項(xiàng)目專項(xiàng)施工方案
高速公路濟(jì)南至泰安段改擴(kuò)建工程
石質(zhì)路塹爆破施工方案
編制:
審核:
審批:
日期:
項(xiàng)目專項(xiàng)施工方案
目錄
第一章編制依據(jù).............................................................................................................1
第二章工程概況.............................................................................................................1
2.1工程建設(shè)概況一覽表...............................................................................................1
2.2設(shè)計(jì)概況...................................................................................................................2
2.2.1路基斷面型式.................................................................................................3
2.3工程施工條件...........................................................................................................3
2.3.1沿線地質(zhì)、地層情況描述..............................................................................4
2.3.2水文地質(zhì).........................................................................................................5
2.3.3地震.................................................................................................................6
2.3.4工程施工環(huán)境.................................................................................................6
第三章施工安排...........................................................................................................12
3.1項(xiàng)目管理組織.........................................................................................................12
3.2項(xiàng)目管理目標(biāo).........................................................................................................15
3.3各項(xiàng)資源供應(yīng)方式.................................................................................................15
3.4施工流水段的劃分及施工工藝流程......................................................................16
3.4.1施工流水段的劃分.......................................................................................16
3.4.2施工工藝流程...............................................................................................16
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施..................................................................18
3.6新技術(shù)應(yīng)用要求.....................................................................................................18
3.7成立爆破指揮部.....................................................................................................19
第四章施工進(jìn)度計(jì)劃...................................................................................................20
第五章施工準(zhǔn)備與資源配置計(jì)劃.................................................................................21
5.1施工準(zhǔn)備計(jì)劃.........................................................................................................21
5.1.1技術(shù)準(zhǔn)備.......................................................................................................21
5.1.2現(xiàn)場準(zhǔn)備.......................................................................................................22
