新建鄭州至濟南鐵路(山東段)工程ZJTLSG-2標段
五分部10t龍門吊安
裝拆卸方案
二〇二〇年六月
新建鄭州至濟南鐵路(山東段)工程ZJTLSG-2標段
五分部10t龍門吊安
裝拆卸方案
編制:
審核:
批準:
二〇二〇年六月
目錄
第一章編制說明....................................................................................................................1
1.1編制依據(jù)....................................................................................................................1
1.2編制原則....................................................................................................................1
1.3編制范圍....................................................................................................................1
第二章工程概況....................................................................................................................2
2.1工程簡介....................................................................................................................2
2.2線路概況....................................................................................................................2
2.3工程地質(zhì)情況............................................................................................................2
2.4龍門吊配置情況........................................................................................................2
第三章施工安排....................................................................................................................4
3.1項目管理組織............................................................................................................4
3.2項目管理目標............................................................................................................5
第四章施工計劃....................................................................................................................6
第五章施工準備與資源配置計劃........................................................................................7
5.1施工準備....................................................................................................................7
5.1.1技術(shù)準備.........................................................................................................7
5.1.2施工準備.........................................................................................................9
5.2汽車吊機選用及參數(shù)計算......................................................................................10
5.2.1單機吊裝起重量...........................................................................................10
5.2.2起重高度計算...............................................................................................10
5.2.3起重臂長度計算...........................................................................................11
5.3索具選擇..................................................................................................................13
5.4資源配置計劃..........................................................................................................15
5.5勞動力配置計劃......................................................................................................16
5.6原材料進場計劃......................................................................................................16
第六章施工方法及工藝要求..............................................................................................17
6.1安裝流程..................................................................................................................17
6.2軌道安裝..................................................................................................................17
