工投高新智谷一期EPC工程

2#塔吊安拆方案

編制單位:

編制人:

日期:

目錄

第一章編制依據(jù)..............................................................................................................................................1

第二章工程概況..............................................................................................................................................2

2.1工程建設(shè)概況表.................................................................................................................................2

2.2設(shè)計(jì)概況.............................................................................................................................................2

2.3工程施工條件.....................................................................................................................................3

2.3.1施工現(xiàn)場(chǎng)地質(zhì)情況..................................................................................................................3

2.3.2施工現(xiàn)場(chǎng)水文情況..................................................................................................................4

第三章施工安排..............................................................................................................................................5

3.1項(xiàng)目管理組織.....................................................................................................................................5

3.2項(xiàng)目管理目標(biāo).....................................................................................................................................6

3.3各項(xiàng)資源供應(yīng)方式.............................................................................................................................6

3.3.1勞務(wù)資源安排一覽表..............................................................................................................6

3.3.2大型機(jī)械設(shè)備采購(gòu)供應(yīng)安排一覽表.......................................................................................6

3.4施工流水段的劃分及施工工藝流程.................................................................................................6

3.4.1施工流水段劃分......................................................................................................................6

3.4.2施工工藝流程..........................................................................................................................6

3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施.............................................................................................6

第四章施工進(jìn)度計(jì)劃......................................................................................................................................8

第五章施工準(zhǔn)備與資源配置計(jì)劃..................................................................................................................9

5.1施工準(zhǔn)備計(jì)劃.....................................................................................................................................9

5.1.1技術(shù)準(zhǔn)備..................................................................................................................................9

5.1.2現(xiàn)場(chǎng)準(zhǔn)備..................................................................................................................................9

5.2資源配置計(jì)劃.....................................................................................................................................9

5.2.1勞動(dòng)力配置計(jì)劃......................................................................................................................9

5.2.2施工機(jī)具配置計(jì)劃................................................................................................................10

5.2.3測(cè)量計(jì)量?jī)x器配置計(jì)劃........................................................................................................10

第六章施工方法及工藝要求........................................................................................................................11

6.1方案及技術(shù)參數(shù)...............................................................................................................................11

6.2施工工藝流程...................................................................................................................................13

6.3施工要點(diǎn)...........................................................................................................................................13

6.3.1安裝工序................................................................................................................................13

6.3.2頂升加節(jié)................................................................................................................................18

6.3.3調(diào)試各安全裝置、驗(yàn)收........................................................................................................19

6.3.4群塔作業(yè)措施........................................................................................................................19

6.3.5拆除要點(diǎn)................................................................................................................................20

6.3.6檢查與驗(yàn)收要點(diǎn)....................................................................................................................22

6.3.7塔機(jī)安(拆卸)裝安全規(guī)程及技術(shù)措施.............................................................................23

6.4驗(yàn)收標(biāo)準(zhǔn)...........................................................................................................................................25

6.5驗(yàn)收程序...........................................................................................................................................25

6.6驗(yàn)收內(nèi)容...........................................................................................................................................25

6.7驗(yàn)收人員...........................................................................................................................................26

第七章各項(xiàng)管理計(jì)劃....................................................................................................................................27

7.1綠色施工管理計(jì)劃...........................................................................................................................27

7.1.1綠色施工組織機(jī)構(gòu)和職責(zé)分工............................................................................................27

7.1.2綠色施工實(shí)施措施................................................................................................................27

7.1.3綠色施工評(píng)價(jià)........................................................................................................................27

7.2進(jìn)度管理計(jì)劃...................................................................................................................................27

7.2.1施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工.....................................................................................27

7.2.2進(jìn)度管理措施........................................................................................................................28

7.3質(zhì)量管理計(jì)劃...................................................................................................................................28

7.3.1質(zhì)量控制目標(biāo)分解................................................................................................................28

7.3.2質(zhì)量管理的組織機(jī)構(gòu)和職責(zé)分工........................................................................................28

7.3.3確定質(zhì)量控制點(diǎn)....................................................................................................................28

7.3.4質(zhì)量保證措施........................................................................................................................28

