6、光纜、電纜保護對于合同段內(nèi)的通訊電纜、光纜及高壓線設(shè)置,必須會同主管部門采取保護措施,施工前要求業(yè)主指明所有地下光纜、電纜的位置,設(shè)置明顯標(biāo)志。臨時設(shè)施的布置應(yīng)盡量避開。在施工中一旦遇到預(yù)先不明的光纜、電纜,應(yīng)立即停止施工,保護好現(xiàn)場,報告業(yè)主、工程師和主管部門處理。十四、安全文明施工措施1、堅持”安全第一、預(yù)防為主”的基本方針在施工過程中要始終把安全,特別是從業(yè)人員和其它人員人身安全放在首要位置,實行”安全優(yōu)先”的原則。在確保安全的前提下,努力實現(xiàn)生產(chǎn)的質(zhì)量和進度目標(biāo)是一致的,是生產(chǎn)經(jīng)營活動順利進行的保證,我施工隊將按照”生產(chǎn)必須安全,安全為了生產(chǎn)”的原則進行安全管理,建立的項目負(fù)責(zé)為首的領(lǐng)導(dǎo)小組,定期組織安全檢查,(附安全組織機構(gòu)圖和安全保證體系圖),發(fā)現(xiàn)事故隱患及時排除。2、保證措施(1)對參戰(zhàn)員工進行安全教育培訓(xùn),特種作業(yè)人員必須持證上崗,做到安全生產(chǎn)、人人有責(zé),從而提高全體員工的安全意識。(2)建立健全生產(chǎn)安全管理制度,落實各級部門安全責(zé)任制。(3)幾個特殊環(huán)節(jié)的預(yù)防保證措施。a、場地建設(shè)必須按施工總平面圖布置,符合安全技術(shù)規(guī)則,設(shè)備、材料、臨時設(shè)施,臨時水電線路,生活設(shè)施等場地布置標(biāo)準(zhǔn)化。b、在施工過程中做到”三定一堅持”即一定人員,專人負(fù)責(zé)設(shè)備的安裝,拆卸、檢修、操作、指揮。二定責(zé)任,對以上各種人員都應(yīng)明確職責(zé),健全安全生產(chǎn)責(zé)任制。三定制度,建立保障安全作業(yè)的規(guī)章制度。作業(yè)區(qū)域內(nèi)掛醒目的標(biāo)志;嚴(yán)禁作業(yè)過程中下方有人穿行;電機作業(yè)設(shè)緊急自動開關(guān),作業(yè)人員不得離崗或與她人說笑聊天,分工明確,緊密配合。作業(yè)人員系安全帶,戴安全帽,禁止穿拖鞋作業(yè)和酒后上崗,特殊危險區(qū)域設(shè)置防護欄和明顯標(biāo)志。(4)安全用電措施①采用通用的安全配電箱,實行一機一閘一漏電保護置。主要配電箱均作接地以防止感應(yīng)電傷人。②照明線路不能與動力線路混用,鋼筋木工機械、振搗棒等電動機械使用的電纜必須嚴(yán)格檢查,不能使用絕緣性差的或有破損的電纜。③機械設(shè)備移位、電器檢修時必須斷電操作,嚴(yán)禁帶電作業(yè),并掛上警示牌。移位時必須有專人指揮。④移動電器修理電器由專業(yè)電工操作。(5)施工操作安全措施①嚴(yán)格執(zhí)行各種安全操作規(guī)程和安全規(guī)章制度。②加強安全生產(chǎn)的宣傳教育工作,做到”人人講安全,事事計安全,時時講安全”。③執(zhí)行崗位責(zé)任制,加強特種作業(yè)人員的上崗培訓(xùn)。(6)交通安全措施①本路段車輛出入口由專人指揮,避免施工段交通事故的發(fā)生。②重型運輸機械的施工通道要及時養(yǎng)護,避免車輛傾覆。十五、技術(shù)管理體系框圖工程監(jiān)理工程監(jiān)理總工程師總工程師測量組技術(shù)組質(zhì)檢組試測量組技術(shù)組質(zhì)檢組試驗霜組土石方施工負(fù)責(zé)人施工負(fù)責(zé)人附屬結(jié)構(gòu)施工負(fù)責(zé)人道路及排水土石方施工負(fù)責(zé)人施工負(fù)責(zé)人附屬結(jié)構(gòu)施工負(fù)責(zé)人道路及排水
、管理措施1)、全面開展質(zhì)量管理2)、積極開展勞動競賽3)、嚴(yán)格執(zhí)行監(jiān)理工程師指令4)、嚴(yán)把材料關(guān)8、技術(shù)措施1)、建立每個分項工程,每道工序,每個施工環(huán)節(jié)的質(zhì)量標(biāo)準(zhǔn)和技術(shù)標(biāo)準(zhǔn),并在施工中嚴(yán)格執(zhí)行。加強職工隊伍培訓(xùn),提高職工安全質(zhì)量和技術(shù)素質(zhì)。2)、嚴(yán)格履行技術(shù)復(fù)核和質(zhì)量管理檢查制,對測量放樣應(yīng)進行復(fù)核,測量資料及其它施工技術(shù)資料由專人保管、收集、整理,和施工同步。3)、組織強有力的施工隊伍及具有經(jīng)驗的工程技術(shù)人員及訓(xùn)練有素的技術(shù)人員參加施工。4)、開工前認(rèn)真審閱圖紙及各種技術(shù)文件,及時編制施工組織設(shè)計與質(zhì)量計劃,進行分項、分部工程劃分,分解創(chuàng)優(yōu)指標(biāo),提出創(chuàng)優(yōu)計劃的實施期限。5)、編制各分項、分部工程施工實施細(xì)則,規(guī)范施工工期、方法、質(zhì)量標(biāo)準(zhǔn),檢測手段并嚴(yán)格實施。6)、嚴(yán)格履行技術(shù)復(fù)核和質(zhì)量管理檢查制,對測量進行復(fù)核,符合制度方能放線。測量資料及其它施工技術(shù)資料必須有專人保管、收集、整理,且和施工同步。7)、認(rèn)真進行工程技術(shù)、質(zhì)量及施工安全技術(shù)交底,施工順序進度安排均要作交底,并作好書面記錄備查。