濟寧至曲阜快速路(兼一級公路)工程
預(yù)制構(gòu)件吊裝安全專項施工方案
編制單位:中國建筑第八工程局有限公司
編制人:
日期:
中國建筑第八工程局
濟寧至曲阜快速路(兼一級公路)工程項目部
2023年08月
目錄
一編制依據(jù)...............................................................................................................................1
二工程概況...............................................................................................................................2
2.1工程建設(shè)概況................................................................................................................2
2.2設(shè)計概況........................................................................................................................2
2.3工程施工條件................................................................................................................4
2.4風(fēng)險源辨識與分級......................................................................................................7
三施工計劃...............................................................................................................................9
3.1施工安排與部署.............................................................................................................9
3.1.1項目管理目標(biāo).....................................................................................................9
3.1.2各項資源供應(yīng)方式.............................................................................................9
3.1.3施工流水段的劃分及施工工藝流程...............................................................10
3.1.4工程施工重點和難點分析及應(yīng)對措施...........................................................12
3.1.5新技術(shù)應(yīng)用要求...............................................................................................13
3.1.6關(guān)鍵及特殊過程控制........................................................................................14
3.2施工進度計劃............................................................................................................14
3.3施工準(zhǔn)備與資源配置計劃........................................................................................18
3.3.1施工準(zhǔn)備計劃...................................................................................................18
3.3.2資源配置計劃...................................................................................................21
四施工方法及工藝要求.........................................................................................................24
4.1墩柱施工方法及工藝要求..........................................................................................24
4.1.1施工準(zhǔn)備...........................................................................................................24
4.1.2立柱運輸...........................................................................................................27
4.1.3墩頂、底部鑿毛...............................................................................................29
4.1.4承臺面清理.......................................................................................................30
4.1.5立柱卸車、翻轉(zhuǎn)...............................................................................................30
4.1.6墩柱預(yù)拼裝.......................................................................................................31
4.1.7墩柱坐漿作業(yè)...................................................................................................31
4.1.8立柱就位與校正...............................................................................................32
4.1.9套筒灌漿連接...................................................................................................35