5.2資源配置計(jì)劃.........................................................................................................22
第六章施工方法及工藝要求........................................................................................25
6.1方案及技術(shù)參數(shù).....................................................................................................25
6.2施工工藝流程.........................................................................................................25
I
項(xiàng)目專項(xiàng)施工方案
6.3施工要點(diǎn).................................................................................................................26
6.4爆破參數(shù)設(shè)計(jì).........................................................................................................28
6.5起爆網(wǎng)路設(shè)計(jì).........................................................................................................34
6.6爆破安全設(shè)計(jì)和安全防護(hù)......................................................................................36
6.6.1爆破安全設(shè)計(jì)...............................................................................................36
6.6.2一般安全技術(shù)及防護(hù)要求............................................................................43
6.7爆破防護(hù)措施.........................................................................................................44
6.8爆破監(jiān)測與驗(yàn)收.....................................................................................................45
6.8.1爆破監(jiān)測.......................................................................................................45
6.8.2爆破驗(yàn)收.......................................................................................................47
6.9驗(yàn)收程序.................................................................................................................48
6.10驗(yàn)收人員...............................................................................................................48
第七章爆破施工危險(xiǎn)因素分析及應(yīng)對(duì)措施..................................................................48
7.1重大危險(xiǎn)源的識(shí)別.................................................................................................48
7.2對(duì)重大危險(xiǎn)源的評(píng)價(jià).............................................................................................48
7.3危險(xiǎn)源的具體預(yù)防措施..........................................................................................49
7.3.1機(jī)械傷害預(yù)防措施.......................................................................................49
7.4爆破作業(yè)安全技術(shù)保證措施..................................................................................49
7.4.1控制爆破施工安全防護(hù)措施........................................................................49
7.4.2爆破振動(dòng)及控制措施....................................................................................50
7.4.3爆破飛散物的飛散距離校核及控制措施....................................................51
7.4.4爆破沖擊波及預(yù)防措施................................................................................52