8)、嚴(yán)格按照有關(guān)的施工規(guī)范及設(shè)計圖紙施工,工程質(zhì)量評定及隱蔽工程驗收,必須經(jīng)監(jiān)理工程師評定簽認(rèn)后,方可進行下步工序施工。9)、施工中,如對結(jié)構(gòu)和其它原因需進行設(shè)計修改,必須在辦理工程聯(lián)系單、設(shè)計修改通知單后方可施工。10)、在保證建設(shè)監(jiān)理工程師充分履行職責(zé)和行使權(quán)力的前提下,建立項目經(jīng)理部內(nèi)部監(jiān)理工程師制,各班組設(shè)質(zhì)量檢查員,實行質(zhì)量否決制度。與工程監(jiān)理密切配合搞好質(zhì)量管理工作,做好事前質(zhì)量控制,施工過程質(zhì)量控制,竣工驗收等工作。十六、施工組織措施1、以合同文件要求和設(shè)計圖紙為依據(jù),以技術(shù)規(guī)范為標(biāo)準(zhǔn),制定項目創(chuàng)優(yōu)規(guī)劃,確定各分項目的質(zhì)量管理目標(biāo)和各工序的質(zhì)量管理標(biāo)準(zhǔn),以工序質(zhì)量標(biāo)準(zhǔn)的實現(xiàn)來保證分項目質(zhì)量目標(biāo)的實現(xiàn),以分項質(zhì)量目標(biāo)的實現(xiàn)來保證工程項目質(zhì)量創(chuàng)優(yōu)目標(biāo)的實現(xiàn)。2、實行項目經(jīng)理質(zhì)量負(fù)責(zé)制和技術(shù)質(zhì)量雙向承包責(zé)任制,逐層簽定技術(shù)質(zhì)量責(zé)任狀,以激發(fā)全體參與項目施工人員的創(chuàng)優(yōu)積極性,促進工程質(zhì)量的提高。3、加強教育,貫徹制度,科學(xué)管理,促進創(chuàng)優(yōu)。在整個工程施工中力求做到”五不施工”(施工圖未復(fù)核、測量未復(fù)核、材料未實驗或無合格證、技術(shù)未交底、隱蔽工程未簽證不施工);”三不交接”(無自檢記錄、無施工記錄、無專職質(zhì)檢人員簽字不交接);”三教育”(工前培訓(xùn)、工中指導(dǎo)、工后講評)。4、加強現(xiàn)場質(zhì)量控制和質(zhì)量檢查。按照合同文件和技術(shù)規(guī)范的規(guī)定,設(shè)立工地試驗站和質(zhì)量監(jiān)測站,配備滿足檢測需要的各種測試儀器設(shè)備,對工程所用的各種材料、設(shè)備和施工的各工序進行有效的檢測控制。5、施工中采用先進的施工工藝和精良的施工設(shè)備,不斷優(yōu)化施工組織設(shè)計方案,推廣應(yīng)用”四新”成果,突破創(chuàng)優(yōu)難點,采用先進的技術(shù)和科學(xué)的管理相結(jié)合。大力組織”兩化”施工,使工程質(zhì)量一次成優(yōu)。6、虛心聽取和接受工程師及其代表的指導(dǎo)和監(jiān)督,堅決執(zhí)行工程師及其代表的指示,及時落實工程師及代表的改進意見。提供滿足工程師及其代表在現(xiàn)場檢測需要的人員和儀器設(shè)備,搞好與工程師及其代表的配合工作,同心協(xié)力創(chuàng)優(yōu)。7、作好各種試驗、檢測記錄,為施工提供準(zhǔn)確可靠的各種數(shù)據(jù),收集整理工程質(zhì)量和施工技術(shù)資料,及時編制竣工文件。8、建立施工與建設(shè)、監(jiān)理、設(shè)計各方組成的質(zhì)量監(jiān)控網(wǎng)絡(luò),使整個工程在施工過程中始終處于受控狀態(tài)。9、工程預(yù)驗收前,承包商組織有關(guān)人員按設(shè)計施工圖和施工標(biāo)準(zhǔn)的要求對其施工工程進行全面的檢查,如有不符立即進行整改。
10、當(dāng)全部工程完工并符合合同規(guī)定時,承包商應(yīng)向業(yè)主或監(jiān)理申請交工驗收。
11、承包商對業(yè)主或監(jiān)理組織的預(yù)驗收提出的問題,應(yīng)在業(yè)主或監(jiān)理規(guī)定的期限內(nèi)整改完,再次提出交工申請。
12、交工資料由業(yè)主或監(jiān)理組織驗收,驗收后辦理交工資料交接手續(xù)。十七、安全保證措施①、安全施工主要措施1、成立環(huán)境保護領(lǐng)導(dǎo)機構(gòu):項目部成立環(huán)境保護委員會,指定一名副經(jīng)理負(fù)責(zé)環(huán)境保護工作的組織領(lǐng)導(dǎo)、規(guī)章制度的制訂和檢查落實。各工程隊成立環(huán)境保護領(lǐng)導(dǎo)小組,隊主管領(lǐng)導(dǎo)任小組組長,各施工工長及后勤保障部門負(fù)責(zé)人為成員,負(fù)責(zé)日常性的環(huán)境保護工作的檢查和落實。2、積極與所在地聯(lián)成環(huán)境保護網(wǎng)絡(luò),認(rèn)真聽取地方環(huán)保部門的意見,虛心接受其監(jiān)督和落實。3、根據(jù)本工程項目的作業(yè)特點,制訂如下保護措施:1)、在砌筑操作之前必須檢查操作環(huán)境是否符合安全要求,道路是否暢通,機具是否完好、牢固,安全設(shè)施和防護用品是否齊全,經(jīng)檢查符合要求后才可施工。2)、砌筑基礎(chǔ)時,應(yīng)經(jīng)常檢查和注意基坑邊坡的土體變化情況,有無開裂、位移現(xiàn)象。堆放石材料應(yīng)離槽(坑)邊1m以上。3)、砌筑高度超過施工操作面1.2m以上時應(yīng)搭設(shè)腳手架。腳手架上堆放材料不得超過規(guī)定荷載值,同一塊腳手板上操作人員不得超過兩人。