6.2.1軌道基礎(chǔ)施工...............................................................................................17
1
6.2.2走行軌道安裝...............................................................................................18
6.3支腿的組裝..............................................................................................................19
6.4主梁吊裝..................................................................................................................19
6.5附屬設(shè)施的吊裝......................................................................................................22
6.6電氣設(shè)備安裝與調(diào)整..............................................................................................23
6.6.1電氣設(shè)備安裝...............................................................................................23
6.6.2電氣設(shè)備調(diào)整...............................................................................................23
6.7安全防護裝置..........................................................................................................24
6.8龍門吊防碰撞裝置..................................................................................................24
6.9檢驗標準..................................................................................................................24
6.10龍門吊試驗............................................................................................................25
6.11龍門吊拆除............................................................................................................28
6.11.1拆除流程.....................................................................................................28
6.11.2安全技術(shù)交底.............................................................................................28
6.11.3場地要求.....................................................................................................29
6.11.4拆解人員.....................................................................................................29
6.11.5主要起重設(shè)備、機具的準備.....................................................................29
6.11.6起重小車吊裝拆除.....................................................................................30
6.11.7地梁與支腿分離.........................................................................................30
6.11.8主梁吊裝拆除.............................................................................................30
6.11.9主梁和支腿解體.........................................................................................31
6.11.10清點入庫...................................................................................................31
6.12吊裝過程注意事項................................................................................................31
第七章安全檢查及驗收......................................................................................................31
7.1龍門吊整體安全檢查及驗收內(nèi)容..........................................................................32
7.2吊鉤安全檢查及驗收內(nèi)容......................................................................................32
7.3滑輪與護罩安全檢查及驗收內(nèi)容..........................................................................33
7.4制動器安全檢查及驗收內(nèi)容..................................................................................33
7.5安全防護裝置安全檢查及驗收內(nèi)容......................................................................34
7.6架體安全檢查及驗收內(nèi)容......................................................................................34
2
7.7傳動系統(tǒng)安全檢查及驗收內(nèi)容..............................................................................34