7.4.5爆破器材運(yùn)輸安全措施................................................................................53
7.4.6爆破器材臨時(shí)存放安全防護(hù)措施................................................................53
7.4.7爆破器材領(lǐng)用、發(fā)放、清退安全措施........................................................54
7.4.8盲炮的處理措施...........................................................................................54
7.4.9爆破作業(yè)防護(hù)措施.......................................................................................54
7.4.10爆破試驗(yàn)安全措施.....................................................................................55
7.4.11施工安全措施.............................................................................................56
7.4.12有毒氣體控制.............................................................................................56
II
項(xiàng)目專項(xiàng)施工方案
7.4.13粉塵控制.....................................................................................................57
7.4.14噪音控制.....................................................................................................57
7.4.15爆破器材檢測.............................................................................................57
7.4.16振動(dòng)觀測與控制.........................................................................................57
7.4.17爆破器材的現(xiàn)場管理..................................................................................58
7.4.18民爆物品的管理.........................................................................................58
7.4.19觸電傷害預(yù)防措施.....................................................................................59
7.4.20高空墜落傷害預(yù)防措施..............................................................................59
7.4.21坍塌與滑坡預(yù)防措施..................................................................................60
第八章安全警戒...........................................................................................................61
8.1爆破警戒宣傳.........................................................................................................61
8.2爆破安全警戒措施.................................................................................................62
8.3裝藥時(shí)的警戒.........................................................................................................62
8.4爆破時(shí)警戒點(diǎn).........................................................................................................62
8.5爆破時(shí)的警戒.........................................................................................................63
8.6爆破時(shí)警戒信號(hào).....................................................................................................63
8.7警戒清場.................................................................................................................64
8.8起爆.........................................................................................................................64
8.9爆后檢查.................................................................................................................64