不準(zhǔn)用放不穩(wěn)固的工具或物品在腳手板上墊高操作,更不準(zhǔn)在未經(jīng)計算和加固的情況下,在腳手板上再隨意疊搭一層腳手板。應(yīng)按規(guī)定搭設(shè)安全網(wǎng)。4)、在腳手架施工時,堆放材料、施工機具等物品不得超過使用荷載,否則,必須經(jīng)過驗算并采取有效的加固措施后,方可堆放和施工。5)、不準(zhǔn)站在墻頂面上劃線、磚砌、刮縫、清理墻面和檢查大腳垂直度等工作;修石時應(yīng)面向墻面砍,并要注意防止碎石跳出傷人,垂直往上、往下人工投遞石料時,要支搭站人用的寬度不小于0.6m的專用腳手架,并認(rèn)真?zhèn)鬟f,以防傷人。6)、不準(zhǔn)在墻頂上或腳手架上修鑿石材,以免墻體受到振動,影響墻體質(zhì)量或石塊掉下傷人。不準(zhǔn)勉強在超過胸部的墻上砌筑片石,以免不宜控制墻面垂直度、碰撞石墻或上石時失手掉下造成事故。不用的石塊不得由上往下投擲,運石上下的坡道要加固定牢,并訂設(shè)防滑條、欄桿扶手等。7)、已砌好的山墻應(yīng)用臨時系桿(如檀條等)放置在各跨山墻上,使其連接穩(wěn)定,或采用其它加固措施,雨期每天下班前應(yīng)用防雨材料遮蓋,以防雨水沖掉砂漿,致使砌體倒塌。4、進出場便道,經(jīng)常灑水養(yǎng)護,避免造成塵土飛揚,污染周圍環(huán)境。5、施工設(shè)備停置有序,材料堆放井井有條,環(huán)境衛(wèi)生專人打掃,施工營區(qū)、生活區(qū)干凈整齊。6、施工管理人員及現(xiàn)場施工人員均掛牌上崗。7、質(zhì)量員對現(xiàn)場所進行的與質(zhì)量有關(guān)的活動進行觀察、監(jiān)督與檢查。檢查現(xiàn)場的施工工作是否按已批準(zhǔn)的程序進行。8、現(xiàn)場檢查活動是隨機的,無特殊原因,原則上每天都要進行,對觀察發(fā)現(xiàn)的不足或缺陷要作出記錄,并將不足或缺陷按重要性的不同以書面或口頭形式通知責(zé)任方。9、每周末,技術(shù)部要總結(jié)檢查情況,進行講評和通報,保證重點項目和重要過程不漏檢。10、項目工地每月召開一次由各部門和項目經(jīng)理參加的質(zhì)量小結(jié)會。技術(shù)部在會上向大家匯報當(dāng)月質(zhì)量體系運行情況,及時找出存在的問題,督促有問題的部門積極采取糾正措施,抓緊整改。11、現(xiàn)場發(fā)現(xiàn)的所有質(zhì)量問題,其改正行動都要按程序文件規(guī)定的格式記錄下來,且隨著工程進展,逐步向下一階段移交,作為竣工狀態(tài)證明質(zhì)量達到要求的記錄文件。12、項目工地對質(zhì)量體系運行中出現(xiàn)與質(zhì)量管理文件有沖突或無法執(zhí)行的情況時,要及時向公司報告,以求得問題的及時解決。13、施工現(xiàn)場平面布置符合有關(guān)安全衛(wèi)生規(guī)定,機具擺放整齊有序,各種標(biāo)志、標(biāo)識正確醒目,達到文明施工標(biāo)準(zhǔn)。14、如出現(xiàn)危及或可能傷及人員的危險時,所有相關(guān)的工作應(yīng)停止直至危險狀態(tài)得到消除。15、任何表現(xiàn)出不安全因素的設(shè)備和工具必須立即停止使用,直至處于安全狀態(tài)或從施工區(qū)域移出或更換。16、若現(xiàn)場發(fā)生事故,應(yīng)立即采取應(yīng)急措施并在第一時間向業(yè)主提交書面報告,按業(yè)主和監(jiān)理的相關(guān)規(guī)定及本公司《事故處理程序》進行事故的調(diào)查和處理。17、施工現(xiàn)場主要道路應(yīng)符合標(biāo)準(zhǔn)要求,特殊地況設(shè)蓋板、安全護欄。18、施工現(xiàn)場根據(jù)消防要求配置消防設(shè)施和器具,保持消防通道暢通。19、晚上施工時,在獲監(jiān)理認(rèn)可后,項目部提供具有足夠照明強度的設(shè)備,確保安全生產(chǎn)。20、控制箱電氣開關(guān)、閘刀等須放置在防雨棚或防雨罩,設(shè)漏電保護器以防漏電。21、作業(yè)現(xiàn)場應(yīng)經(jīng)常打掃并保持清潔,垃圾應(yīng)集中堆放并及時清理、運送至指定地點。22、熟悉與安全和健康有關(guān)的法律責(zé)任和義務(wù),熟悉項目部全面的、綜合的安全和健康程序的細(xì)節(jié)。23、對違反安全程序的有關(guān)人員將依據(jù)項目部相關(guān)規(guī)定,采取適當(dāng)?shù)膽土P性措施。違反安全規(guī)定并危及生命和財產(chǎn)安全的人員將被從施工隊伍中清除出去。24、施工人員工作前應(yīng)按規(guī)定穿戴好與作業(yè)相適應(yīng)的防護用品,檢查作業(yè)場地、施工機具及設(shè)備的完好情況,記錄每次檢查的日期、發(fā)現(xiàn)的問題、所采取的補救措施等。25、施工人員工作中應(yīng)遵守崗位安全技術(shù)操作規(guī)程,做到文明施工。26、施工人員在工作前和工作中均不得食用酒精類飲料,不應(yīng)在禁止煙火的場所吸煙。27、在施工區(qū)域應(yīng)走指定通道,不應(yīng)跨越危險區(qū),不應(yīng)在行駛的機動車上爬上跳下和攀登起重機吊鉤和吊運中的物件。28、應(yīng)注意各種安全標(biāo)志,不應(yīng)隨便拆除或占用各種照明、信號、防雷等安全防護裝置、安全標(biāo)志和檢測儀表等。29、發(fā)生事故應(yīng)及時搶救人員、財產(chǎn),保護現(xiàn)場并向有關(guān)人員報告。