4.2蓋梁施工方法及工藝要求........................................................................................36
4.2.1技術(shù)參數(shù)...........................................................................................................36
4.2.2施工工藝流程...................................................................................................37
4.2.3施工準(zhǔn)備...........................................................................................................38
4.2.4蓋梁運輸...........................................................................................................41
4.2.5臨時支墩搭設(shè)...................................................................................................43
4.2.6砂筒的安裝.......................................................................................................45
4.2.7蓋梁試吊...........................................................................................................46
4.2.8蓋梁試吊拼裝的測量監(jiān)控與調(diào)整...................................................................46
4.2.9擋漿模板的安裝...............................................................................................48
4.2.10拌漿與立柱頂面坐漿.....................................................................................49
4.2.11蓋梁的正式拼裝與調(diào)整.................................................................................49
4.2.12蓋梁連接波紋管壓漿.....................................................................................49
4.2.13后澆帶施工.....................................................................................................50
4.2.14波紋管的連接與預(yù)應(yīng)力筋穿束.....................................................................50
4.2.15后澆帶鋼筋的加工與安裝.............................................................................51
4.2.16側(cè)模安裝.........................................................................................................54
4.2.17混凝土澆筑.....................................................................................................55
4.2.18混凝土養(yǎng)護.....................................................................................................56
4.2.19預(yù)應(yīng)力的張拉.................................................................................................56
4.2.20孔道壓漿、封錨.............................................................................................60
4.2.21臨時支墩及底模拆除.....................................................................................61
4.3履帶吊安拆施工方法和工藝要求..............................................................................62
施工工藝流程...........................................................................................................62
4.3.2安裝...................................................................................................................63
4.3.3拆卸...................................................................................................................74
4.3.4施工要點...........................................................................................................76
五施工保證措施.....................................................................................................................81
5.1安全保障措施..............................................................................................................81
5.1.1組織保障措施...................................................................................................81
5.1.2安全技術(shù)措施...................................................................................................82