第九章爆破作業(yè)審批流程............................................................................................64
9.1爆破方案的審批.....................................................................................................64
9.2爆炸物品的審批及使用..........................................................................................65
9.3爆破記錄.................................................................................................................65
第十章各項(xiàng)管理計(jì)劃...................................................................................................66
10.1綠色施工管理計(jì)劃...............................................................................................66
10.1.1項(xiàng)目綠色施工考核指標(biāo)..............................................................................66
10.1.2綠色施工技術(shù)措施.....................................................................................67
10.2進(jìn)度管理計(jì)劃.......................................................................................................69
10.2.1工期保證體系.............................................................................................69
10.2.2施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工..........................................................71
III
項(xiàng)目專項(xiàng)施工方案
10.2.3工期保證措施.............................................................................................71
10.3質(zhì)量管理計(jì)劃.......................................................................................................72
10.3.1工程施工質(zhì)量目標(biāo).....................................................................................72
10.3.2項(xiàng)目質(zhì)量管理組織機(jī)構(gòu)和職責(zé)分工..........................................................72
10.3.3項(xiàng)目施工質(zhì)量控制點(diǎn)..................................................................................75
10.3.4現(xiàn)場質(zhì)量管理制度.....................................................................................75
10.3.5質(zhì)量保證措施.............................................................................................78
10.4安全管理計(jì)劃.......................................................................................................79
10.4.1職業(yè)健康安全管理目標(biāo)..............................................................................79
10.4.2現(xiàn)場職業(yè)健康安全管理組織機(jī)構(gòu)和職責(zé)分工..........................................79
10.4.3職業(yè)健康安全重大危險(xiǎn)源..........................................................................81
10.4.4職業(yè)健康安全資源配置計(jì)劃......................................................................82
10.4.5施工現(xiàn)場安全生產(chǎn)管理制度......................................................................82
10.4.6職業(yè)健康安全保證措施..............................................................................83
10.5成品保護(hù)計(jì)劃.......................................................................................................86
10.5.1成立成品保護(hù)管理機(jī)構(gòu)..............................................................................87