執(zhí)行交接班制度。30、施工現(xiàn)場電氣作業(yè),由專職電工按規(guī)范操作。并負(fù)責(zé)作業(yè)區(qū)內(nèi)各種帶電設(shè)備及電線的漏電檢查,發(fā)現(xiàn)問題立即整改。31、電氣設(shè)備操作人員,必須穿合格勞保服裝,戴標(biāo)準(zhǔn)絕緣手套,使用前必須對電氣設(shè)備進行漏電試驗。32、雨雪或潮濕天氣,一般不在露天使用電氣設(shè)備,必要時采取適當(dāng)?shù)陌踩秒姶胧?3、施工現(xiàn)場用電設(shè)施應(yīng)在設(shè)備負(fù)荷線的首端處設(shè)置漏電保護裝置。漏電保護器應(yīng)裝設(shè)在開關(guān)箱內(nèi)。34、施工現(xiàn)場的配電室應(yīng)通風(fēng)良好,并采取防止雨雪和動物入內(nèi)的措施。35、用電設(shè)備的金屬外殼(安全電壓除外)應(yīng)作保護接地或保護接零。潮濕或條件特別惡劣的施工現(xiàn)場的電氣設(shè)備應(yīng)采用保護接零。36、配電屏(盤)上的各種配電線路應(yīng)有編號并標(biāo)明用途。配電線路維修時應(yīng)懸掛”禁止合閘,有人操作”警告標(biāo)志。停、送電必須有專人負(fù)責(zé)。37、搬運石塊時要注意配合,步調(diào)協(xié)調(diào)一致,互相用力均勻,保證安全。38、石籠制作時注意安全,綁扎鐵絲時注意不要滑傷皮膚,鉤破衣服。39、修筑施工便道應(yīng)保證足夠的寬度和強度,確保運輸安全。40、人工開挖基槽時注意不要滑傷管子防腐層,人工鑿巖時要防止石塊崩傷操作人員。41、修筑圍堰導(dǎo)流時圍堰應(yīng)有足夠的強度,防止被水沖垮。42、漿砌石護坡時應(yīng)把坡上的石塊清理干凈,防止石塊清理不凈滑落傷人。43、攪拌機操作時應(yīng)遵守操作規(guī)程,嚴(yán)禁非崗位人員違章操作44、進料便道、堆料場盡量利用施工作業(yè)帶或已有的鄉(xiāng)村砂石路等,沒有植被的砂石場和植被已被破壞的場地。45、施工時采取適當(dāng)措施保證現(xiàn)場道路、斜坡和其它對地面不會形成障礙,造成水災(zāi),破壞植被。46、作業(yè)帶外被不慎砍伐的樹木要立即補救,只要安全性和可施工性允許,平整場地的工作人員應(yīng)盡量不破壞場地表面,不觸及原有的根系,植物能夠從地面切斷,為以后重新萌芽生長創(chuàng)造條件。47、開挖管溝時要把表層土和底層土分開堆放,設(shè)置合適的溝渠排水和保持跨躍管溝的安全通道,以一種不影響其它土地使用的方式把管溝里過多的水抽到臨近的地區(qū)。48、回填管溝時,應(yīng)盡量作到恢復(fù)地表的原來形狀,使表面能正常排水。49、下層土和表層土回填應(yīng)與管溝內(nèi)兩側(cè)的土層匹配,保存的表土不可在下層土回填之前填到管溝里面。50、在回填堆放挖出的土壤時,不可把表層的草皮或表土除去。51、壓實管溝中的回填土,壓實程度要大致相當(dāng)于施工前狀態(tài),以盡量減少下沉。在管溝與水道交叉處和中斷的排水溝的兩岸壓實填土?xí)r注意,必要時采取適當(dāng)?shù)拇胧?確保施工安全。52、在回填前需對大開挖的管溝用肉眼檢查,如發(fā)現(xiàn)有動物,則應(yīng)把它們弄出來,對于較大的動物,可在夠壁挖一個斜坡,以便讓它能夠爬出來。53、取料場與任何水域保持最低限度的植被緩沖帶。54、取料場擴展過程中移走的表土層必須適當(dāng)堆放,采取措施防止水土流失,把侵蝕局限在取料場范圍內(nèi),不得擅自擴大作業(yè)面。55、除了指定的料場,未經(jīng)當(dāng)?shù)赜嘘P(guān)部門許可在施工中不能隨意從河床或岸邊傾倒或挖取卵石、采砂及廢棄物。56、毀壞、遷移或清理樹木、植被不得超過工程施工所需的范圍,不得亂砍亂伐。
57、施工時臨時加寬加固的道路,施工完畢應(yīng)結(jié)合當(dāng)?shù)貙嶋H情況,對影響環(huán)境的予以恢復(fù)原貌。58、對于違反環(huán)保規(guī)章造成環(huán)境破壞,應(yīng)立即報告項目監(jiān)理,按照項目監(jiān)理的指示負(fù)責(zé)清理、回收和(或)采取復(fù)原措施。地表徑流向聚集,沖溝上部設(shè)置環(huán)向節(jié)流排水溝,邊坡處沿管溝砌筑截水墻。59、穩(wěn)定性差的沖溝邊坡,軟土地基采用漿砌條(塊)石護坡。
60、在施工作業(yè)前,經(jīng)過對風(fēng)險和危害分析以及當(dāng)?shù)爻R姴?、傳染病和醫(yī)院狀況調(diào)查的基礎(chǔ)上,針對有毒蛇出沒的環(huán)境、使用機械設(shè)備、發(fā)電機排水等危險因素,編制應(yīng)急預(yù)案和應(yīng)急程序,成立應(yīng)急小組,準(zhǔn)備應(yīng)急物資,保證每位員工都熟悉應(yīng)急預(yù)案和緊急情況下的應(yīng)急行動。61、如電源開關(guān)在附近、應(yīng)迅速關(guān)閉電源,否則用絕緣物體挑開電線或分離電器,使患者脫離電源;呼吸停止者,立即進行人工呼吸;
心臟停跳者,進行胸外心臟按壓;送醫(yī)院急救處理。62、處理損傷的原則是首先搶救傷員的生命,對呼吸、心跳停止的傷員,應(yīng)就地立即進行復(fù)蘇術(shù)。63、治療窒息。如遇嚴(yán)重失血或胸部開放性損傷,應(yīng)盡快止血或封閉胸部傷口;
64、治療休克和骨折固定。運送四肢骨折傷員,必須用夾板固定傷肢,脊椎骨折須臥硬板床;