7.8龍門吊驗收要求......................................................................................................35
7.9龍門吊安全檢查記錄表..........................................................................................35
7.10龍門吊驗收人員....................................................................................................36
第x章施工安全保證措施..................................................................................................37
8.1組織保障..................................................................................................................37
8.1.1組織機構(gòu).......................................................................................................37
8.1.2各應(yīng)急小組成員聯(lián)系方式...........................................................................40
8.2技術(shù)措施..................................................................................................................41
8.2.1技術(shù)要求.......................................................................................................41
8.2.2安全技術(shù)措施...............................................................................................41
8.2.3安全保證措施...............................................................................................42
8.3應(yīng)急準備..................................................................................................................43
8.4危險源辨識及危險源原因分析..............................................................................43
8.4.1人為因素.......................................................................................................45
8.4.2施工臨時用電...............................................................................................46
8.4.3機械設(shè)備.......................................................................................................47
8.4.4高空作業(yè).......................................................................................................48
8.4.5電焊與氣焊安全保證措施...........................................................................48
8.5應(yīng)急響應(yīng)..................................................................................................................49
8.6信息發(fā)布..................................................................................................................52
8.7后期處置..................................................................................................................52
8.8保障措施..................................................................................................................53
8.9應(yīng)急救援路線..........................................................................................................54
第九章新型冠狀病毒肺炎疫情防控預(yù)案..........................................................................56
9.1風險分析..................................................................................................................56
9.2防護及應(yīng)急救援組織機構(gòu)及職責..........................................................................56
9.3預(yù)防疫情防控措施..................................................................................................59
9.4監(jiān)測與預(yù)警..............................................................................................................60
9.5應(yīng)急響應(yīng)..................................................................................................................61
3
9.6后期處置..................................................................................................................63