10.5.2一般規(guī)定.....................................................................................................87
10.5.3具體保護(hù)措施.............................................................................................87
第十一章應(yīng)急預(yù)案.......................................................................................................87
11.1應(yīng)急指揮機(jī)構(gòu)及職責(zé)...........................................................................................87
11.2事故風(fēng)險(xiǎn)分析.......................................................................................................90
11.3應(yīng)急救援程序.......................................................................................................91
11.4應(yīng)急處置措施.......................................................................................................93
11.5應(yīng)急物資準(zhǔn)備.......................................................................................................94
11.6應(yīng)急響應(yīng)、響應(yīng)結(jié)束、演練................................................................................95
第十二章新型冠狀病毒肺炎疫情防控預(yù)案..................................................................97
12.1風(fēng)險(xiǎn)分析...............................................................................................................97
12.2防護(hù)及救援組織機(jī)構(gòu)及職責(zé)................................................................................97
12.3預(yù)防疫情防控措施...............................................................................................99
12.4監(jiān)測與預(yù)警.........................................................................................................100
IV
項(xiàng)目專項(xiàng)施工方案
12.5救援響應(yīng).............................................................................................................101
12.6后期處置.............................................................................................................103
12.7救援保障.............................................................................................................103
V
項(xiàng)目專項(xiàng)施工方案
第一章編制依據(jù)
表1編制依據(jù)
序
類別文件名稱編號(hào)
號(hào)
中華人民共和國主席令
1中華人民共和國安全生產(chǎn)法
第八十八號(hào)
中華人民共和國主席令
2中華人民共和國環(huán)境保護(hù)法
第九號(hào)
中華人民共和國國務(wù)院
3建設(shè)工程質(zhì)量管理?xiàng)l例
令(第714號(hào))
第十三屆中華人民共和
4國家行政文中華人民共和國環(huán)境噪聲污染防治法
件國主席令第二十四號(hào)
5民用爆炸物品安全管理?xiàng)l例國務(wù)院令466號(hào)
6建設(shè)工程安全生產(chǎn)管理?xiàng)l例國務(wù)院令第393號(hào)
住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于實(shí)施《危險(xiǎn)性較大的
7建辦質(zhì)〔2018〕31號(hào)
分部分項(xiàng)工程安全管理規(guī)定》有關(guān)問題的通知
住房和城鄉(xiāng)建設(shè)部令第
8危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)定
37號(hào)
9爆破安全規(guī)程GB6722-2014
10爆破作業(yè)單位資質(zhì)條件和管理要求GA990-2012
11國家行業(yè)規(guī)爆破作業(yè)項(xiàng)目管理要求GA991-2012
范
《施工現(xiàn)場臨時(shí)用電安全技術(shù)規(guī)范(附條文說
JGJ46-2005
明)》
12土方與爆破工程施工及驗(yàn)收規(guī)范GB50201-2012
13合同xx高速公路濟(jì)南至泰安段改擴(kuò)建工程施工總承包合同
設(shè)計(jì)xx高速濟(jì)南至泰安段改擴(kuò)建工程項(xiàng)目兩階段施工
14第三冊(cè)
文件圖設(shè)計(jì)