7.4安全管理計(jì)劃...................................................................................................................................29

7.4.1職業(yè)健康安全管理目標(biāo)........................................................................................................29

7.4.2現(xiàn)場(chǎng)職業(yè)健康安全管理組織機(jī)構(gòu)和職責(zé)分工.....................................................................29

7.4.3職業(yè)健康安全重大危險(xiǎn)源....................................................................................................32

7.4.4職業(yè)健康安全資源配置計(jì)劃................................................................................................32

7.4.5安全生產(chǎn)管理制度................................................................................................................33

7.4.6職業(yè)健康安全保證措施........................................................................................................33

7.5成品保護(hù)計(jì)劃...................................................................................................................................33

7.5.1成品保護(hù)管理目標(biāo)................................................................................................................34

7.5.2成品和設(shè)備保護(hù)的組織機(jī)構(gòu)與職責(zé).....................................................................................34

7.5.3成品保護(hù)計(jì)劃及保證措施....................................................................................................34

第x章應(yīng)急預(yù)案............................................................................................................................................35

8.1應(yīng)急指揮機(jī)構(gòu)及職責(zé).......................................................................................................................35

8.2事故風(fēng)險(xiǎn)分析...................................................................................................................................35

8.3應(yīng)急救援程序...................................................................................................................................36

8.3.1應(yīng)急救援流程........................................................................................................................36

8.3.2事故報(bào)告原則........................................................................................................................36

8.3.3事故報(bào)告程序........................................................................................................................36

8.3.4報(bào)告內(nèi)容................................................................................................................................36

8.3.5應(yīng)急處置................................................................................................................................36

8.3.6應(yīng)急救援結(jié)束........................................................................................................................37

8.4應(yīng)急處置措施...................................................................................................................................37

8.4.1機(jī)械傷害事故應(yīng)急措施........................................................................................................37

8.4.2觸電事故應(yīng)急措施................................................................................................................37

8.5應(yīng)急物資準(zhǔn)備...................................................................................................................................38

8.6應(yīng)急響應(yīng)、響應(yīng)結(jié)束、演練...........................................................................................................38

8.6.1響應(yīng)程序................................................................................................................................38

8.6.2應(yīng)急響應(yīng)級(jí)別........................................................................................................................39

8.6.3應(yīng)急響應(yīng)結(jié)束........................................................................................................................39

8.6.4應(yīng)急演練................................................................................................................................40

第九章疫情防控管理........................................................................................Error!Bookmarknotdefined.

9.1組織機(jī)構(gòu)及職責(zé)...................................................................................Error!Bookmarknotdefined.

9.1.1疫情防控組織體系....................................................................Error!Bookmarknotdefined.

9.1.2疫情防控組織機(jī)構(gòu)職責(zé)............................................................Error!Bookmarknotdefined.

9.2項(xiàng)目?jī)?chǔ)備防疫物資...............................................................................Error!Bookmarknotdefined.

9.3施工現(xiàn)場(chǎng)準(zhǔn)備.......................................................................................Error!Bookmarknotdefined.

9.3.1落實(shí)工人來(lái)源............................................................................Error!Bookmarknotdefined.

9.3.2準(zhǔn)備施工現(xiàn)場(chǎng)............................................................................Error!Bookmarknotdefined.

9.3.3組織進(jìn)場(chǎng)檢查............................................................................Error!Bookmarknotdefined.

9.3.4進(jìn)場(chǎng)后安排................................................................................Error!Bookmarknotdefined.

9.4疫情預(yù)防及復(fù)工前后應(yīng)急措施...........................................................Error!Bookmarknotdefined.

9.4.1疫情預(yù)防措施............................................................................Error!Bookmarknotdefined.

9.4.2項(xiàng)目開(kāi)工后疫情防控應(yīng)急措施................................................Error!Bookmarknotdefined.

9.5疫情防控設(shè)備、物資、藥品清單及急救醫(yī)院...................................Error!Bookmarknotdefined.

9.5.1隔離醫(yī)務(wù)室設(shè)置........................................................................Error!Bookmarknotdefined.

