1、#10機(jī)組除氧器吊裝(X-005) 16 / 17作 業(yè) 指 導(dǎo) 書工程名稱:內(nèi)蒙古大唐國際托克托電廠五期擴(kuò)建工程編號(hào): X-005作業(yè)項(xiàng)目名稱:#10機(jī)組除氧器吊裝作業(yè)編制單位:中能建江蘇省電力建設(shè)第一工程有限公司大唐托電項(xiàng)目部編寫: 日期:審核: 日期:審定: 日期: 日期:批準(zhǔn): 日期:出版日期:版次: 第一版目 錄1適用范圍······················&
2、#183;········································22編制依據(jù)········&
3、#183;·················································&
4、#183;····23主要工程量············································
5、·················24組織機(jī)構(gòu)和作業(yè)人員的資格要求······························
6、183;············25主要機(jī)械及工器具···································
7、3;···················46施工進(jìn)度·····························
8、3;·································47施工準(zhǔn)備···············
9、3;···············································48作業(yè)程序·
10、3;·················································
11、3;···········59作業(yè)方法、工藝要求及質(zhì)量標(biāo)準(zhǔn)····································
12、·······510相關(guān)計(jì)算 ·········································
13、3;················711工序交接及成品保護(hù)·······························
14、3;····················912安全和文明施工措施···························
15、3;························913強(qiáng)制性條文························
16、183;···································1014應(yīng)急處置方案············
17、3;·············································11附表:重大危險(xiǎn)源/重要環(huán)境因素控制計(jì)劃表·
18、··································141 適用范圍 本作業(yè)指導(dǎo)書適用于指導(dǎo)和實(shí)施我公司承建的內(nèi)蒙古大唐國際托克托電廠五期擴(kuò)建工程10#機(jī)組除氧器吊裝作業(yè)。2 編制依據(jù)除氧器安裝圖 圖號(hào):F211102S-J0302-11CC2
19、500(450t)履帶吊使用說明書FZQ1380(63t)塔式起重機(jī)使用說明書 起重機(jī)械安全規(guī)程 GB 6067.12010電力建設(shè)安全工作規(guī)程火力發(fā)電廠部分 DL 5009.1-2014 特種設(shè)備安全法 2014年1月1日起施行 起重機(jī)械安全規(guī)程 GB 6067.12010 特種設(shè)備作業(yè)人員監(jiān)督管理辦法 國家質(zhì)量監(jiān)督檢驗(yàn)檢疫總局令第140號(hào) 起重機(jī)械監(jiān)督檢驗(yàn)規(guī)程 國家質(zhì)量監(jiān)督檢驗(yàn)檢疫總局 大唐托克托電廠五期擴(kuò)建工程第二標(biāo)段施工組織設(shè)計(jì) 江蘇電建一公司大唐托克托電廠五期擴(kuò)建工程施工總平面圖引用標(biāo)準(zhǔn)GB/T706-2008、GB/T8919-2006、GB/T20067-2006等3 主要工程量