15招投標(biāo)文件xx高速濟(jì)南至泰安段改擴(kuò)建工程項(xiàng)目主體工程施工招標(biāo)文件
16其他xx高速公路濟(jì)南至泰安段改擴(kuò)建工程實(shí)施性施工組織設(shè)計(jì)
第二章工程概況
2.1工程建設(shè)概況一覽表
表2.1工程建設(shè)概況一覽
工程名稱工程性質(zhì)公路
建設(shè)規(guī)模特大型(1級(jí))工程地址
1
項(xiàng)目專項(xiàng)施工方案
施工里程53.262km工程造價(jià)36.73億元
建設(shè)單位
設(shè)計(jì)單位
勘察單位
監(jiān)理單位
施工單位
標(biāo)段工程交工驗(yàn)收的質(zhì)量評(píng)定:合格;
質(zhì)量
竣工驗(yàn)收的質(zhì)量評(píng)定:優(yōu)良。
合同要求工期計(jì)劃工期:36個(gè)月,爭取30個(gè)月。
安全項(xiàng)目實(shí)施中無安全事故。
科技/
工程主要功能
交通公路
或用途
項(xiàng)目承包范圍高速公路改擴(kuò)建工程
2.2設(shè)計(jì)概況
xx高速濟(jì)南至泰安段起于與濟(jì)廣高速交叉的殷家林樞紐立交,起點(diǎn)樁號(hào)K415+160,
路線向西南與長清區(qū)大學(xué)路交叉并設(shè)置固山互通立交,經(jīng)固云湖街道后轉(zhuǎn)向東南,經(jīng)鳳
凰莊村、小西莊村、下龍華村、小河西村后路線轉(zhuǎn)向南延伸,經(jīng)饅頭山西、吳家莊,之
后在萬德鎮(zhèn)小石都莊北側(cè)下穿在建濟(jì)南繞城高速二環(huán)線,設(shè)置張夏樞紐立交,之后在萬
德鎮(zhèn)北側(cè)設(shè)置萬德互通立交連接G104,路線轉(zhuǎn)向東南,于長城村穿越齊長城遺址,經(jīng)
葉家洼村、界首村后進(jìn)入泰安境內(nèi),之后上跨縣道XO14并設(shè)置泰山西互通立交與石臘
河西街及XO14相接,路線繼續(xù)向南,跨過G104、泰肥鐵路后與S243(泰山大街)交叉
并設(shè)置泰安西互通立交,路線繼續(xù)向南,到達(dá)泰山樞紐立交,與青蘭高速相接,終點(diǎn)樁
號(hào)為K468+421.635,全長53.264公里。本項(xiàng)目自北向南依次經(jīng)過濟(jì)南市市中區(qū)和長清
區(qū)、泰安市岱岳區(qū)。
表2.1主要技術(shù)指標(biāo)
序號(hào)技術(shù)指標(biāo)名稱單位設(shè)計(jì)值(老路)
1公路等級(jí)/高速高速
2設(shè)計(jì)速度km/h120120
3路基寬度m4235.5
4路線長度km53.26453.262
2
項(xiàng)目專項(xiàng)施工方案
5路線增長系數(shù)/1.0681.068
6交點(diǎn)數(shù)個(gè)2525
7平均每公里交點(diǎn)數(shù)個(gè)0.4690.469
8平曲線占路線總長%58.09956.609
9圓曲線最小半徑mJan-03Jan-00
10最大縱坡%/處3.235/13.764/1
11最短坡長m310455
12平均每公里縱坡變更次數(shù)%1.1831.145
凸形m14000/114000/2
13最小豎曲線半徑
凹形m12000/113137.62/1
14豎曲線占路線總長%58.28957.9
2.2.1路基斷面型式
(1)路基加寬方案:
本路段現(xiàn)狀為雙向六車道高速公路,本項(xiàng)目推薦方案改擴(kuò)建方式為“兩側(cè)拼寬為主,
局部路段中分帶偏移”,設(shè)計(jì)速度為120km/h。
(2)路基標(biāo)準(zhǔn)橫斷面:
項(xiàng)目主線為六車道改擴(kuò)建成八車道工程,改建、線位偏移、調(diào)整縱段標(biāo)準(zhǔn)整體式路
基寬42m,其中:中間帶寬4.5m(中央分隔帶3.0m+路緣帶2×0.75m),行車道寬度2×
4×3.75m,硬路肩寬為2×3.0m(含路緣帶寬2x0.5m),土路肩寬度2×0.75m。
(3)路基設(shè)計(jì)標(biāo)高及路拱橫坡:主線整體式路基設(shè)計(jì)標(biāo)高為中央分隔帶路緣石外側(cè)
邊緣處路面標(biāo)高;行車道、路緣帶及硬路肩采用2%橫坡,土路肩采用4%橫坡。
(4)路基超高及加寬:本路段主線超高及加寬按照規(guī)范設(shè)置。
(5)公路用地范圍:路堤兩側(cè)排水溝外邊緣(無排水溝時(shí)為路堤或護(hù)坡道坡腳)以
外1.0m,或路塹坡頂截水溝外邊緣以外1.0m,無截水溝為坡頂以外2.0m范圍內(nèi)的土地
為公路用地范圍。橋梁地段除特、大橋常水位時(shí)水面寬度所占用的土地不作為橋梁用地
外,其余橋梁為正投影。
2.3工程施工條件
2.3.1沿線地質(zhì)、地層情況描述
根據(jù)區(qū)域地質(zhì)資料,擬建路線廊帶范圍內(nèi)分布的主要地層如下:
3
項(xiàng)目專項(xiàng)施工方案
(1)第四系(Q)
第四系(Q)主要是現(xiàn)代沉積,多分布于現(xiàn)代河谷和山間盆地之中、本區(qū)西南部平
原湖沼地區(qū),厚者可達(dá)200m左右,一般除表層的黃土狀土、砂礫等沖、洪積層外,在
沉積較厚的地區(qū),夾湖沼淤積層。
全新統(tǒng)(Q4)
淺黃、灰黃色粉土、粉砂、粉細(xì)砂層夾少量灰白色鈣質(zhì)結(jié)核及小礫石。結(jié)構(gòu)疏松,
層理清晰。
上更新統(tǒng)(Q3)
上部為淺黃色、褐黃色粉土、粉質(zhì)黏土及粉砂、粉細(xì)砂層;下部為棕黃色粉質(zhì)黏土、
粉土夾粉細(xì)砂和黏土層,局部地區(qū)夾有細(xì)礫、中細(xì)砂層,含大量的鈣質(zhì)結(jié)合。
中更新統(tǒng)(Q2)
以橙黃、棕紅、灰綠色粉質(zhì)黏土、粉土及黏土為主,夾薄層粉砂、粉細(xì)砂,局部地
區(qū)夾厚3m左右的淤泥質(zhì)粉土。黏性上常具灰綠色條紋及灰白色長石風(fēng)化斑點(diǎn),結(jié)構(gòu)致
密,含鈣質(zhì)及鐵錳質(zhì)結(jié)核。
下更新統(tǒng)(Q1)
雜色黏土、粉質(zhì)黏土及薄層粉細(xì)砂層。下部具有中細(xì)砂層,含礫中粗砂層,局部被
鈣質(zhì)膠結(jié)為砂巖、砂礫巖,礫石一般為鈣質(zhì)結(jié)合及砂巖塊,粒徑0.2-3cm。黏土結(jié)構(gòu)致
密,裂面光滑而具油脂光澤,夾灰綠色斑塊,具網(wǎng)狀細(xì)紋。
(2)奧陶系(O)
奧陶系(O)該系地層分布和出露地區(qū)基本和寒武系地層一致,一般都緊靠其上。
奧陶系地層也分上、中、下統(tǒng)。下統(tǒng)又分為紙坊莊組、北庵莊組和馬家溝組,中統(tǒng)包括
閣莊組和八陡組。本區(qū)缺失上統(tǒng),總厚約700-800m。主要由厚層狀的石灰?guī)r、薄層狀