9.5.2應(yīng)急救援醫(yī)院............................................................................Error!Bookmarknotdefined.

第十章附圖......................................................................................................................................................48

10.1塔機(jī)平面布置圖.............................................................................................................................48

第一章編制依據(jù)

序號(hào)類(lèi)別文件名稱(chēng)編號(hào)

1《建設(shè)工程安全生產(chǎn)管理?xiàng)l例》國(guó)務(wù)院令第393號(hào)

2國(guó)家行政文件《建筑起重機(jī)安全監(jiān)督管理規(guī)定》建設(shè)部令第166號(hào)

3《特種設(shè)備安全監(jiān)察條例》國(guó)務(wù)院第549號(hào)令

4《混凝土結(jié)構(gòu)設(shè)計(jì)規(guī)范》GB50010-2010

5《建筑地基基礎(chǔ)工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn)》GB50202-2018

6《混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范》GB50204-2015

7《建筑地基基礎(chǔ)設(shè)計(jì)規(guī)范》GB50007-2011

8《建筑結(jié)構(gòu)荷載規(guī)范》GB50009-2012

9《塔式起重機(jī)設(shè)計(jì)規(guī)范》GB/T13752-2017

10國(guó)家行業(yè)規(guī)范《鋼結(jié)構(gòu)設(shè)計(jì)標(biāo)準(zhǔn)》GB50017-2017

11《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011

12《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012

13《危險(xiǎn)化學(xué)品重大危險(xiǎn)源辨識(shí)》GB18218-2018

14《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011

15《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016

16《施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范》JGJ46-2005

17合同《工投高新智谷一期EPC》合同/

18設(shè)計(jì)文件《工投高新智谷一期EPC》施工圖/

19招投標(biāo)文件《工投高新智谷一期EPC》招投標(biāo)文件/

20《工投高新智谷一期EPC》澄清公告/

21《工投高新智谷一期EPC》勘察報(bào)告/

22其他《W7015-8E塔式起重機(jī)使用說(shuō)明書(shū)》/

23《W7015-8E塔式起重機(jī)操作手冊(cè)》

24《50T汽車(chē)吊使用說(shuō)明書(shū)》/

第1頁(yè)

第二章工程概況

2.1工程建設(shè)概況表

工程名稱(chēng)工投高新智谷一期EPC項(xiàng)目工程性質(zhì)創(chuàng)新產(chǎn)業(yè)園

建設(shè)規(guī)模7.15億工程地址新大道與柏堰灣路交口東南角

總占地面積73084㎡總建筑面積231062.40㎡

一期地塊紅線范圍內(nèi)的施工圖設(shè)

合肥工投高新科創(chuàng)投資發(fā)展有限公計(jì)、采購(gòu)、安裝、施工總承包、工

建設(shè)單位項(xiàng)目承包范圍

司程驗(yàn)收及項(xiàng)目建成后的維修維保

工作。

設(shè)計(jì)單位主要分包工程電梯、精裝、智能化設(shè)備及線路

確保A2#A2#或者B2#獲得安徽省

勘察單位江蘇新亞勘測(cè)設(shè)計(jì)有限公司質(zhì)量

優(yōu)質(zhì)工程“黃山杯“

監(jiān)理單位合肥工大建設(shè)監(jiān)理有限責(zé)任公司工期920日歷天

合同確保獲得“省級(jí)安全文明示范工

總承包單位中國(guó)建筑第x工程局有限公司要求安全地”稱(chēng)號(hào),同時(shí)必須達(dá)到“智慧工

地”要求

精度為L(zhǎng)OD400的BIM竣工模型及

分包單位蕪湖岳云科技

相關(guān)成果

工程主要功能

生產(chǎn)、研發(fā)、服務(wù)等

或用途

2.2設(shè)計(jì)概況

1、塔吊選型

本次擬安裝2#塔吊,塔吊型號(hào)W7015(臂長(zhǎng)65米),安裝高度60m。塔吊基礎(chǔ)位于B

8#樓和B9#樓之間地庫(kù)筏板內(nèi),塔吊基礎(chǔ)頂與地庫(kù)筏板底平齊。塔吊基礎(chǔ)為4根預(yù)制管樁+

承臺(tái)基礎(chǔ),滿(mǎn)足塔吊基礎(chǔ)承載力要求?;A(chǔ)尺寸8m×8m×1.5m,混凝土強(qiáng)度等級(jí)C35,基

礎(chǔ)和板地下室筏板斷開(kāi)。

臺(tái)