20、內(nèi)蒙古大唐國際托克托電廠五期擴(kuò)建工程10#機(jī)組除氧器采用滑壓運(yùn)行,正常運(yùn)行由汽輪機(jī)四段抽汽供汽,啟動(dòng)或低負(fù)荷時(shí)由輔助蒸汽系統(tǒng)供汽。本期機(jī)組汽機(jī)房不設(shè)除氧間,除氧器布置在鍋爐房K0-K1鋼架上。除氧器外形尺寸為26100mm×4360mm×4500mm,凈重約為95t。 就位軸向中心線標(biāo)高44851mm,基礎(chǔ)支座平面標(biāo)高為41300mm,距離K1鋼柱中心4238mm。鋼架立柱G3-G5排柱中心距離28000mm,實(shí)際凈吊裝距離為27300mm,根據(jù)設(shè)備到貨和鍋爐安裝情況,決定由450t履帶吊單機(jī)吊裝除氧器直接落在元寶座上就位。除氧器采用450t履帶吊卸車。4 組織機(jī)構(gòu)和作業(yè)人
21、員的資格要求4.1組織機(jī)構(gòu)以江蘇電建一公司大唐托克托項(xiàng)目部為依托,按照以下表格內(nèi)要求抽調(diào)專業(yè)骨干實(shí)施作業(yè)。為保證吊裝安全,特成立“大唐托克托項(xiàng)目部#10除氧器吊裝”專項(xiàng)組織機(jī)構(gòu),見下表:序號(hào)姓名分工職務(wù)/職稱1呂從軍吊裝總負(fù)責(zé)人副經(jīng)理/高工2翁慶松現(xiàn)場安全管理安全科長3李安保吊裝區(qū)域安全監(jiān)督安全員4丁興宏吊裝機(jī)械安全監(jiān)督機(jī)修工地安全員5畢正斌安裝負(fù)責(zé)人機(jī)爐工地主任6孫逸誠施工協(xié)調(diào)工程科科長7鄧海雄吊裝負(fù)責(zé)人機(jī)修工地主任8陸茂生起重總指揮機(jī)爐工地起重班長9林大亮方案編制、技術(shù)指導(dǎo)機(jī)修工地專工10丁慶濤現(xiàn)場應(yīng)急預(yù)案準(zhǔn)備辦公室主任4.2勞動(dòng)力計(jì)劃和作業(yè)人員的資格要求序號(hào)工種技術(shù)等級(jí)數(shù)量特殊工種上崗證
22、備注1電工中級(jí)工1電工證監(jiān)護(hù)現(xiàn)場供電2鉗工中級(jí)工2監(jiān)護(hù)履帶吊3起重指揮中級(jí)工2起重指揮證除氧器吊裝指揮4起重司索初級(jí)工4起重司索證除氧器吊裝司索5操作工中級(jí)工6起重機(jī)械操作操作起重機(jī)械6安裝工初、中級(jí)工4安裝除氧器7架子工初、中級(jí)工4架子工證7安全員2安全員證安全監(jiān)護(hù)8電風(fēng)焊工中級(jí)工2焊工證加固焊接9總指揮高級(jí)工1協(xié)調(diào)吊裝作業(yè)10技術(shù)員中級(jí)1措施、技術(shù)交底5 主要機(jī)械及工器具 序號(hào)名稱規(guī)格型號(hào)數(shù)量備注1履帶式起重機(jī)450t一臺(tái)吊裝2塔式起重機(jī)1380/63tT一臺(tái)輔助3卸扣35t4只4千斤繩6×37-170-65mm 2對30m5鋼絲繩6×37-170-17.5mm400m
23、6鋼絲繩20mm 20m/對2對7溜繩60m2根8風(fēng)焊工具2套9鏈條葫蘆5t、2t若干10千斤頂100t4只11捆綁繩若干12卷尺5m若干6 施工進(jìn)度 本項(xiàng)目預(yù)計(jì)12月底開始準(zhǔn)備,1月初完成吊裝。7 施工準(zhǔn)備7.1履帶吊工作場地準(zhǔn)備:鍋爐鋼架驗(yàn)收合格,擴(kuò)建端場地平整、壓實(shí)后鋪好路基板,滿足履帶吊作業(yè)。7.2吊車準(zhǔn)備CC2500(450t)履帶吊SWSL工況,接54m主臂、30m副臂、配重120t、超級(jí)配重140t,超起半徑15m、超起副臂30m。履帶吊幅度工況性能如下表。幅度m28m30m32m34m起重量t12611610899CC2500(450t)履帶吊SSL工況,接54m主臂、中心配重