65、如動脈出血,要上止血帶,每隔1小時放松一次,每次1—2分種,轉(zhuǎn)運途中應(yīng)保持呼吸道暢通;
66、送醫(yī)院,預(yù)防感染,糾正電解質(zhì)代謝失調(diào),注射破傷風(fēng)抗毒素。67、急性中毒者,立即終止接觸毒物,毒物由呼吸道或皮膚侵入時,要立即將病人撤離中毒現(xiàn)場,移到空氣新鮮的地方,污染的衣服必須立即脫去,清洗接觸部位的皮膚;采取催吐、洗胃、導(dǎo)瀉等方法清除體內(nèi)尚未被吸收的毒物;清除皮膚上的毒物,脫去污染衣服,用大量溫水清洗皮膚毛發(fā);清除眼內(nèi)毒物,用清水徹底清洗;清除傷口毒物;使用解毒劑并送醫(yī)院。十八、安全保證體系安全保證體系框圖安全安全法規(guī)技術(shù)負(fù)責(zé)人項目經(jīng)理(安全責(zé)任人)技術(shù)負(fù)責(zé)人項目經(jīng)理(安全責(zé)任人)項目安全規(guī)程技術(shù)措施項目安全規(guī)程技術(shù)措施現(xiàn)場安全負(fù)責(zé)人現(xiàn)場安全負(fù)責(zé)人各施工區(qū)各施工區(qū)糾正、整改糾正、整改1、建立安全生產(chǎn)責(zé)任制2、建立安全保證體系,健全各級各部門生產(chǎn)責(zé)任制,責(zé)任落實到人;3、各項施工任務(wù)都有明確的安全指標(biāo)和包括獎懲辦法在內(nèi)的保證措施,簽訂各級安全生產(chǎn)責(zé)任制。4、加強安全意識和技術(shù)教育1)、剛進施工現(xiàn)場施工人員必須進行安全技術(shù)教育;2)、工人變工種,必須進行新工種的安全技術(shù)教育;3)、工人掌握本工種操作技能,熟悉本工種安全技術(shù)操作規(guī)程;4)、認(rèn)真建立”職工勞動保護記錄卡”,及時做好記錄。5、安全保證的指導(dǎo)思想本工程施工現(xiàn)場和工程規(guī)模較大,施工人員多,專業(yè)交叉施工頻繁,不安全因素多。為切實保證施工過程安全無事故,將”安全第一,預(yù)防為主”指導(dǎo)思想落到實處,為實現(xiàn)這一指導(dǎo)思想,安全生產(chǎn)將在組織保證管理制度及防止傷害事故、培訓(xùn)和教育等方面采取切實可行的相應(yīng)措施。6、建立以項目經(jīng)理部及安全監(jiān)察部門為主的安全領(lǐng)導(dǎo)組織,強調(diào)”管生產(chǎn)必須管安全”的生產(chǎn)原則,推行全員安全生產(chǎn)責(zé)任制.7、本項目設(shè)專職安全監(jiān)察部門,配合工班長進行施工過程中的安全管理工作。8、施工工班設(shè)兼職安全員,配合工班長進行施工過程中的安全管理工作.9、管理制度措施建立健全各項安全生產(chǎn)管理制度,在進行施工技術(shù)交底時,同時進行安全交底。特種作業(yè)人員必須經(jīng)過有關(guān)部門培訓(xùn),考試合格后持證上崗、建立定期安全檢查制度,建立相應(yīng)的考核措施,施工管理人員及各工種操作人員要佩戴不同的崗位標(biāo)識;嚴(yán)禁違章指揮、違章作業(yè)、野蠻施工。10、施工過程安全措施施工過程中對安全教育、執(zhí)證上崗以及用電、樁基開挖的通風(fēng)、防坍塌、高空作業(yè)等嚴(yán)格按安全規(guī)程執(zhí)行,保證安全生產(chǎn)。11、消防安全保證措施為加強工程消防安全管理,貫徹”預(yù)防為主,防消結(jié)合”的消防方針,確保工程順利進行,采取以下措施確保消防安全。12、重點防范的安全措施在本工程施工中,各環(huán)節(jié)的安全管理不容忽視,隨時采取措施改進。本工程重點防護措施有以下幾項,這在開工之前,必須完善安全措施。1)、防止觸電事故的發(fā)生,電工應(yīng)經(jīng)常檢查電器及線路安全,線路均配備標(biāo)準(zhǔn)配電箱。2)、為維護行人和交通安全,施工現(xiàn)場出入口及重要部位實行封閉施工。采用鋼圍欄將施工現(xiàn)場封閉,既有利于文明施工,又減少相互干擾。3)、作好機械設(shè)備的安全防護措施。4)、做好防洪、防火、防盜、防爆炸事故等”四防”工作。防洪:施工場地開挖臨時排水溝,備好抽水設(shè)備。防火:電力線路和照明線路按規(guī)定布設(shè);生產(chǎn)和生活臨時用房除特殊情況(試驗)一律不得使用電爐;不得亂丟煙頭;組建防火組織,定期檢查;在施工現(xiàn)場安放各種滅火器具。防盜:現(xiàn)場派專人保衛(wèi),加強與地方公安、聯(lián)防機關(guān)聯(lián)系,確保施工安全。防爆:易燃、易爆物品必須派專人管理,且與其它物品分開儲存;乙炔、氧氣瓶的存放應(yīng)設(shè)立單間儲存,并照防火規(guī)定距離及要求修建儲存庫房,庫房周圍應(yīng)設(shè)立明顯的防火標(biāo)志。一切無關(guān)人員嚴(yán)禁動用乙炔、氧氣及進入儲存庫房。13、其它需重點防范的安全措施1)、施工現(xiàn)場設(shè)置安全標(biāo)志,場內(nèi)的溝、坑等邊緣設(shè)安全護欄。場地狹小,行人和運輸繁忙的路段設(shè)專人指揮交通。2)、工地上較高的建(構(gòu))筑物、臨時設(shè)施及重要庫房均應(yīng)架設(shè)避雷裝置。3)、施工測量釘樁要注意周圍行人的安全,不得對面使錘。鋼釬和其它工具不得隨意拋擲。4)、場內(nèi)道路應(yīng)經(jīng)常維護,保持暢通,場內(nèi)道路應(yīng)平坦順直。5)、現(xiàn)場架設(shè)的臨時線路必須用絕緣物支撐,不得將電線纏繞在鋼筋、樹木或腳手架上。