5.1.3施工保證措施...................................................................................................85
5.1.4監(jiān)測點布置.......................................................................................................91
5.2起重鋼絲繩的檢查驗收管理....................................................................................91
5.2.1鋼絲繩使用前的檢查.......................................................................................91
5.2.2鋼絲繩的日常檢查...........................................................................................92
5.2.3鋼絲繩的報廢標(biāo)準(zhǔn)...........................................................................................92
5.3特種設(shè)備的安全管理..................................................................................................93
5.3.1特種設(shè)備驗收小組及其職責(zé)...........................................................................93
5.3.2特種設(shè)備的進場條件.......................................................................................93
5.3.3特種設(shè)備的檢查與驗收...................................................................................93
5.3.4特種設(shè)備的操作人員.......................................................................................93
5.3.5特種設(shè)備日常檢查...........................................................................................93
5.4質(zhì)量保證措施..............................................................................................................94
5.4.1質(zhì)量保證體系...................................................................................................94
5.4.2檢測、試驗保證措施.......................................................................................99
5.4.3關(guān)鍵過程質(zhì)量保證措施.................................................................................100
5.5成品保護保證措施....................................................................................................101
5.5.1一般保護措施.................................................................................................101
5.5.2主要分項成品和設(shè)備保護措施.....................................................................101
六施工管理及作業(yè)人員配備和分工...................................................................................103
6.1管理人員配置..........................................................................................................103
6.1.1項目管理人員組織機構(gòu)...............................................................................103
6.1.2項目管理人員配置.......................................................................................103
6.2安全生產(chǎn)領(lǐng)導(dǎo)小組..................................................................................................111
6.3特種作業(yè)人員..........................................................................................................111
6.4其他作業(yè)人員..........................................................................................................112
七驗收標(biāo)準(zhǔn)...........................................................................................................................112
7.1驗收標(biāo)準(zhǔn)....................................................................................................................112
7.2驗收程序....................................................................................................................113
7.3驗收內(nèi)容....................................................................................................................114