9.7應(yīng)急保障..................................................................................................................63
第十章龍門吊基礎(chǔ)驗算書..................................................................................................64
10.1設(shè)計依據(jù)................................................................................................................64
10.2概述........................................................................................................................65
10.3基本情況................................................................................................................65
10.4基礎(chǔ)梁正截面強度配筋計算................................................................................65
10.5基礎(chǔ)梁承受的最大剪力計算................................................................................65
4
第一章編制說明
1.1編制依據(jù)
表1.1編制依據(jù)
序號類別文件名稱編號
起重機械安全規(guī)程第5部分:橋式和門式起
1GB6067.5-2014
重機
2起重機械安全技術(shù)監(jiān)察規(guī)程-橋式起重機TSGQ0002-2008
3配電系統(tǒng)電氣裝置安裝工程施工及驗收規(guī)范DL/T5759-2017
規(guī)程、規(guī)范
4起重機試驗規(guī)范和程序GB/T5905-2011
5建筑機械使用安全技術(shù)規(guī)程JGJ33-2012
6通用門式起重機GB/T14406-2011
7起重設(shè)備安裝工程施工及驗收規(guī)范GB50278-2010
8文件五分部施工組織設(shè)計
1.2編制原則
1安全第一原則
認真貫徹落實國家“安全第一、預(yù)防為主、綜合治理”的安全生產(chǎn)方針,全面、
系統(tǒng)做好鋼筋加工場龍門吊機安裝及拆除過程中的安全措施。
2堅決執(zhí)行規(guī)范、規(guī)程原則
貫徹執(zhí)行各項技術(shù)標準、安全技術(shù)規(guī)程,執(zhí)行業(yè)主針對本工程建設(shè)制定的各項安
全管理辦法、細則和規(guī)程。確保龍門吊安裝質(zhì)量,為實現(xiàn)工程順利進行提供機械保
障,以適應(yīng)安全生產(chǎn)和施工組織安排的要求。
3杜絕事故原則
有效對龍門吊安裝、拆除過程實施監(jiān)控,杜絕安全事故的發(fā)生。
1.3編制范圍
本方案適用于新建鄭州至濟南鐵路山東段站前工程ZJTLSG-2標段五分部鋼筋廠
龍門吊(23m跨10t)安裝及拆除。
1
第二章工程概況
2.1工程簡介
新建鄭州至濟南鐵路山東段站前工程ZJTLSG-2DK109+179.16(茌平特大橋左線
905#橋墩)~DK119+508.91(跨316特大橋左線濟南臺),正線線路長度9.94公里,
施工內(nèi)容主要有單線特大橋3座,2段區(qū)間路基以及站場路基。
橋涵工程:茌平特大橋左線7.117km、茌平特大橋右線7.143km、聊城立折線跨京
九客專特大橋1.727km;連續(xù)梁9處、7-32m道岔梁1處、3-32m雙線變線間距連續(xù)梁
1處、2處(12+16+12)m剛構(gòu)連續(xù)梁,框構(gòu)橋10座15205頂平方、框架涵6座834.6
橫延米。
路基工程:共2段區(qū)間路基,1段站場路基。區(qū)間路基里程為DK116+296.13~
DK116+800短鏈長度389.721,實際長度0.114km,右線區(qū)間路基里程為
DK116+322.35~DK116+800短鏈長度364.821,實際長度為0.113km,站場路基為聊
城西站站場路基,正線DK116+800~DK119+508.91,長度2.709km。
2.2線路概況
束。
圖2.2線路平面走向示意
2.3工程地質(zhì)情況
沿線既有鐵路東西、南北縱橫交錯;既有公路(高速公路、國道、省道、鄉(xiāng)道)
2.4龍門吊配置情況
現(xiàn)安裝6臺10t-23m龍門吊機,龍門吊機吊重10t,跨度23m,起升高度6.3m。
2
龍門吊機主橫梁采用焊接包箱結(jié)構(gòu)形式,主梁總長度23.4m。主橫梁與支腿采用高
強螺栓連接,主梁下設(shè)電動葫蘆。支腿采用雙剛腿結(jié)構(gòu),高度7.062m。
表2.4-1場站龍門吊配置情況
序號場站名稱樁號投入主要設(shè)備數(shù)量功能區(qū)
1#綜合場DK114+000右側(cè)
110t龍門吊4臺7#鋼筋加工廠
站500
2#綜合場
2DK118+50010t龍門吊2臺9#鋼筋加工廠
站
表2.4-2龍門吊主要組成及各部分重量
序號名稱數(shù)量重量(kg)備注
1主梁1
5700同類構(gòu)件總重
2上橫梁4
3剛性支腿43700同類構(gòu)件總重
4電動葫蘆11000同類構(gòu)件總重
5地梁21600同類構(gòu)件總重
6大車運行機構(gòu)2//
3
第三章施工安排
3.1項目管理組織
為完成本工程任務(wù),加強項目施工標準化管理,確保工程建設(shè)工期、質(zhì)量、安全
目標,項目部組建連續(xù)梁施工的第五架子隊,由生產(chǎn)經(jīng)理崔永峰負責,技術(shù)由總工程
亮負責,由工程技術(shù)部、安全部、質(zhì)量部、財務(wù)資金部、計劃合同部、物資設(shè)備部、
征地拆遷部、綜合辦公室、測量部、試驗室共10個職能部室配合,現(xiàn)場由孔豪、王世
國等專業(yè)工程師按照龍門吊安拆方案指導現(xiàn)場施工,對現(xiàn)場進行管理和協(xié)調(diào)工作;現(xiàn)
場組織機構(gòu)見下圖:
項目經(jīng)理
(游珈驊)
協(xié)調(diào)經(jīng)理
生產(chǎn)經(jīng)理項目總工
商務(wù)經(jīng)理(訾乃強)
(張龍)(崔永峰)(程亮)
綜合辦公室物資設(shè)備部計劃合同部工程技術(shù)部測量部安全部質(zhì)量部工地試驗室
財務(wù)資金部征地拆遷部
(劉冬)(周長江)(劉慶冰)(喬守靖)(康新建)(王建耀)(張建立)(劉海洋)
第五架子隊第五架子隊
孔豪王世國
圖3.1現(xiàn)場組織結(jié)構(gòu)
表3.1施工管理人員
序號職務(wù)姓名備注
1項目經(jīng)理游珈驊負責龍門吊安拆全面工作
2總工程師程亮負責施工隊對安拆方案執(zhí)行的監(jiān)督工作
3生產(chǎn)經(jīng)理崔永峰按照龍門吊安拆專項方案進行現(xiàn)場管理
負責龍門吊安拆安全監(jiān)督工作、龍門吊安
4安全總監(jiān)王建耀
拆人員安全交底擠培訓工作
5質(zhì)量總監(jiān)張建立負責對龍門吊安拆質(zhì)量監(jiān)督
6工程技術(shù)部長喬守靖負責對龍門吊安拆人員安全監(jiān)督