6)、各種電器設(shè)備應(yīng)配有專用開關(guān),室外使用的開關(guān)、插座應(yīng)外裝防水箱并加鎖,在操作處加設(shè)絕緣墊層。7)、在三相五線制供電系統(tǒng)中,電器設(shè)備的金屬外殼應(yīng)作接地保護,其接地電阻應(yīng)不大于4。8)、各種電器設(shè)備的檢查維修,應(yīng)停電作業(yè);如必須帶電作業(yè)時,應(yīng)有可靠的安全措施并派專人監(jiān)護。9)、工地安裝變壓器必須符合電業(yè)部門的要求,并設(shè)專人管理,施工用電要盡量保持三相平衡。10)、現(xiàn)場的變(配)電設(shè)備處,必須備有滅火器材和高壓安全用具,非電工人員嚴(yán)禁接近帶電設(shè)備。11)、施工現(xiàn)場的臨時照明:室內(nèi)照明線路應(yīng)用瓷夾固定;電線接頭應(yīng)牢固,并用絕緣膠帶包扎,保險絲應(yīng)按用電負(fù)荷量裝設(shè)。12)、檢修電氣設(shè)備時應(yīng)按下列要求進行:電氣設(shè)備的檢修必須由電工進行,她人不得任意操作。工作中如遇停電應(yīng)拉下開關(guān),切斷電源;檢修結(jié)束必須仔細(xì)檢查各項設(shè)備的情況,沒有異常,方可合閘。大型電氣設(shè)備檢修應(yīng)在切斷電源,設(shè)好防護后進行,并在開關(guān)處設(shè)置警示標(biāo)牌,工作完成后方可拆除;如需進行送電試驗時,必須在認(rèn)真檢查并與有關(guān)部門聯(lián)系后,方可進行。13)、操作人員在工作中不得擅離崗位,不得操作與操作證不相符合的機械;不得將機械設(shè)備交給無本機種操作證的人員操作。14)、機械設(shè)備在施工現(xiàn)場停放時,應(yīng)選擇安全的停放地點,關(guān)閉好駕駛室(操作室),要拉上駐車制動閘。十九、文明施工,加強環(huán)保①、文明施工在施工現(xiàn)場管理中,采取各種措施,按現(xiàn)代化施工的客觀要求組織施工,使施工現(xiàn)場保持良好的施工環(huán)境和施工秩序。主要措施有:
1、組織管理措施1)、建立健全管理組織機構(gòu)。施工現(xiàn)場應(yīng)成立以項目負(fù)責(zé)人為組長,生產(chǎn)、技術(shù)質(zhì)量、安全、消防、保衛(wèi)、材料、行政衛(wèi)生管理人員為成員的文明施工管理組織。2)、健全管理制度。包括:個人崗位責(zé)任制、經(jīng)濟責(zé)任制、檢查制度、獎懲制度、會議制度和各項專業(yè)管理制度等;3)、健全管理資料。加強教育培訓(xùn)工作;推廣應(yīng)用新技術(shù)、新工藝、新設(shè)備和現(xiàn)代化管理方法,提高機械化作業(yè)程度。2、現(xiàn)場管理措施1)、對施工現(xiàn)場各生產(chǎn)要素(主要是物的要素)的所處狀態(tài),不斷地進行整理、整頓、清掃、清潔,并培養(yǎng)員工的素質(zhì)及技術(shù),實現(xiàn)文明施工。2)、合理定置。將全工地施工期間所需要的物在空間上合理布置,實現(xiàn)人與物、人與場所、物與場所、物與物之間的最佳結(jié)合,使施工現(xiàn)場秩序化、標(biāo)準(zhǔn)化、規(guī)范化,體現(xiàn)文明施工水平。3)、目視管理。目視管理就是用眼睛看的管理,亦可稱之為”看得見的管理”。它是利用形象直觀,色彩適宜的各種視覺感知信息來組織現(xiàn)場施工生產(chǎn)活動,達到提高勞動生產(chǎn)率,保證工程質(zhì)量,降低工程的成本。目視管理是一種簡便適用,透明度高,便于員工自主管理,自我控制,科學(xué)組織生產(chǎn)的一種有效的管理方式。4)、其主要內(nèi)容與形式如下:①施工現(xiàn)場各項管理制度、操作規(guī)程、工作標(biāo)準(zhǔn)、施工現(xiàn)場管理實施細(xì)則等布告等應(yīng)用墻報、掛板等形式,展示清楚。②在定置過程中,以清晰的、標(biāo)準(zhǔn)化的視覺顯示信息落實定置設(shè)計,實現(xiàn)合理定置。③施工現(xiàn)場的管理崗位責(zé)任人采用標(biāo)牌顯示,以更好地落實崗位責(zé)任制,激發(fā)崗位人員的責(zé)任心,并有利于群眾監(jiān)督。④在施工現(xiàn)場合理利用各種色彩、安全色、安全標(biāo)志等,并實行標(biāo)準(zhǔn)化管理,有利于生產(chǎn)和員工的安全。⑤將施工現(xiàn)場管理的各項檢查結(jié)果張榜公布。二十、施工現(xiàn)場環(huán)境保護1、環(huán)境保護是中國的一項基本國策。在施工過程中,采取措施,按照國家、地方法規(guī)和行業(yè)、企業(yè)要求,采取措施控制施工現(xiàn)場的各種粉塵、廢水、廢氣、固體廢棄物以及噪聲、振動等對環(huán)境的污染和危害,同時要防止水土流失。保護和改進施工環(huán)境,保證人們身體健康,消除外部干擾,保證順利進行。2、環(huán)境保護的措施及具體做法:1)、實行環(huán)保目標(biāo)責(zé)任制2)、加強檢查和監(jiān)控工作3)、對要保護和改進的施工現(xiàn)場環(huán)境,進行綜合治理4)、嚴(yán)格執(zhí)行國家的法律、法規(guī),統(tǒng)籌安排,合理布置,綜合治理。5)、施工前應(yīng)制定施工期間環(huán)境保護措施,防止大氣污染、水源污染和噪聲污染。6)、施工廢棄物采取措施集中外運到指定地點,避免阻塞河溝、污染水源。如無法及時處理或運走,則必須設(shè)法防止散失。7)、施工中所產(chǎn)生的污水或廢水,集中處理,不能隨意排放。