機(jī)

圖2.2-1塔機(jī)平面布置圖

第2頁(yè)

2、W7015塔機(jī)性能

2

塔機(jī)65m臂時(shí),起重性能如下:

2.3工程施工條件

1.5~2.0m,淤泥層厚度約0.5~1.7m。擬建場(chǎng)地地勢(shì)東北高西南低,地形起伏較大。

勘察期間測(cè)得勘探孔孔口處地面標(biāo)高為27.36~38.06m,高差10.70m。

2.3.1施工現(xiàn)場(chǎng)地質(zhì)情況

根據(jù)本次鉆探揭露、原位測(cè)試分層,并結(jié)合室內(nèi)土工試驗(yàn)定名,該場(chǎng)地內(nèi)各地層自上

而下分布為:

①層素填土(Qml)——層厚0.60~7.10m,層底標(biāo)高27.36~38.06m。灰褐色,以黏

性土為主,表層含植物根莖,局部夾淤泥、碎石、磚塊等,結(jié)構(gòu)松散,均勻性差。屬于欠

固結(jié)高壓縮性土。

ml

①1層淤泥(Q)——層厚0.80~1.70m,層底標(biāo)高26.94~29.04m?;液谏?,飽和,

流塑狀態(tài),含少量腐殖質(zhì)殘骸,具微嗅味。屬于欠固結(jié)高壓縮性土。

al+pl

②1層粉質(zhì)黏土(Q4)——層厚1.70~5.80m,層底標(biāo)高23.15~27.78m?;尹S色、

青灰色,濕,軟塑~可塑狀,含氧化鐵、鐵錳結(jié)核及少量灰白色高嶺土,干強(qiáng)度低,韌性

低。單橋靜探Ps值為1.54~1.58MPa,平均值為1.56MPa;其實(shí)測(cè)標(biāo)準(zhǔn)貫入試驗(yàn)錘擊數(shù)一

般為4~6擊/30cm,平均為5.1擊/30cm。該層分布不均勻,屬于中等壓縮性土。

al+pl

②2層黏土(Q4)——層厚0.70~4.30m,層底標(biāo)高23.06~35.23m?;尹S色、黃褐

色,稍濕,可塑狀,含氧化鐵、鐵錳結(jié)核及少量灰白色高嶺土,干強(qiáng)度中等,韌性中等。

單橋靜探Ps值為1.66~2.56MPa,平均值為2.05MPa;其實(shí)測(cè)標(biāo)準(zhǔn)貫入試驗(yàn)錘擊數(shù)一般為

9~12擊/30cm,平均為10.3擊/30cm。該層分布不均勻,屬于中等壓縮性土。

al+pl

③層黏土(Q3)——受孔深限制,部分勘探孔未揭穿該層,最大揭露層厚15.80m。

黃褐、褐黃色,稍濕,硬塑狀態(tài),含少量鐵錳氧化物及灰白色高嶺土,局部底部鐵錳結(jié)核

富集,干強(qiáng)度中等,韌性中等。單橋靜探Ps值為3.62~6.91MPa,平均值為5.58MPa;其

實(shí)測(cè)標(biāo)準(zhǔn)貫入試驗(yàn)錘擊數(shù)一般為16~20擊/30cm,平均為17.1擊/30cm。該層分布于整個(gè)

場(chǎng)區(qū)內(nèi),屬于中等壓縮性土。

al+pl

④層粉質(zhì)黏土(Q3)——受孔深限制,部分勘探孔未揭穿該層,最大揭露層厚

5.70m。黃褐色、褐黃色,稍濕,硬塑狀態(tài),含少量鐵錳氧化物,局部夾可塑狀態(tài)粉質(zhì)黏

第3頁(yè)