的泥質(zhì)石灰?guī)r以及白云質(zhì)石灰?guī)r組成。在萊蕪、泰安一帶,由于巖漿活動(dòng)的熱液接觸交
代作用,產(chǎn)生有重要的富鐵礦床。
奧陶系馬家溝組第二段(O2m2):含燧石結(jié)核灰?guī)r。
奧陶系馬家溝組第一段(O2m1):純灰?guī)r、豹皮狀灰?guī)r夾白云質(zhì)灰?guī)r。
奧陶系馬家溝組未分(O2m):泥灰?guī)r、純灰?guī)r夾豹皮灰?guī)r。
奧陶系冶里-亮甲山組(O1y-1):白云質(zhì)灰?guī)r。
(3)寒武系(E)
古生界寒武系(E)該系地層區(qū)內(nèi)分布很廣,特別是前述山區(qū)的兩翼均有大面積出
4
項(xiàng)目專項(xiàng)施工方案
露,其中泰山西北坡的崮山、張夏、炒米店一帶是中國北方寒武系地層的命名地之
一,是具有國際意義的寒武系標(biāo)準(zhǔn)地層剖面。該系地層從老到新劃分為下統(tǒng)、中統(tǒng)和上
統(tǒng)。主要由石灰?guī)r、泥質(zhì)石灰?guī)r、鮞狀石灰?guī)r、竹葉狀石灰?guī)r以及紫色、黃綠色砂質(zhì)頁
巖所組成,總厚一般為600-800m,含三葉蟲化石。
鳳山組(E3r):泥質(zhì)條帶灰?guī)r,竹葉狀灰?guī)r夾豹皮狀灰?guī)r及鮞狀灰?guī)r。
長山組、鳳山組未分(E3c+f):灰?guī)r,竹葉狀灰?guī)r夾豹皮狀灰?guī)r及鮞狀灰?guī)r。
長山組(E3c):灰?guī)r、泥灰?guī)r夾竹葉狀灰?guī)r。
長山組、固山組未分(E3c+g):頁巖、板狀灰?guī)r,竹葉狀灰?guī)r及泥質(zhì)條帶灰?guī)r。
固山組(E3g):頁巖夾灰?guī)r及竹葉狀灰?guī)r。
張夏組(E22):含海綠石鮞狀灰?guī)r,豹皮灰?guī)r夾結(jié)晶灰?guī)r。
徐莊組(E2x):頁巖夾鮞狀灰?guī)r及具磷酸鹽反應(yīng)的交錯(cuò)層砂質(zhì)灰?guī)r。
毛莊組(E1mmz):云母頁巖夾鮞狀灰?guī)r。
饅頭組(E1mm2):泥質(zhì)灰?guī)r夾頁巖。
(4)泰山群(Art)
太古界泰山群(Art),為一套巨厚而復(fù)雜的深變質(zhì)巖系,通常稱之為“泰山雜巖”,
是最古老的巖石之一。主要有片麻巖類、角閃巖類、片巖、變粒巖及混合巖類等深變質(zhì)
巖組成,是很好的建筑石料。按地層劃分,自下而上可分為萬山莊、太平頂、雁翎關(guān)和
山草峪等四個(gè)層組,總厚度在11000m以上。主要分布于泰山、祖徠山、蓮花山、蒙山
以及萊蕪、新泰、肥城一帶的高山脊軸地區(qū)。
太平頂組(Artr):角閃黑云斜長片麻巖及黑云鉀長片麻巖。
雁翎關(guān)組(Arty):角閃石片巖。
山草峪組(Arts):黑云變粒巖及黑云片麻巖。
(5)混合巖類
混合巖(Ga-y):花崗巖及花崗片麻巖。
2.3.2水文地質(zhì)
場區(qū)地下水類型主要為松散巖類孔隙水、碳酸鹽巖裂隙巖溶水、基巖裂隙水三種。
路線沿線的地下水受地形、地貌、地層構(gòu)造、巖性分布等水文地質(zhì)條件的制約,形成不
同的水文地質(zhì)單元,富水程度有明顯的差異,地表土層的天然含水量隨季節(jié)、地表和地
下水的變化而變化。大氣降水是地下水的主要補(bǔ)給來源,由于區(qū)內(nèi)地形起伏變化,地下
水隨地形伸展運(yùn)動(dòng),呈連續(xù)的高低起伏的不統(tǒng)一的自由水面。
5
項(xiàng)目專項(xiàng)施工方案
地下水類型及儲(chǔ)運(yùn)規(guī)律,根據(jù)地質(zhì)成因的不同可分為三類。即:山前第四紀(jì)洪殘積
含水層、第四紀(jì)和第三紀(jì)沖積含水層、基巖風(fēng)化裂隙水含水層。不同類型的含水層交接
過渡呈相互疊置關(guān)系。由于地質(zhì)構(gòu)造、地層巖性、地形地貌、補(bǔ)給條件的控制和第四紀(jì)
沉積環(huán)境的影響,決定了地下水的分布和變化規(guī)律。場區(qū)整體地勢起伏較小,上部無明
顯隔水層,而區(qū)域內(nèi)降水季節(jié)不均,夏豐冬枯,從而導(dǎo)致地下水水位隨季節(jié)變化嚴(yán)重不
均。
地下水類型比較單一,主要是重碳酸鹽型水及碳酸鹽水,其次是氯化物型水。地下
水PH值,屬弱酸性-弱堿性水,礦化度小于2克/升,屬全淡型水,大都符合人畜飲用
和工農(nóng)業(yè)用水標(biāo)準(zhǔn)。
根據(jù)水質(zhì)分析試驗(yàn)結(jié)果,按《公路工程地質(zhì)勘察規(guī)范》(JTGC20-2011)評(píng)定,場區(qū)
環(huán)境類型屬Ⅱ類,擬建項(xiàng)目所經(jīng)區(qū)域的水質(zhì)對(duì)混凝土結(jié)構(gòu)有微~弱腐蝕性,對(duì)鋼筋混凝
土結(jié)構(gòu)中的鋼筋有微~弱腐蝕性。
2.3.3地震
本區(qū)域在地震分區(qū)上處于華北地震區(qū)的郯城一營口地震帶,是我國東部大陸區(qū)一條
強(qiáng)烈地震活動(dòng)帶。據(jù)記載本帶共發(fā)生4.7級(jí)以上地震60余次,其中7-7.9級(jí)地震6次;
8級(jí)以上地震1次。
根據(jù)《中國地震動(dòng)參數(shù)區(qū)劃圖》(GB18306-2015)相關(guān)內(nèi)容,xx高速公路濟(jì)南至泰
安段改擴(kuò)建工程起點(diǎn)~K439+200段、K451+600~終點(diǎn)段地震動(dòng)峰值加速度為0.10g,相
應(yīng)的基本地震烈度為Ⅶ度;K439+200~K451+600段地震動(dòng)峰值加速度為0.05g,相應(yīng)的
基本地震烈度為VI度;擬建場區(qū)動(dòng)反應(yīng)譜特征周期為0.45s。
2.3.4工程施工環(huán)境
表2.3.4主要爆破段落初步劃分及工程量
序
段落位置分級(jí)估算方量(m3)歸屬辦事處
號(hào)
1K418+460-K418+780右幅最高兩級(jí)29902
濟(jì)南長清區(qū)崮云
2K422+580-K422+710右幅最高兩級(jí)12148
湖辦事處
3K423+020-K423+090右幅最高兩級(jí)5038
4K431+400-K431+530右幅最高兩級(jí)29575濟(jì)南長清區(qū)張夏
5K434+650-K435+356左幅僅爆破一級(jí)214520辦事處
6K445+900-K446+430右幅最高三級(jí)96025濟(jì)南長清區(qū)萬德
6
項(xiàng)目專項(xiàng)施工方案
辦事處
7K447+680-K447+810右幅最高四級(jí)49646
8合計(jì)43.68萬m3/
(1)主要爆破段落橫斷面圖