8)、在運輸和貯存施工材料時,采取覆蓋、倉貯等措施防止漏失。9)、當(dāng)路線經(jīng)過農(nóng)田灌溉區(qū)時,采取必要臨時措施。如接邊溝,安設(shè)水管等以保證不影響或中斷農(nóng)田的排灌作業(yè)。10)、對工程范圍以外的土地及植被應(yīng)注意保護,未經(jīng)工程師批準(zhǔn),不得隨意堆置廢方和挖掘。3、保持作業(yè)帶范圍內(nèi)不遺留施工產(chǎn)生的垃圾和碎片。4、工現(xiàn)場的食物垃圾應(yīng)每天清楚掉。5、垃圾應(yīng)運到施工場地以外適當(dāng)?shù)睦幚韴鐾咨铺幚怼?、不得將垃圾處理到溝渠里,表土或土堆上。7、清理人員收拾垃圾、碎片、切斷的殘枝和施工預(yù)料進行處理。把固體廢料和垃圾(非生物可降解的垃圾)收集起來在一個場外地點進行處理。8、把固體廢料和垃圾(非塵物可降解的垃圾)收集起來在一個場外地點進行處理。9、各種油料應(yīng)在容器內(nèi)存放,廢油應(yīng)及時回收集中儲存,嚴(yán)禁就地傾倒,油料對地面造成污染時應(yīng)采取措施進行清理。10、清理時被切斷的樹木可運出作業(yè)帶范圍或在作業(yè)帶范圍內(nèi)進行切片、切碎、或堆在一個可接近的地方,可供公眾加以利用。
二十一、綠化工作措施1、工地附近的樹木、花草盡可能進行保護。2、施工期間對綠化地區(qū)進行管理養(yǎng)護。二十二、施工進度工期保證措施本項工程施工我們將按照”高效、優(yōu)質(zhì)、有序”的原則均衡進行,根據(jù)工期、質(zhì)量、安全等要求,合理安排,精心施工,在確保質(zhì)量、安全的前提下采取如下措施以保證預(yù)定工期的實現(xiàn)。本工程施工不受外圍交通影響,現(xiàn)場采用局部封閉圍蔽施工,全路段進行統(tǒng)籌安排施工,控制好施工的進度,能夠安排晚間施工。關(guān)鍵工序擬定全天候施工,管理人員分為三班和作業(yè)人員分為四班進行施工。在施工安排中要充分的考慮雨季施工時候的特點,認(rèn)真做好雨季施工的質(zhì)量保證工作。二十三、一般措施我公司的技術(shù)力量雄厚,設(shè)備齊全,特別善于組織打大仗、打硬仗,在建設(shè)單位中具有良好的信譽。具有良好及廣泛的社會關(guān)系,這些條件為工程的順利進行奠定了基礎(chǔ)。工程開工后,立即根據(jù)施工進度計劃進行各項工作的落實,使工程一開始施工就有組織、有步驟地進行。1、從機構(gòu)組織、人員配備,管理上保證。配備高級技術(shù)人才組成精干的項目經(jīng)理部。詳見工程項目管理機構(gòu)。按部門、單位、崗位為主體制訂嚴(yán)格的責(zé)任制度,做到人人有責(zé)可負(fù)。制定嚴(yán)密的規(guī)章制度,任何人都須毫無例外地遵守。2、從計劃安排上保證。按照施工進度總計劃的工期要求,精心制定分項施工計劃和各項實施方案,重要工序做好施工組織專項設(shè)計,合理安排各分項工程的施工順序、全面覆蓋施工的全過程和所有方面。確保關(guān)鍵線路上的各工序按時完成,充分利用有利條件和時間,縮短作業(yè)流程,從各個環(huán)節(jié)上加快施工進度。計劃按周按日進行細(xì)分,計劃的執(zhí)行和檢查落實到人。預(yù)先解決后續(xù)工作中可能會出現(xiàn)的問題,為后續(xù)工作順利進行創(chuàng)造有利條件。3、從材料管理和機械設(shè)備管理上保證。材料進行分層管理,明確材料管理制度,使整個施工過程的材料周轉(zhuǎn)順利。其中鋼板校等支護材料的投入是關(guān)鍵,為確保施工進度,支護材料均按周轉(zhuǎn)2次的數(shù)量投入。編制詳細(xì)的施工項目材料計劃與材料供應(yīng)計劃,合理指導(dǎo)與組織施工項目材料的管理,確保材料的及時供應(yīng),在材料供應(yīng)計劃的執(zhí)行過程中,定期或不定期地檢查。堅決杜絕停工待料的現(xiàn)象發(fā)生。本工程的土方施工機械和土方運輸車輛是控制施工進度的關(guān)鍵設(shè)備,因此施工期間必須保證按施工機械設(shè)備表中的機械及時進場施工。機械設(shè)備管理中,做到人機固定,實行機械使用、保養(yǎng)責(zé)任制,將機械設(shè)備的使用效益與個人經(jīng)濟利益聯(lián)系起來,進而提高機械的生產(chǎn)效率,確保各工序按時完成。組織好機械設(shè)備的流水施工,搞好機械設(shè)備的綜合利用,為機械設(shè)備的施工創(chuàng)造良好的條件,大力提高其使用率,縮短作業(yè)時間。4、從技術(shù)上保證。本標(biāo)項目技術(shù)負(fù)責(zé)人全面負(fù)責(zé)該標(biāo)段的施工技術(shù)管理,與各級技術(shù)人員建立技術(shù)管理小組,負(fù)責(zé)各項專利技術(shù)問題的解決,施工方案的編制與監(jiān)督執(zhí)行。建立技術(shù)責(zé)任制,對各級技術(shù)人員建立明確的職責(zé)和范圍,以達到各負(fù)其責(zé),各司其職,充分調(diào)動各級技術(shù)人員的積極性和創(chuàng)造性,及時解決施工中的技術(shù)問題,以方案指導(dǎo)施工,防止出現(xiàn)返工現(xiàn)象而影響工期。各技術(shù)管理小組及時總結(jié)施工中出現(xiàn)的問題與經(jīng)驗,把易于施工、保證質(zhì)量、加快進度的各項措施加以推廣,以更好地指導(dǎo)后續(xù)作業(yè)。5、從施工組織與管理上保證。在施工生產(chǎn)過程中,合理支排各工序的交接與搭接,確保每道工序的施工順利進行。