7物資部長周長江負責對龍門吊安拆設(shè)備調(diào)度工作
4
序號職務(wù)姓名備注
8測量負責人康新健負責對龍門吊安拆過程實時監(jiān)控
9施工現(xiàn)場負責人孔豪現(xiàn)場管理
10施工現(xiàn)場負責人王世國現(xiàn)場管理
3.2項目管理目標
表3.2施工管理目標
序號項目內(nèi)容
龍門吊安裝時間:2023年6月20日-2023年8月31日計劃工期72天
工期目
1龍門吊拆除時間:2023年9月1日-2023年9月15日
標
2023年10月1日-2023年10月15日計劃工期30天
質(zhì)量目
2順利通過龍門吊安裝質(zhì)量驗收
標
安全目
3項目實施中無安全責任事故
標
文明工1)做到依法施工,文明施工,杜絕違法施工、野蠻施工事件發(fā)生。
4地建設(shè)2)現(xiàn)場布局合理,不擾民、場地整潔,物流有序,標識醒目,標牌規(guī)
目標范,達到建設(shè)單位要求的安全文明工地標準。
環(huán)保目控制噪聲、粉塵、固體廢棄物、有毒有害氣體、污水污染,排放達標;
5
標無嚴重擾民;無環(huán)保事件發(fā)生
5
第四章施工計劃
根據(jù)總體施工前期計劃安排7#鋼筋加工廠4臺10t共軌龍門吊(23m跨),龍門
吊計劃同時安裝,基礎(chǔ)建設(shè)及龍門吊安裝計劃為:
龍門吊基坑開挖:2023年6月20日~2023年6月22日;
基礎(chǔ)混凝土澆筑:2023年6月23日~2023年6月28日;
龍門吊走行軌道安裝:2023年6月29日~2023年7月13日;
龍門吊組裝:2023年7月14日~2023年7月16日;
龍門吊吊裝:2023年7月17日;
龍門吊附屬設(shè)施安裝:2023年7月17日~2023年7月18日;
龍門吊試運行:2023年7月19日;
龍門吊取證交驗:2023年7月21日。
7#鋼筋加工場龍門吊拆除施工:2023年9月1日~2023年9月15日
根據(jù)總體施工前期計劃安排9#鋼筋加工廠2臺10t共軌龍門吊(23m跨),龍門
吊計劃同時安裝,基礎(chǔ)建設(shè)及龍門吊安裝計劃為:
龍門吊基坑開挖:2023年8月1日~2023年8月2日;
基礎(chǔ)混凝土澆筑:2023年8月3日~2023年8月8日;
龍門吊走行軌道安裝:2023年8月9日~2023年8月23日;
龍門吊組裝:2023年8月24日~2023年8月25日;
龍門吊吊裝:2023年8月26日;
龍門吊附屬設(shè)施安裝:2023年8月27日~2023年8月28日;
龍門吊試運行:2023年8月29日;
龍門吊取證交驗:2023年8月31日。
9#鋼筋加工場龍門吊拆除施工:2023年10月1日~2023年10月15日
6
第五章施工準備與資源配置計劃
5.1施工準備
5.1.1技術(shù)準備
1對參加拼裝及拆除施工人員進行安全技術(shù)交底。
2本工程10t龍門吊安拆由具有專業(yè)資質(zhì)公司進行施工,并提前做好龍門吊報
裝、報監(jiān)、報拆等手續(xù)的辦理。
310t龍門吊主要由1片主梁、4支腿、1臺電動葫蘆起重機、2個地梁、供電系
統(tǒng)、爬梯、護欄等主要構(gòu)件組成。龍門吊主梁采用箱式焊接結(jié)構(gòu)形式單列,分二段制
造,段間采用高強螺栓(廠家提供)連接。主梁與支腿采用高強螺栓(廠家提供)連
接,主梁設(shè)天車導電架。按照23m跨龍門吊MH10T-23mA3龍門吊技術(shù)特性進行施工
安排。
表5.1.1-1MH10t-23mA3門式起重機技術(shù)特性
主要參數(shù)和用途
1額定起重量10t跨度23m
2整機工作級別A3起升高度6.3m
主鉤左右極限位
3大車基距5.8m1293/1893mm
置
4整機功率18.2KW最大輪壓55KN
5主要結(jié)構(gòu)形式包箱+花架操作方式地操
6吊具形式吊鉤
表5.1.1-2MH10t-23mA3門式起重機工作機構(gòu)主要特性
工作機構(gòu)主要特性
相應(yīng)最大起
110t起升速度7m/min
重量
起升
2機構(gòu)制動力矩147.1Kn/m鋼絲繩6*37+1-15.5
3電機型號ZD151-4電機功率13KW
4電機型號ZD21-4/2臺電機功率0.8KW
小車
運行
5工作級別M3運行速度20m/min
7
工作機構(gòu)主要特性
6電機型號YSE180-4/2臺電機功率2.2KW
大車
7行走工作級別M3運行速度20m/min
機構(gòu)
8減速機裝置LDHC變速適應(yīng)軌道P38
9電源三相交流380V50HZ
圖5.1.1-1龍門吊立面示意
8
圖5.1.1-2龍門吊側(cè)面示意
5.1.2施工準備
1施工場地事先進行硬化處理,場地開闊沒有與安裝施工相干涉的障礙物,吊車
工作區(qū)域地基堅實可靠。
2龍門吊走行線建設(shè)完成,并驗收合格。
3施工人員必須熟悉施工現(xiàn)場,熟悉本安裝方案,技術(shù)人員做好施工工序的技術(shù)
安全交底。
4對配合安裝吊車及人員進行資歷審核及技術(shù)安全交底,配合機具進行全面檢
查。
5對所有用于安裝作業(yè)的工器具進行全面檢查,所有的安全裝置必須齊全可靠。
9
6作業(yè)中使用的安全帶、速差保護器、保險繩應(yīng)經(jīng)檢驗合格。
7布設(shè)龍門吊拼裝、拆除安全施工警戒范圍、設(shè)置各類施工警示標志。
8龍門吊拼裝、拆除起重機械用吊裝鋼絲繩等經(jīng)檢查合格,各類輔助鋼絲繩使用
前嚴格檢查,起重機械操作人員持證上崗。
9吊裝技術(shù)人員(龍門吊生產(chǎn)廠家委派)具備多年吊裝經(jīng)驗,且持證上崗,吊裝
現(xiàn)場設(shè)專人安全監(jiān)護。
10配備足夠的安全防護用品安全帶、安全繩等,防護用品驗收合格。
1110t龍門吊主梁和支腿分開吊裝,主梁重為5.7噸,吊裝用1臺25t汽車吊。
5.2汽車吊機選用及參數(shù)計算
5.2.1單機吊裝起重量
以最大構(gòu)件為驗算對象,若能滿足受力要求,那么其他構(gòu)件能滿足起吊受力要
求。
單機吊裝的起重量應(yīng)滿足下式要求:
Q×K≥Q1+Q2
根據(jù)設(shè)計圖紙中主梁最重按5.7噸,即Q1=5.7噸,考慮索具重量Q2=0.5噸,K
為起重機降低系數(shù),取0.80。即:Q≥7.8噸。
5.2.2起重高度計算
H≥h1+h2+h3+h4
式中:H——起重機的起重高度(m),停機面至吊鉤的距離;
h1——龍門吊支腿高度(m),
h2——安裝間隙,視具體情況而定,一般取0.2~0.5m;
h3——龍門吊主梁高度(m);
h4——索具高度(m),綁扎點至吊鉤的距離,視具體情況而定。
10
圖5.2.2-1起重機起重高度示意
由圖5.2.2-1龍門吊立面示意可推斷出h1和h3高度總和為8.5m,h2安裝間隙取
0.5m。h4索具高度通過以下計算進行推算:
主梁采用兩點吊裝的方式進行吊裝,吊裝方式如下圖示意:
長方形物體吊點的選擇:兩個吊點時吊點分別距桿件兩端的距離為0.21L處。
圖5.2.2-2主梁吊裝示意
如上圖可以推斷出h4索具高度為7.02m。
選用起重機的起重高度H≥8.5+0.5+7.02米,起重高度H取16.02m。
5.2.3起重臂長度計算
L≥(H+ha-hb)/sinα
式中:L——起重臂長度(m);
H——起重高度(m);
11
ha——起重臂頂至吊鉤底面的距離(m),ha取3m;
hb——起重臂底鉸至停機面距離(m),本工程取1.5m;
α——起重臂仰角,一般取70°~77°,本工程取70°。
L≥(16.02+3-1.5)/sin(70°)=18.64m。
吊車工作半徑取6m,綜合考慮單機吊起重量Q≥7.8t、起重高度H≥
16.02m、起重臂長L≥18.64m及起重機的工作幅度,參考吊車性能參數(shù)表,選用汽車起
重機QY25K汽車吊滿足施工要求。
表5.2.325t汽車吊主要性能與參數(shù)
序號項目數(shù)值備注
1最大額定總起重量25000kg
2基本臂最大起重力矩970kN.m
3最長主臂最大起重力矩510.12kN.m.