24、30t,配重140t,超起半徑15m、超起臂30m。履帶吊幅度工況性能如下表。幅度m10m12m14m16m起重量t242179140114 FZQ1380塔吊,回轉(zhuǎn)半徑25米,最大起重量52.8t。 7.3 除氧器及吊車停放在除氧間外側(cè)托運(yùn)軸線方向,按圖一布置要求停放:圖一:450t履帶吊起吊除氧器卸車7.4 現(xiàn)場條件準(zhǔn)備7.4.1 環(huán)境準(zhǔn)備i 滅火器等器材已定址放置。ii 施工電源布置完成。iii 通道暢通,光線充足,安全設(shè)施工作狀態(tài)良好,氧乙炔供應(yīng)充足。iv 安裝區(qū)域平臺(tái)完善,格柵板鋪設(shè)完畢,預(yù)留孔洞裝設(shè)蓋板,無妨礙施工的任何物品。7.4.2 安全條件i 設(shè)立臨時(shí)警戒區(qū)域,派專人監(jiān)護(hù),無
25、關(guān)人員不得入內(nèi)。ii 吊裝、托運(yùn)用具、支座滾柱必須檢查應(yīng)滿足安全使用要求。iii 安全防護(hù)設(shè)施及安全用具(安全帶等)必須符合安全使用要求。iv 所有參加作業(yè)人員必須經(jīng)過三級(jí)安全教育,高空作業(yè)人員必須經(jīng)過體檢合格后方可參加作業(yè)。作業(yè)前必須對所有參加人員進(jìn)行安全、技術(shù)和質(zhì)量交底。8 作業(yè)程序 鍋爐鋼架設(shè)施驗(yàn)收合格 450t履帶吊就位 除氧器卸車 450t履帶吊就位除氧器吊裝 找正安裝就位9 作業(yè)方法、工藝要求及質(zhì)量標(biāo)準(zhǔn)9.1除氧器由450t履帶吊卸車時(shí),接54m主臂、配重140t,超起半徑15m、超起副臂30m,回轉(zhuǎn)半徑13m,最大起重量140t,單機(jī)起吊,鋼絲繩鉤頭重約8t,吊裝總重約為103t
26、,負(fù)荷率約73.6%,滿足要求。9.2除氧器吊裝時(shí),用一臺(tái)450t履帶吊(接54m主臂、30m副臂、配重120t、超級(jí)配重100t,超起半徑15m、超起副臂30m),回轉(zhuǎn)半徑22m,最大起重量140t,單機(jī)起吊,鋼絲繩鉤頭重約8t,吊裝總重約為103t,負(fù)荷率約73.6%,滿足要求。起吊前應(yīng)檢查起重機(jī)械及其安全裝置;除氧器吊離地面約10cm時(shí)應(yīng)暫停起吊并進(jìn)行全面檢查和試驗(yàn)剎車,確認(rèn)正常后方可正式起吊。第一步:450t履帶吊帶100t超級(jí)配重,除氧器緩慢起吊,待超過除氧器就位層41.3m約10cm后停止起吊。第二步:450t履帶吊幅度不變,沿走道板方向緩慢向前移動(dòng)21.1m,待除氧器到達(dá)KO、K
27、1軸線上方,停止移動(dòng)。第三步:450t履帶吊增加40t超級(jí)配重(由1380塔吊在25m幅度吊裝4塊10t超級(jí)配重,負(fù)荷率為18%),超級(jí)配重總重140t,然后緩慢變幅至32m,除氧器達(dá)到就位位置上方,找準(zhǔn)就位中心,緩慢的將除氧器放在固定的元寶型支座上。450t履帶吊,回轉(zhuǎn)半徑32m,額定起重量為108t,負(fù)荷率為95.3%,滿足要求。見下圖三:圖二:吊裝立面圖 圖三:起吊平面圖圖四:就位平面圖9.5 施工過程要求。 施工作業(yè)人員必須按圖紙、有關(guān)規(guī)程規(guī)范和作業(yè)指導(dǎo)書要求進(jìn)行施工。在施工過程中對有疑問不清楚之處及時(shí)反饋給施工總指揮,不得盲目施工。在施工過程中如發(fā)現(xiàn)問題需立即向技術(shù)人員及現(xiàn)場指揮人員