7.3.1機械驗收.........................................................................................................114
7.3.2起重鋼絲繩驗收.............................................................................................115
7.3.3臨時支架驗收.................................................................................................117
7.3.4安全專項驗收.................................................................................................120
7.3.5地基承載力驗收.............................................................................................122
7.4驗收人員....................................................................................................................122
7.4.1六標(biāo)驗收人員.................................................................................................122
7.4.2七標(biāo)驗收人員.................................................................................................122
八應(yīng)急處置措施...................................................................................................................123
8.1應(yīng)急預(yù)案的方針與原則............................................................................................123
8.2危險目標(biāo)的確定........................................................................................................124
8.3應(yīng)急救援小組機構(gòu)與職責(zé)........................................................................................124
8.4吊裝時的應(yīng)急準(zhǔn)備....................................................................................................125
8.5施工現(xiàn)場的急救步驟................................................................................................126
8.6應(yīng)急處理措施............................................................................................................128
8.7事故的處理與報告....................................................................................................129
九計算書和相關(guān)圖紙...........................................................................................................131
9.1墩柱吊裝計算書........................................................................................................131
9.1.1履帶吊選型計算.............................................................................................131
9.1.2汽車吊選型計算.............................................................................................132
9.1.3鋼絲繩及卡環(huán)計算.........................................................................................134
9.1.4履帶吊抗傾覆驗算.........................................................................................135
9.1.5汽車吊抗傾覆驗算.........................................................................................137
9.1.6地基承載力驗算.............................................................................................138
9.1.7立柱抗風(fēng)能力驗算.........................................................................................138
9.2蓋梁吊裝計算書........................................................................................................139
9.2.1A型蓋梁吊裝計算..........................................................................................139
9.2.2N型蓋梁起重機選擇計算..............................................................................144
9.2.3履帶吊抗傾覆驗算.........................................................................................148
9.2.4地基承載力驗算.............................................................................................152