土及細(xì)砂,干強(qiáng)度中等,韌性中等。單橋靜探Ps值為5.93~9.90MPa,平均值為

7.72MPa;其實(shí)測(cè)標(biāo)準(zhǔn)貫入試驗(yàn)錘擊數(shù)一般為15~21擊/30cm,平均為18.2擊/30cm。該

層分布于整個(gè)場(chǎng)區(qū)內(nèi),屬于中等壓縮性土。

⑤層強(qiáng)風(fēng)化泥質(zhì)砂巖(K)——受孔深限制,部分勘探孔未揭穿該層,最大揭露層厚

4.60m?;野咨?、棕紅色,大多已風(fēng)化成壤及砂,汽車(chē)鉆無(wú)水可鉆進(jìn),含長(zhǎng)石、少量云母

等,局部夾薄層粉砂巖,堅(jiān)硬狀態(tài)。巖體完整程度為破碎,巖體基本質(zhì)量等級(jí)為Ⅴ級(jí)。其

實(shí)測(cè)標(biāo)準(zhǔn)貫入試驗(yàn)錘擊數(shù)一般為52~63擊/30cm,平均為57.8擊/30cm。該層在場(chǎng)地中普

遍分布,屬于低壓縮性強(qiáng)風(fēng)化極軟巖。

⑥層中風(fēng)化泥質(zhì)砂巖(K)——該層未揭穿,最大揭露層厚10.30m?;野咨?、棕紅色,

砂質(zhì)構(gòu)造、泥質(zhì)膠結(jié),巖芯呈柱狀及短柱狀,取芯率一般,巖石質(zhì)量指標(biāo)RQD為80%,柱

狀巖芯強(qiáng)度稍高,重?fù)艏磾?,聲沉,夾有石英、云母、長(zhǎng)石。巖體完整程度為較破碎,巖

體基本質(zhì)量等級(jí)為Ⅴ級(jí)。天然抗壓強(qiáng)度0.92~1.53MPa,平均1.22MPa。該層在場(chǎng)地中普

遍分布,屬于微壓縮性中風(fēng)化極軟巖。

2.3.2施工現(xiàn)場(chǎng)水文情況

擬建場(chǎng)地地下水類(lèi)型為上層滯水及基巖裂隙水。上層滯水主要賦存于①層素填土中,

主要由大氣降水滲入及地表逕流補(bǔ)給,受大氣降水、季節(jié)、氣候以及地形的變化較大,無(wú)

穩(wěn)定地下水位且分布不連續(xù),主要以蒸發(fā)方式排泄;基巖裂隙水主要賦存于⑤層強(qiáng)風(fēng)化泥

質(zhì)砂巖及⑥層中風(fēng)化泥質(zhì)砂巖中,主要由地下徑流補(bǔ)給,其排泄方式為徑流排泄??辈炱?/p>

間測(cè)得上層滯水穩(wěn)定地下水位埋深為0.52~2.65m,相應(yīng)的穩(wěn)定地下水位標(biāo)高為31.61~

38.17m,地下水水位年變化幅度為1.0~1.5m。

根據(jù)區(qū)域水文地質(zhì)資料,本場(chǎng)地歷史最高水位曾接近地表,近3~5年最高水位埋深

約0.5m。

第4頁(yè)

第三章施工安排

3.1項(xiàng)目管理組織

表3.1-1總承包項(xiàng)目管理人員

部門(mén)人員職責(zé)

負(fù)責(zé)總協(xié)調(diào)工作,負(fù)領(lǐng)導(dǎo)責(zé)任,施工人員組織,合理安排工序,進(jìn)度

項(xiàng)目經(jīng)理胡延濤

計(jì)劃考核,保證工作按要求有序進(jìn)行

1、施工人員組織,合理安排工序,進(jìn)行方案交底,過(guò)程技術(shù)復(fù)核,

保證工程質(zhì)量滿(mǎn)足要求;

項(xiàng)目執(zhí)行經(jīng)理劉志洋

2、負(fù)責(zé)圖紙審核、設(shè)計(jì)變更、圖紙的深化等工作;