各工序施工前均進行詳細(xì)的施工技術(shù)交底,統(tǒng)一施工工藝,加強過程控制,出專職質(zhì)檢員負(fù)責(zé)施工全過程的工序質(zhì)量檢查。確保各工序達到規(guī)定的質(zhì)量目標(biāo),防止出現(xiàn)不合格工序返工而影響工期的現(xiàn)象。在施工時如果因客觀原因而延誤工期時,經(jīng)監(jiān)理工程師同意后,利用多加夜班,集中人力物力搶回關(guān)鍵線路工期。6、從安全生產(chǎn)上保證。加強職工法規(guī)、安全制度的學(xué)習(xí)與教育,增強安全生產(chǎn)觀念。對于新工人進行崗位教育,對于特種操作人員,除接受一般性的安全教育外,還進行專門的安全操作技術(shù)教育訓(xùn)練。在施工生產(chǎn)過程中,進行經(jīng)常性在施工生產(chǎn)中,對安全生產(chǎn)進行監(jiān)督檢查。并結(jié)合季節(jié)的特點,做好防水、防觸電、防墜落、防坍塌、防火等各項措施和制度。項目經(jīng)理部成立安全小組,設(shè)專職人員負(fù)責(zé)日常的安全檢查、監(jiān)督,保證施工順利進行。7、從后勤供應(yīng)上保證。加強機械設(shè)備和車輛保養(yǎng)、維修,保障施工正常運轉(zhuǎn)。搞好職工食堂,防病治病,保障職工身體健康,保證正常的出勤率,確保工期。8、從工作關(guān)系及其協(xié)調(diào)上保證。根據(jù)不同工作關(guān)系的客觀性采取不同的處理方法。比如企業(yè)內(nèi)的經(jīng)濟協(xié)作關(guān)系經(jīng)過企業(yè)內(nèi)部分工、分責(zé)、分權(quán)、分利來解決。9、加強與工作各方的聯(lián)系,做好與當(dāng)?shù)鼐用竦膮f(xié)調(diào)工作,取得她們的支持與配合,使工程得以順利進行。。二十四、組織保證措施1、快速進場,快速展開我單位中標(biāo)后,迅速成立以項目經(jīng)理、總工程師為首的施工領(lǐng)導(dǎo)小組,根據(jù)工程各工序工種,合理組織勞動力,配足人員、機具設(shè)備,統(tǒng)一指揮,統(tǒng)一調(diào)度,統(tǒng)一安排。主要施工人員、施工機械設(shè)備做到”三快”,即”進場快、施工準(zhǔn)備快、開工快”。2、準(zhǔn)備工作有條不紊進場后,積極配合業(yè)主加強征地拆遷,創(chuàng)造良好的施工外部環(huán)境;施工便道、施工用水、用電及施工臨時設(shè)施本著先通后善的原則,在一個月內(nèi)全部完成,保證主體工程順利開工。3、科學(xué)組織,合理安排加強施工計劃管理的科學(xué)性,突出重點、兼顧一般,運用統(tǒng)籌學(xué)、網(wǎng)絡(luò)技術(shù)、系統(tǒng)工程進行實施性施工組織設(shè)計編制;并在實施過程中針對實際情況不斷充實調(diào)整。4、人員保障組建強有力的項目經(jīng)理部,選派富有經(jīng)驗、并具有敢打敢拼精神的工程師擔(dān)任項目經(jīng)理;并選派具有豐富施工經(jīng)驗的專業(yè)化施工隊伍。5、設(shè)備保障本項目設(shè)備投入量大,施工前期一定要按計劃上足設(shè)備,并留有余地,加強保養(yǎng)和維修,保證設(shè)備的完好率。二十五、技術(shù)保證措施1、編制網(wǎng)絡(luò)計劃項目經(jīng)理部進場后,將根據(jù)技術(shù)文件和合同文件要求及現(xiàn)場實際情況重新編制實施性網(wǎng)絡(luò)計劃,并以此進行施工組織、調(diào)度、同時以此為依據(jù)編排月、旬、日作業(yè)計劃,特別對控制性工程和重點工程的施工必須制訂單項作業(yè)計劃,并具體采取如下措施進行工期控制:2、按總體計劃工期90%的日歷天數(shù),制訂各單位工程目標(biāo)計劃和相應(yīng)措施。3、全面編制各項總工期、階段工期和工序作業(yè)工期三級網(wǎng)絡(luò)計劃,并向所設(shè)計工期的直接、間接施工隊伍分解落實。4、強化施工過程中的勞動力、機械設(shè)備、材料供應(yīng)等資源平衡協(xié)調(diào)、監(jiān)督指導(dǎo)工作。5、預(yù)先制訂網(wǎng)
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2024年遙控電子管前置放大器項目可行性研究報告
- 夜宵店餐飲合同范例
- 臨時解聘合同范例
- 果筐加工合同范例
- 核酸試劑銷售合同范例
- 聘請老師合同范例
- 五年級數(shù)學(xué)(小數(shù)除法)計算題專項練習(xí)及答案匯編
- 2024至2030年鉑金900濾芯式過濾器項目投資價值分析報告
- 課程咨詢合同范例
- 品牌營銷托管合同范例
- 中華聯(lián)合財產(chǎn)保險股份有限公司校招筆試題目
- 七年級上冊生物2024-2025學(xué)年新人教版期末綜合試卷(含答案)
- 進口再生鑄造鋁合金原料檢驗規(guī)程
- 軟件開發(fā)公司代碼備份與恢復(fù)方案
- 《貨幣銀行學(xué)》課件
- 2024年人教版初二道德與法治上冊期末考試卷(附答案)
- 3dmax整體設(shè)計說課稿
- 2024-2025形勢與政策全冊課件
- 2024-2025學(xué)年統(tǒng)編版八年級語文上學(xué)期 專題03 綜合性學(xué)習(xí)
- 中國民間藝術(shù)的奇妙之旅學(xué)習(xí)通超星期末考試答案章節(jié)答案2024年
- 使用個人充電樁協(xié)議書(2篇)
評論
0/150
提交評論