9.3臨時支撐計算書......................................................................................................152
9.3.1鋼管柱支架受力計算.....................................................................................152
9.3.2立柱基礎(chǔ)計算.................................................................................................159
9.3.3蓋梁現(xiàn)澆段支撐(盤扣式)計算書.............................................................168
一編制依據(jù)
序號類別文件名稱編號
中華人民共和國住房和城
1《危險性較大的分部分項工程安全管理規(guī)定》
鄉(xiāng)建設(shè)部令第37號
國家行政文件
住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于實施《危險性較大的分
2建辦質(zhì)[2018]31號
部分項工程安全管理規(guī)定》有關(guān)問題的通知
《山東省房屋市政施工危險性較大分部分項工程
3地方行政文件魯建質(zhì)安字[2018]15號
安全管理實施細則》
4《起重機設(shè)計規(guī)范》GB/T3811-2008
5《起重機手勢信號》GB/T5082-2023
6《起重機鋼絲繩保養(yǎng)、維護、檢驗和報廢》GB/T5972-2016
7《建筑施工場界環(huán)境噪聲排放標(biāo)準(zhǔn)》GB12523-2011
8《預(yù)應(yīng)力混凝土用鋼絞線》GB/T5224-2014
9《建筑施工承插型盤扣式鋼管支架安全技術(shù)規(guī)程》DB32/T4073-2023
10《建筑結(jié)構(gòu)荷載規(guī)范》GB50009-2012
11《城市橋梁工程施工與質(zhì)量驗收規(guī)范》CJJ2-2008
12《城市道路工程設(shè)計規(guī)范》CJJ37-2012
13《公路橋涵施工技術(shù)規(guī)范》JTG/T3650-2023
14國家行業(yè)規(guī)范《公路工程質(zhì)量檢驗評定標(biāo)準(zhǔn)第一冊土建工程》JTGF80/1-2017
15《公路工程施工安全技術(shù)規(guī)范》JTGF90-2015
16《公路鋼筋混凝土及預(yù)應(yīng)力混凝土橋涵設(shè)計規(guī)范》JTG3362-2018
17《鋼筋焊接及驗收規(guī)程》JGJ18-2012
18《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011
19《建設(shè)工程施工現(xiàn)場環(huán)境與衛(wèi)生標(biāo)準(zhǔn)》JGJ146-2013
20《鋼筋機械連接用套筒》JG/T163-2013
21《鋼筋機械連接技術(shù)規(guī)程》JGJ107-2016
22《履帶式起重機》CAS130-2006
23《高空作業(yè)車安全技術(shù)要求》CB4286-2013
24《粗直徑鋼絲繩》GB/T20067-2017
1
25《建筑機械使用安全技術(shù)規(guī)程》JGJ33-2012
26《鋼結(jié)構(gòu)設(shè)計標(biāo)準(zhǔn)》JGJ/T483-2023
27《建筑結(jié)構(gòu)可靠性設(shè)計統(tǒng)一標(biāo)準(zhǔn)》GB50068-2018
28《預(yù)制拼裝橋墩技術(shù)規(guī)程》DG/TJ08-2160-2015
29《公路工程裝配式施工質(zhì)量驗收評定標(biāo)準(zhǔn)》DG/TJ08-2250-2017
《裝配整體式混凝土結(jié)構(gòu)工程預(yù)制構(gòu)件制作與驗
30DB37/T5020-2014
收規(guī)程》
地方規(guī)范標(biāo)準(zhǔn)
31《裝配式混凝土結(jié)構(gòu)工程施工與質(zhì)量驗收標(biāo)準(zhǔn)》DB37/T5019-2023
32《安全生產(chǎn)風(fēng)險分級管控體系通則》DB37/T2882-2016
33《生產(chǎn)安全事故隱患排查治理體系通則》DB37/T2883-2016
34合同工程施工承包合同以及相關(guān)協(xié)議
35濟寧至曲阜快速路(兼一級公路)工程設(shè)計圖紙
設(shè)計文件
36圖紙會審文件
濟寧至曲阜快速路(兼一級公路)工程施工組織設(shè)
37其他
計
二工程概況
2.1工程建設(shè)概況
表2.1-1工程建設(shè)概況一覽表
濟寧至曲阜快速路(兼
工程名稱工程地址山東省濟寧市兗州區(qū)
一級公路)工程
濟寧公用濟曲發(fā)展建設(shè)
建設(shè)單位合同額88567.58萬元
有限公司
上海市政工程設(shè)計研究
設(shè)計單位總里程/km3.67
總院(集團)有限公司
山東明嘉勘察測繪有限工程交工驗收的質(zhì)量評定:合格;
勘察單位質(zhì)量
公司竣工驗收的質(zhì)量評定:優(yōu)良。
山東省圣地公路工程監(jiān)
監(jiān)理單位理咨詢中心、北京雙圓合同工期360日歷天
工程咨詢監(jiān)理有限公司
中國建筑第八工程局有
總承包單位安全符合國家安全生產(chǎn)管理相關(guān)規(guī)定
限公司
主要功能或
城市快速路兼一級公路
用途
2.2設(shè)計概況
標(biāo)準(zhǔn)橋墩尺寸為1.8x1.4m(主線),橋墩尺寸采用0.2m分檔設(shè)置。單段吊裝長度
2
控制在11m以內(nèi)且重量控制在200t以內(nèi)。
表2.2-1六標(biāo)預(yù)制墩柱設(shè)計概況一覽表
類型截面尺寸(m)數(shù)量(根/m)柱長范圍(m)柱重范圍(t)備注
LZ1Y1.8×1.4628.8-11
表2.2-2七標(biāo)預(yù)制墩柱設(shè)計概況一覽表
類型截面尺寸(m)數(shù)量(根/m)柱長范圍(m)柱重范圍(t)備注
LZ1Y1.8×1.470
圖2.2-1預(yù)制墩柱面圖
本項目A蓋梁采用預(yù)制裝配式施工,A型蓋梁整榀長25.38米,寬3.1m,蓋梁
中心線處高3.5m,蓋梁頂面從中心線到兩端設(shè)置2%橫坡,兩端處高2.9m,倒T型結(jié)構(gòu)
寬度1.2m。施工時分為兩節(jié)段安裝,節(jié)段采用后澆帶連接,后澆帶長2m,單節(jié)段長度
11.69m,重186.8t。
預(yù)制蓋梁與墩柱連接采用JBG-80Z不銹鋼波紋管與墩柱預(yù)留鋼筋連接,墩柱類
型為LZ1Y型墩柱,墩柱高度8.4m-11m。
按照《公路工程施工安全規(guī)范》(JTGF90-2015)附錄A危險性較大的工程要求:
采用非常規(guī)起重設(shè)備、方法,且單件起吊重量在100kN及以上的起重吊裝工程
本項目預(yù)制預(yù)制蓋梁安裝工程最大起吊重量為186t,判別為需專家論證、審查
的危險性較大的工程。
表2.2-3預(yù)制蓋梁設(shè)計概況一覽表
3
類型數(shù)量(榀)尺寸(m)單片重量(t)備注
A型蓋梁7025.38×3.1×3.5~2.9186.8
圖2.2-2A型蓋梁立面圖
圖2.2-3A型蓋梁頂面圖
圖2.2-4A型蓋梁底面圖
2.3工程施工條件
1)運輸路線
路線1:沿預(yù)制場施工便道向東行至西浦路右轉(zhuǎn),沿西浦路向南行駛進入融通大道再
進入世紀(jì)大道,進入南環(huán)城路到達項目起點,總計7.2km。
路線2:沿預(yù)制場施工便道東行橫穿西浦路進入勝利西路,沿勝利西路行駛至荊州南
路右轉(zhuǎn),沿荊州南路向南行駛至南環(huán)城路到達二工區(qū)K43+900處,總計6.5km。