3、參加組織施工方案的編制,審核技術(shù)交底;

項(xiàng)目總工康宋全面負(fù)責(zé)現(xiàn)場(chǎng)技術(shù)管理和復(fù)核、現(xiàn)場(chǎng)工作安排與協(xié)調(diào)

商務(wù)經(jīng)理劉莉負(fù)責(zé)洽商各種費(fèi)用、簽證收量,負(fù)責(zé)月報(bào)量或節(jié)點(diǎn)報(bào)量

1、對(duì)本項(xiàng)目的安全生產(chǎn)管理工作負(fù)責(zé),協(xié)助項(xiàng)目經(jīng)理做好對(duì)有關(guān)安

全生產(chǎn)法律、法規(guī)及規(guī)章制度的貫徹落實(shí),并檢查監(jiān)督執(zhí)行。

2、負(fù)責(zé)并參與本項(xiàng)目安全生產(chǎn)管理制度、安全技術(shù)措施計(jì)劃和安全

技術(shù)操作規(guī)程的制定工作,督促落實(shí),并對(duì)起執(zhí)行情況進(jìn)行檢查。

3、負(fù)責(zé)對(duì)現(xiàn)場(chǎng)違章作業(yè)、違章指揮、違反勞動(dòng)紀(jì)律的人員和行為進(jìn)

行查處;正確分析、判斷和處理各種事故隱患,參與事故隱患整改方

案的編制,即是對(duì)隱患整改方案的落實(shí)情況進(jìn)行檢查;對(duì)現(xiàn)場(chǎng)存在重

大隱患的專(zhuān)業(yè)性較強(qiáng)的項(xiàng)目,有權(quán)下達(dá)停工整改決定。

安全總監(jiān)張奇

4、組織做好對(duì)現(xiàn)場(chǎng)人員的安全教育、培訓(xùn)與考核。

5、負(fù)責(zé)在有較大危險(xiǎn)因素的工作和活動(dòng)場(chǎng)所和有關(guān)設(shè)施、設(shè)備上設(shè)

置明顯的安全警示標(biāo)志。

6、依據(jù)有關(guān)法律、法規(guī)和標(biāo)準(zhǔn),做好對(duì)現(xiàn)場(chǎng)易燃易爆和有毒有害危

險(xiǎn)品及危險(xiǎn)廢棄物的管理;做好對(duì)現(xiàn)場(chǎng)安全設(shè)備、防護(hù)器材、急救器

具和勞動(dòng)防護(hù)用品的管理。

7、及時(shí)、如實(shí)地進(jìn)行事故報(bào)告,做好事故現(xiàn)場(chǎng)保護(hù)工作,參與對(duì)事

故的調(diào)查和處理。

蔡彬彬、付冬、

技術(shù)工程師負(fù)責(zé)方案執(zhí)行情況檢查、技術(shù)復(fù)核等

徐皖山

1、負(fù)責(zé)工程質(zhì)量的現(xiàn)場(chǎng)監(jiān)督檢查和質(zhì)量驗(yàn)收。

2、負(fù)責(zé)一般不合格品的處置,發(fā)現(xiàn)嚴(yán)重不合格品及時(shí)報(bào)告技術(shù)負(fù)責(zé)

質(zhì)量總監(jiān)張濤人,并負(fù)責(zé)處置后的質(zhì)量驗(yàn)收與評(píng)定。

3、對(duì)勞務(wù)分包和施工班組提出質(zhì)量獎(jiǎng)罰。

4、質(zhì)量驗(yàn)收文件的記錄與整理。

測(cè)量兼試驗(yàn)工

劉富負(fù)責(zé)定位放線和進(jìn)場(chǎng)材料取樣及送檢及工程相關(guān)試驗(yàn)管理

程師

負(fù)責(zé)審核材料進(jìn)場(chǎng)申請(qǐng),負(fù)責(zé)按照材料進(jìn)場(chǎng)計(jì)劃組織材料進(jìn)場(chǎng),負(fù)責(zé)

物資工程師魏慶猛

材料報(bào)驗(yàn)總協(xié)調(diào)