圖2.3.4-1K434+650-K435+356橫斷面
圖2.3.4-2K446+130-K446+302橫斷面
7
項(xiàng)目專項(xiàng)施工方案
圖2.3.4-3高邊坡BIM效果圖
(2)施工環(huán)境
項(xiàng)目范圍內(nèi)巖石節(jié)理發(fā)育,多為風(fēng)化片麻巖、石灰?guī)r及花崗巖,f值在5-10之間,
爆破施工深度深淺不一,深度在3m-52m之間。項(xiàng)目范圍沿線其他區(qū)域巖石硬度低、下
挖深度淺,主要采用機(jī)械方式施工或有爆破施工均為零星爆破點(diǎn),爆破范圍50m以外的
路基需要保護(hù)。
根據(jù)周圍環(huán)境情況,每個(gè)作業(yè)隊(duì)每次爆破藥量不超過10000kg(通長為4000kg-5000
kg),對(duì)爆破區(qū)域周邊環(huán)境進(jìn)行調(diào)查,包括周邊房屋、管線等。根據(jù)環(huán)境(保證一側(cè)正
常通車)及一次爆破用量本工程路基爆破工程確定為露天巖土爆破B級(jí)。
①K418+460-K418-780段
段1位于濟(jì)南市長清區(qū)崮云湖街道開山村西北約300m,地形起伏較大,施工位置
樁號(hào)為K418+460至K418+780。具體位置位于崮山收費(fèi)站南側(cè),距離崮山收費(fèi)站辦公
樓最近距離85m,爆區(qū)東北側(cè)有一處廠房,最近距離約85m,擬對(duì)其進(jìn)行拆遷,爆區(qū)西
北側(cè)有一處房屋,最近距離約85m,爆區(qū)西側(cè)為一處廠房,最近距離約為105m。
8
項(xiàng)目專項(xiàng)施工方案
圖2.3.4-4K418+460-K418+780右幅(距最近房屋85m)
②K422+580-K422-710段
段2位于濟(jì)南市長清區(qū)范莊村西北約500m,地形起伏較大,施工位置樁號(hào)為K422+5
80至K422+710。具體位置位于xx高速西側(cè),東側(cè)在高速公路對(duì)面有一處房屋,距離約
為85m。爆破區(qū)域南側(cè)和北側(cè)為高速公路延長線,爆破區(qū)域西側(cè)為山體。
圖2.3.4-5K422+580-K422+710右幅(距最近房屋85m)
③K423+020-K423-090段
段3位于濟(jì)南市長清區(qū)鳳凰莊村西北約300m,地形起伏較大,施工位置樁號(hào)為K428
+740至K428+920。具體位置位于xx高速東側(cè),爆破區(qū)域東側(cè)約300m有一條村鎮(zhèn)道路,
爆破區(qū)域西側(cè)約140m處有一條村鎮(zhèn)道路。爆破區(qū)域南側(cè)和北側(cè)為高速公路延長線,爆
破區(qū)域東側(cè)為山體。
9
項(xiàng)目專項(xiàng)施工方案
圖2.3.4-6K423+020-K423+090右幅(距最近房屋65m)
圖2.3.4-7K431+400-K431+530右幅(距最近房屋85m)
10
項(xiàng)目專項(xiàng)施工方案
圖2.3.4-8K434+650-K435+356左幅(僅爆破第一級(jí)其余機(jī)械破碎開挖,
距最近房屋280m,國防光纜30m)
圖2.3.4-9K445+900-K446+430右幅為主(距最近房屋226m)
11
項(xiàng)目專項(xiàng)施工方案
圖2.3.4-10K447+680-K447+810右幅(距最近房屋120m)
第三章施工安排
3.1項(xiàng)目管理組織
為完成本工程任務(wù),加強(qiáng)項(xiàng)目施工標(biāo)準(zhǔn)化管理,確保工程建設(shè)工期、質(zhì)量、安全目
標(biāo),由項(xiàng)目經(jīng)理部總負(fù)責(zé),一、二、三、四工區(qū)負(fù)責(zé)具體施工,工程技術(shù)部、計(jì)劃合同
部、物資設(shè)備部、安全質(zhì)量部、征地協(xié)調(diào)部、測量部、財(cái)務(wù)資金部、綜合辦公室、試驗(yàn)
室共9個(gè)職能部室配合,現(xiàn)場專業(yè)工程師進(jìn)行管理及協(xié)調(diào)工作。
挖方爆破施工組織機(jī)構(gòu)如圖3.1:
項(xiàng)目經(jīng)理
生產(chǎn)/協(xié)調(diào)經(jīng)理項(xiàng)目總工常務(wù)副經(jīng)理商務(wù)經(jīng)理安全總監(jiān)
工程技術(shù)部安全部質(zhì)量部商務(wù)部物資設(shè)備部綜合辦公室試驗(yàn)室測量部交通保障部協(xié)調(diào)部財(cái)務(wù)部
工程技術(shù)部長安全管理員質(zhì)量總監(jiān)計(jì)劃合同部長物資部部長辦公室主任試驗(yàn)室主任測量部部長交通保障部部長協(xié)調(diào)辦主任財(cái)務(wù)主管
技術(shù)/專業(yè)工程師質(zhì)量工程師商務(wù)工程師材料工程師辦公室文員試驗(yàn)工程師測量工程師交通保障員協(xié)調(diào)專員
一工區(qū)二工區(qū)三工
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 2024年標(biāo)準(zhǔn)展位搭建及撤展服務(wù)承攬協(xié)議版
- 2024年標(biāo)準(zhǔn)勞務(wù)派遣合作協(xié)議模板版B版
- 2024年民間個(gè)人借款協(xié)議合同模板
- 2024年砂石供應(yīng)中介服務(wù)協(xié)議版
- 借款合同中的利息規(guī)定
- 家用凈水器銷售協(xié)議
- 接地防雷分包工程合同范本
- 項(xiàng)目委托合同協(xié)議簽訂注意事項(xiàng)
- 2024年度電子商務(wù)支付安全標(biāo)準(zhǔn)制定與實(shí)施協(xié)議3篇
- 生豬銷售合同協(xié)議書
- GB/T 38119-2019邵氏硬度計(jì)的檢驗(yàn)
- GB/T 31856-2015廢氯氣處理處置規(guī)范
- 珠寶領(lǐng)域:周大生企業(yè)組織結(jié)構(gòu)及部門職責(zé)
- 中藥配方顆粒
- 如何理解歐盟MDR臨床評(píng)價(jià)要求
- 課題工作方案范文模板及進(jìn)度計(jì)劃3篇
- 養(yǎng)老機(jī)構(gòu)醫(yī)護(hù)服務(wù)管理制度
- DB4405-T 293-2022《紅螯螯蝦池塘養(yǎng)殖技術(shù)規(guī)范》-(高清現(xiàn)行)
- 檔案袋密封條模板
- 最新版護(hù)理常規(guī)
- 互聯(lián)網(wǎng)+大賽創(chuàng)新創(chuàng)業(yè)路演PPT課件(帶內(nèi)容)
評(píng)論
0/150
提交評(píng)論