4主臂最大起升高度32.5m
5副臂最大起升高度.40.3m
6外形尺寸(長×寬×高)12750×2500×3225mm
7主臂長10.2~32.0m
8副臂長7.5m
圖5.2.3-1主臂起重性能
12
圖5.2.3-2起升高度曲線
5.3索具選擇
13
鋼絲繩允許拉力按下列公式計算:
[Fg]=αFg/K
式中[Fg]——鋼絲繩的允許拉力(KN);
Fg——鋼絲繩的鋼絲破斷拉力總和(KN);
α——換算系數(shù),按表5.3-1取用;
K——鋼絲繩的安全系數(shù),按表5.3-2取用。
5.3-1鋼絲繩破斷拉力換算系數(shù)
序號鋼絲繩結(jié)構(gòu)換算系數(shù)
16×190.85
26×370.82
36×610.8
表5.3-2鋼絲繩的安全系數(shù)
序號用途安全系數(shù)用途安全系數(shù)
1作纜風3.5作吊索、無彎曲時5~7
2用于手動起重設(shè)備4.5作捆綁吊索8~10
3用于機動起重設(shè)備5~6用于載人的升降機14
N=K1*G/n*1/Sinα≤P/K2
式中:N—每根鋼絲繩索具的受拉力;
G—主梁重量;
n—吊索根數(shù);n=2
α—吊索鋼絲繩與主梁水平夾角;
P—吊索鋼絲繩的破斷拉力;
K1—吊裝時動載系數(shù),取1.2;K2—吊索鋼絲繩的安全系數(shù),取5。
主梁質(zhì)量取G=5.7×10=57KN,由圖5.2.2-2主梁吊裝示意中可知吊索鋼絲繩與主
梁水平夾角α取45°
N=K1*G/n*1/Sinα=1.2*57/2*1/Sin45°=48.4KN
擬選用6*37鋼絲繩,鋼絲繩φ28mm,公稱抗拉強度1670N/mm2,破斷拉力為
466KN。
[Fg]=αFg/K
式中:[Fg]——鋼絲繩的允許拉力(KN);
Fg——鋼絲繩的鋼絲破斷拉力總和(KN);
14
α——換算系數(shù),按表5.3-1取用;對6×37鋼絲繩,α=0.82。
K——鋼絲繩的安全系數(shù),按表5.3-2取用。K=5
[Fg]=0.82*466/5=76.4KN
因為N=48.4KN<[Fg]=76.4KN
所以選用6*37鋼絲繩,鋼絲繩φ28mm,公稱抗拉強度1670N/mm2,破斷拉力
466KN,鋼絲繩滿足要求。
5.4資源配置計劃
表5.4龍門吊安裝施工設(shè)備工具(一臺龍門吊安裝時需用)
序號設(shè)備名稱數(shù)量備注
1汽車吊1臺25噸
2水準儀2臺
3500V兆歐表1臺
45t手拉葫蘆4件
5萬用電表1臺
650M鋼卷尺1把
7千斤頂1臺
81M鋼直尺1把
9電焊機2臺
10100MM塞尺1把
11氣割設(shè)備2套
12框式水平儀1件
13切割機2臺
140~200MM游標卡尺1把
15角向磨光機2臺
160~200MM彈簧稱1把
17安全帶5條
18活動扳手2把
19力矩扳手2把
20Y11-40騎馬式鋼絲繩卡20個
15
21麻繩φ22cm*80米
22鋼絲繩φ12cm*20米
23套筒扳手1把
24撬棍2把
25活動扳手2把
26力矩扳手2把
5.5勞動力配置計劃
表5.5勞動力配置
序號設(shè)備名稱數(shù)量備注
1管理人員2
2信號工2持證上崗
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
- 6. 下載文件中如有侵權(quán)或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 雨水收集利用的政策與實踐分析計劃
- 教學評價與反思落實計劃
- 人事部年度工作計劃分析
- 塔吊相關(guān)項目投資計劃書范本
- 班級時事討論活動的開展計劃
- 《促銷員升級培訓》課件
- 跨部門協(xié)作與整合培訓
- 《供電系統(tǒng)節(jié)能改》課件
- 《高端餐飲成都》課件
- 輕度抑郁發(fā)作護理查房
- 烤煙煙葉等級圖庫課件
- 純電動汽車整車控制器(VCU)設(shè)計方案
- CQJTGT D07-2021 重慶市高速公路環(huán)境保護與綠化景觀工程標準化設(shè)計指南
- (完整版)設(shè)計的進度計劃保證措施
- 7的乘法口訣說課--完整版PPT課件
- 危大工程安全管理檔案
- 最新標點符號用法
- 2022機械設(shè)備安全管理及保證措施
- 特困人員生活自理能力評估表
- 新風系統(tǒng)安裝合同模板
- 狂暴戰(zhàn)一鍵輸出宏
評論
0/150
提交評論