材料工程師左伯明負(fù)責(zé)按照材料進(jìn)場(chǎng)計(jì)劃組織材料進(jìn)場(chǎng),負(fù)責(zé)材料報(bào)驗(yàn)及協(xié)調(diào)

袁高峰、陳浪、

專(zhuān)業(yè)工程師負(fù)責(zé)組織協(xié)調(diào)現(xiàn)場(chǎng)施工,負(fù)責(zé)施工現(xiàn)場(chǎng)材料堆場(chǎng)管理

王楓

表3.1-2安裝單位負(fù)責(zé)人及職責(zé)分工

職務(wù)姓名工作職責(zé)

塔吊單位項(xiàng)目

張軍負(fù)責(zé)整個(gè)項(xiàng)目實(shí)施,保證工期、質(zhì)量安全處于受控狀態(tài)。

負(fù)責(zé)人

塔吊單位

夏廣洲負(fù)責(zé)技術(shù)方案制定,確保方案的正確性,科學(xué)性和可行性。

技術(shù)負(fù)責(zé)人

塔吊單位安全落實(shí)安全責(zé)任制度,負(fù)責(zé)檢查,監(jiān)督現(xiàn)場(chǎng)人、機(jī)、物安全性、可靠性,制止

邵俊

負(fù)責(zé)人違章作業(yè),消除可能存在的安全隱患。

第5頁(yè)

職務(wù)姓名工作職責(zé)

現(xiàn)場(chǎng)工長(zhǎng)唐懷忠負(fù)責(zé)現(xiàn)場(chǎng)的統(tǒng)一安排和現(xiàn)場(chǎng)指揮。

嚴(yán)守工作紀(jì)律,服從正確安排,正確使用勞保用品,防護(hù)齊全,嚴(yán)守工作崗

安拆工4人

位,嚴(yán)格遵循操作規(guī)程。

負(fù)責(zé)檢查吊具、索具安全性,保證吊點(diǎn)正確,物件平穩(wěn),指揮信號(hào)清晰、明

信號(hào)指揮1人

確。

負(fù)責(zé)檢查電器系統(tǒng)安全性,電器系統(tǒng)的維修維護(hù),以及正確的操作規(guī)范,保

電工1人

證塔機(jī)正確安全使用。

嚴(yán)守操作規(guī)程操作塔吊,檢查塔吊各個(gè)限位保險(xiǎn)部件是否正常,確保塔吊處

塔吊司機(jī)1人

于良好狀態(tài)。

3.2項(xiàng)目管理目標(biāo)

項(xiàng)目管理目標(biāo)名稱(chēng)目標(biāo)值

工期安裝3天,拆除3天

質(zhì)量目標(biāo)一次驗(yàn)收合格率100%

特種作業(yè)人員持證上崗率100%;安全防護(hù)用品正確配備率100%;無(wú)高空墜落事故、

安全文明目標(biāo)

觸電事故、起重設(shè)備坍塌事故及重傷事故的發(fā)生。

綠色施工目標(biāo)推行“五節(jié)一環(huán)?!毕嚓P(guān)內(nèi)容(塔吊吊臂設(shè)置LED節(jié)能燈帶)

科技目標(biāo)/

3.3各項(xiàng)資源供應(yīng)方式

3.3.1勞務(wù)資源安排一覽表

施工項(xiàng)目資質(zhì)開(kāi)始分包商

專(zhuān)業(yè)施工隊(duì)名稱(chēng)建設(shè)工期分包方式責(zé)任人

名稱(chēng)要求施工時(shí)間選擇方式

項(xiàng)目選擇

塔吊安裝二級(jí)2023.08.073專(zhuān)業(yè)分包

公司批準(zhǔn)

夏廣洲

項(xiàng)目選擇

塔吊拆除二級(jí)2023.01.303專(zhuān)業(yè)分包

公司批準(zhǔn)

3.3.2大型機(jī)械設(shè)備采購(gòu)供應(yīng)安排一覽表

機(jī)械設(shè)備名稱(chēng)擬選供應(yīng)商提供方式要求進(jìn)場(chǎng)時(shí)間計(jì)劃出場(chǎng)時(shí)間責(zé)任人