沿線車流量較小,路況較好,運輸通道下穿魯南高鐵、日蘭高速、新石鐵路,通過
府河橋,項目部提前與運輸通道相關(guān)管理部門聯(lián)系,征得管理單位同意。對需要處理的
道路及橋梁進行加固,滿足通行條件后再進行構(gòu)件運輸。
由預(yù)制場便道向東到勝利西路現(xiàn)狀道路為鄉(xiāng)村土路,長度930米,寬度6m,車輛通
4
行顛簸嚴(yán)重,無法滿足蓋梁運輸車輛通行要求,將原狀土路面進行整平壓實,上鋪20cm
泥結(jié)碎石進行處理。
圖2.3-1預(yù)制蓋梁運輸路線圖
圖2.3-2勝利西路-荊州南路路口現(xiàn)狀圖
5
圖2.3-2荊州南路-南環(huán)城路路口現(xiàn)狀圖
2)管線情況
施工現(xiàn)場影響吊裝施工的管線基本遷改完成,剩余一處110kV安銀、科化線位于
JQ069橋墩上方,自道路北側(cè)K44+040處斜穿至道路南側(cè)K44+060處。高壓線至原地表
15m,至墩柱頂凈距9.3m,安全距離無法保證,此處預(yù)制蓋梁吊裝施工待高壓線遷改完
成后施工。
6
圖2.3-4110kV安銀、科化線現(xiàn)狀照片
圖2.3-5110kV安銀、科化線與JQ069相對位置關(guān)系
3)現(xiàn)場臨時交通
施工現(xiàn)場既有道路為現(xiàn)狀環(huán)城西路,承臺兩側(cè)目前保留8.75m寬原狀道路作為施工
便道,無法滿足吊裝機械行走需求。預(yù)制蓋梁施工前需將施工便道拓展至兩側(cè)機非分隔
帶處。
2.4風(fēng)險源辨識與分級
序號危險源事故類型控制措施責(zé)任人
7
現(xiàn)場人員較多,在起重運行中對人現(xiàn)場除必要人員外嚴(yán)禁其他人員靠黃良濤、
1起重傷害
體造成的擠壓或撞擊。近吊裝范圍康千
駕駛員在吊運過程中控制好產(chǎn)品擺
在吊運落料時因產(chǎn)品擺動幅度較黃良濤、
2起重傷害動幅度落料時作業(yè)人員要給自己預(yù)
大,對落料人員造成的擠壓或撞擊康千
留相應(yīng)閃避空間
在吊運落料時速度過快,貨物對落嚴(yán)格控制起吊高度和落料速度,落料黃良濤、
3起重傷害
料人員造成的擠壓或撞擊時貨物在接近地面時方可靠近貨物??登?/p>
起重機吊鉤超載斷裂、吊運時吊
起重傷害黃良濤、
4索具從吊鉤中滑出,吊運貨物墜落嚴(yán)禁超限作業(yè)
爆炸康千
傷人或爆炸
吊運中吊索具因磨損或使用應(yīng)報
廢的鋼絲繩、使用的吊具吊運超過起重傷害吊具安裝人員每次檢查吊具,確保合黃良濤、
5
額定起重量的重物等不合格斷裂,爆炸格后方可進行作業(yè)康千
重物墜落傷人或爆炸
汽車起重機作業(yè)場所地面不平整、
現(xiàn)場指揮人員在作業(yè)前進行檢查,確黃良濤、
6支撐不穩(wěn)定、配重不平衡、重物超起重傷害
保無異常后方可作業(yè)康千
過額定起重量而造成起重機傾覆。
風(fēng)力過大、違章作業(yè)造成起重機傾現(xiàn)場指揮人員執(zhí)行起重作業(yè)“十不吊”黃良濤、
7起重傷害
覆。規(guī)定。康千
機械傳動部分未加防護,造成機械
傷害;違章在卷揚機鋼絲繩上面通現(xiàn)場指揮人員在作業(yè)前進行檢查,確黃良濤、
8起重傷害
過,運動中的鋼絲繩將人擠傷或絆保無異常后方可作業(yè)康千
倒。
吊裝貨物違章載人,人站立或坐黃良濤、
9起重傷害嚴(yán)禁人員站在、攀爬吊裝貨物或吊鉤
在吊鉤上??登?/p>
黃良濤、
10人站在起重臂下等危險區(qū)域。起重傷害嚴(yán)禁人員站立或行進在吊裝區(qū)域
康千
電氣設(shè)備漏電、保護裝置失效、裸
現(xiàn)場指揮人員在作業(yè)前進行檢查,確黃良濤、
11導(dǎo)線未加屏蔽、吊裝區(qū)域有架空電起重傷害
保無異常后方可作業(yè)康千
源線等造成觸電。
吊運時無人指揮、作業(yè)區(qū)內(nèi)有人逗
吊裝前確定現(xiàn)場負(fù)責(zé)人,指揮、調(diào)度黃良濤、
12留、運行中的起重機的吊具及重物起重傷害
作業(yè)現(xiàn)場康千
擺動撞擊行人。
現(xiàn)場指揮人員在作業(yè)前進行檢查,確黃良濤、
13司機室玻璃未擦凈,造成視野不清。起重傷害
保無異常后方可作業(yè)康千
司機與指揮人員聯(lián)絡(luò)不暢,或誤作業(yè)前現(xiàn)場指揮人員與司機明確指黃良濤、
14起重傷害
解吊運信號。揮手勢等信號康千
吊掛方式不正確,重物從吊鉤中起重傷害每次起吊前進行確認(rèn),無異常后方可黃良濤、
15
脫出,重物墜落傷人或爆炸爆炸起吊康千
鋼絲繩從滑輪中跳出輪槽,重物墜起重傷害現(xiàn)場指揮人員和駕駛員在作業(yè)前進黃良濤、
16
落傷人或爆炸。爆炸行檢查,確保無異常后方可作業(yè)康千
制動器出現(xiàn)裂紋、摩擦墊片磨損過
起重傷害現(xiàn)場指揮人員和駕駛員在作業(yè)前進黃良濤、
17多,造成滑車,重物墜落傷人或爆
爆炸行檢查,確保無異常后方可作業(yè)康千
炸。
8
三施工計劃
3.1施工安排與部署
3.1.1項目管理目標(biāo)
表3.1.1-1項目管理目標(biāo)
項目管理目標(biāo)目標(biāo)值
預(yù)制墩柱計劃2023年9月6日-2023年10月30日
工期
預(yù)制蓋梁2023年9月10日-2023年11月29日
工程交工的質(zhì)量評定:合格
質(zhì)量管理目標(biāo)
工程竣工的質(zhì)量評定:優(yōu)良
安全管理目標(biāo)符合國家安全生產(chǎn)管理相關(guān)規(guī)定。杜絕死亡與重傷事故、機械事故、火災(zāi)事故。
揚塵治理目標(biāo)嚴(yán)格執(zhí)行濟寧市建筑工地?fù)P塵治理的有關(guān)規(guī)定,做到8個100%。
綠色施工目標(biāo)中建八局綠色施工達標(biāo)工程。
完成實用新型專利:5項;發(fā)明專利:4項;工法:2項;QC成果:2項;論文:
5篇。
科技管理目標(biāo)
新技術(shù)應(yīng)用:采用建筑業(yè)十項新技術(shù)中5大項18小項,局級新技術(shù)3大項4小
項,中建八局基礎(chǔ)設(shè)施新技術(shù)中4大項7小項;省級BIM應(yīng)用成果:1項。
3.1.2各項資源供應(yīng)方
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2024年版餐廳股權(quán)轉(zhuǎn)讓協(xié)議書
- 2025年度綠色環(huán)保水電安裝項目合同書3篇
- 2025年度汽車吊機租賃及吊裝作業(yè)現(xiàn)場應(yīng)急預(yù)案合同3篇
- 2024年股權(quán)轉(zhuǎn)讓之擔(dān)保協(xié)議要覽
- 2025年度消防工程應(yīng)急物資儲備與供應(yīng)合同3篇
- 2025年度水暖設(shè)備研發(fā)、生產(chǎn)、銷售與售后一體化承包合同3篇
- 二零二五年度光伏發(fā)電站建設(shè)項目合同3篇
- 2025年度虛擬偶像創(chuàng)作軟件銷售合同范本2篇
- 地面施工冬季施工方案(7篇)
- 春節(jié)放假的通知匯編9篇資料
- GB/T 5130-1997電氣用熱固性樹脂工業(yè)硬質(zhì)層壓板試驗方法
- FZ/T 01041-2014絨毛織物絨毛長度和絨毛高度的測定
- 《經(jīng)濟學(xué)導(dǎo)論》考試復(fù)習(xí)題庫(含答案)
- 農(nóng)田水利渠道灌溉與排水課件
- 精品解析浙教版科學(xué) 九年級上冊 3.43 簡單機械之機械效率 同步練習(xí)
- 六棱塊護坡施工方案
- 機械制圖課件(完整版)
- 夸美紐斯-大教學(xué)論-文本細讀
- 《行政組織學(xué)小抄》word版
- 日立多聯(lián)機系統(tǒng)調(diào)試培訓(xùn)教材
- (完整版)環(huán)境科學(xué)與工程-專業(yè)英語詞匯必備(免費)
評論
0/150
提交評論