江蘇磊騰機(jī)械工

50t汽車(chē)吊租賃2023.07.282023.02.03袁高峰

程有限公司

3.4施工流水段的劃分及施工工藝流程

施工流水段劃分

本次僅安裝一臺(tái)2#塔吊,無(wú)施工流水段劃分需求。

施工工藝流程

1安裝流程:

安裝塔身節(jié)→吊裝爬升架→安裝回轉(zhuǎn)總成→安裝塔帽總成→安裝平衡臂總成→安裝

平衡臂總成→安裝一塊平衡重→吊裝起重臂總成→吊裝剩余平衡重→起升機(jī)構(gòu)繞繩系統(tǒng)

→接電源及試運(yùn)轉(zhuǎn)。

2拆除流程:

拆卸前檢查→塔機(jī)的配平→塔機(jī)降節(jié)→拆卸平衡臂配重→拆卸起重臂→拆卸平衡臂

→拆卸司機(jī)室→拆卸塔頂→拆卸回轉(zhuǎn)塔身→拆卸回轉(zhuǎn)總成→拆卸爬升架及剩余的標(biāo)準(zhǔn)節(jié)、

基節(jié)。

3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施

第6頁(yè)

序號(hào)重點(diǎn)和難點(diǎn)具體分析應(yīng)對(duì)措施責(zé)任人

混凝土強(qiáng)度必須達(dá)

1塔吊基礎(chǔ)到設(shè)計(jì)強(qiáng)度90%方運(yùn)用同條件試塊,試驗(yàn)報(bào)告合格后方可安裝康宋

可安裝

現(xiàn)場(chǎng)施工位置進(jìn)行隔離,無(wú)關(guān)人員禁止靠近;現(xiàn)場(chǎng)

起重吊裝作業(yè),交

2塔吊節(jié)安裝對(duì)作業(yè)人員嚴(yán)格執(zhí)行持證上崗;塔司、起重指揮人張奇

叉作業(yè)

員及作業(yè)人員作業(yè)前進(jìn)行安全技術(shù)交底

第7頁(yè)

第四章施工進(jìn)度計(jì)劃

本工程塔吊預(yù)計(jì)2023年8月7日開(kāi)始安裝,2023年8月9日安裝完成,拆除工作2023

年1月30日開(kāi)始拆除,2023年2月2日拆除完成。塔吊安裝前,基礎(chǔ)必須經(jīng)各方驗(yàn)收合

格后方可進(jìn)行。

序號(hào)名稱(chēng)開(kāi)始時(shí)間完成時(shí)間工期

12#塔吊安裝2023年8月7日2023年8月9日3日歷天

22#塔吊拆除2023年1月30日2023年2月2日3日歷天

第8頁(yè)

第五章施工準(zhǔn)備與資源配置計(jì)劃

5.1施工準(zhǔn)備計(jì)劃

5.1.1技術(shù)準(zhǔn)備

表5.1.1-1技術(shù)文件準(zhǔn)備計(jì)劃一覽表

序號(hào)文件名稱(chēng)編號(hào)配備數(shù)量保管部門(mén)

1《建設(shè)工程安全生產(chǎn)管理?xiàng)l例》國(guó)務(wù)院令第393號(hào)1技術(shù)部

2《建筑起重機(jī)安全監(jiān)督管理規(guī)定》建設(shè)部令第166號(hào)1技術(shù)部

3《混凝土結(jié)構(gòu)設(shè)計(jì)規(guī)范》GB50010-20101技術(shù)部

4《建筑地基基礎(chǔ)工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn)》GB50202-20181技術(shù)部

5《混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范》GB50204-20151技術(shù)部

6《建筑地基基礎(chǔ)設(shè)計(jì)規(guī)范》GB50007-20111技術(shù)部

7《建

溫馨提示

  • 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
  • 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶(hù)所有。
  • 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
  • 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
  • 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶(hù)上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶(hù)上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
  • 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
  • 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶(hù)因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。

最新文檔

評(píng)論

0/150

提交評(píng)論