28、匯報(bào),不得擅自施工。10 相關(guān)計(jì)算10.1 鋼絲繩校核在吊裝過程中除氧器凈重95t,履帶吊選用6×37+FC-1870-65mm千斤繩破斷拉力T=254t。千斤繩起吊夾角220(見下圖七),則鋼絲繩單根受力: N=95/(4·COS11º) =95/(4×0.98)=24.2t吊裝鋼絲繩的安全系數(shù)K,K=T/N=254/24.2=10.49>8 滿足要求。 圖五:鋼絲繩夾角示意圖10.4 除氧器卸車要求高度:圖六:卸車高度幅度校核 除氧器卸車時(shí),450t起吊后,吊裝高度剩余30m,除氧器距離履帶吊主臂7.5m,滿足吊裝要求。 11 工序交接及成品保
29、護(hù) 除氧器吊裝過程中,鋼絲繩生鉤過程等不得對除氧器造成損傷,做好保護(hù),對各施工階段所需物品應(yīng)提前準(zhǔn)備;各施工階段結(jié)束后應(yīng)核查是否達(dá)到預(yù)計(jì)效果,判斷能否進(jìn)行下一工序施工。12 安全和文明施工措施12.1 技術(shù)人員應(yīng)在起吊作業(yè)前進(jìn)行安全、技術(shù)、質(zhì)量交底,交底時(shí)分公司總工、安全科、工程科、機(jī)修工地、機(jī)爐工地及甲方、監(jiān)理有關(guān)人員到場,起吊前應(yīng)開好安全作業(yè)票。12.2 劃定工作區(qū)域,并派專人監(jiān)護(hù),無關(guān)人員不得入內(nèi),不得在危險(xiǎn)區(qū)域內(nèi)逗留或通過?,F(xiàn)場吊裝應(yīng)由專人指揮,指揮信號(hào)應(yīng)統(tǒng)一,分工明確,信號(hào)清楚。12.3除氧器吊裝前,必須先將元寶座安裝在鍋爐鋼架上,保證除氧器順利就位。12.4因現(xiàn)場情況復(fù)雜,現(xiàn)場施工
30、區(qū)域內(nèi)應(yīng)清理干凈、清理與施工無關(guān)的雜物。12.5起吊用索具必須檢查,確保索具合格后再進(jìn)行作業(yè)。起吊前認(rèn)真檢查吊機(jī),尤其是力矩限制器及各限位等安全裝置,以保證機(jī)械機(jī)況的完好。12.6起吊、行走回轉(zhuǎn)及脫鉤等過程一定要緩慢,特別注意工序步驟的銜接。12.7 施工過程中要有專人監(jiān)護(hù)吊機(jī)卷揚(yáng)機(jī)。12.8 高空作業(yè)施工人員必須系好安全帶,并牢固地掛在施工作業(yè)區(qū)的上方牢固處。高處作業(yè)的平臺(tái)、走道、斜道等應(yīng)裝設(shè)由上下兩道欄桿和欄桿組成的防護(hù)欄桿及檔腳板,或設(shè)防護(hù)立網(wǎng)。12.9 高處作業(yè)所用工具必須系安全繩,傳遞物件禁止拋擲,設(shè)備、材料及廢料臨時(shí)存放在要有可靠的防止移動(dòng)和墜落的措施。12.10嚴(yán)格控制除氧器保持
31、水平,以免載荷分配變化。12.11履帶吊拆鉤時(shí)作業(yè)人員必須掛好安全帶防止高空墜落及高空落物。12.12 除氧器拖運(yùn)過程中應(yīng)注意保持拖運(yùn)方向,防止側(cè)向滑移。12.13 千斤頂頂升就位時(shí)應(yīng)做好各項(xiàng)防護(hù)措施。12.14 吊裝作業(yè)完畢后,把所有工具,器具,材料和一切雜物回收分類存放,嚴(yán)禁污染破壞環(huán)境。12.15 發(fā)生任何意外情況,按照分公司相應(yīng)應(yīng)急預(yù)案處置。12.16作業(yè)完畢必須做到“工完料盡,場地清”文明施工。13、強(qiáng)制性條文:電力建設(shè)安全工作規(guī)程火力發(fā)電廠部分/DL 5009.1-20144.12.1通用規(guī)定:1 作業(yè)前應(yīng)進(jìn)行安全技術(shù)交底,交底人和作業(yè)人員簽字。2 作業(yè)應(yīng)統(tǒng)一指揮。指揮人員和操作人
32、員應(yīng)集中精力、堅(jiān)守崗位,不得從事與作業(yè)無關(guān)活動(dòng)。3 起重機(jī)械操作人員、指揮人員(司索信號(hào)工)應(yīng)經(jīng)專業(yè)技術(shù)培訓(xùn)并取得操作資格證書。5 起重作業(yè)前應(yīng)對起重機(jī)械、工機(jī)具、鋼絲繩、索具、滑輪、吊鉤進(jìn)行全面檢查。11嚴(yán)禁在惡劣天氣或照明不足情況下進(jìn)行起重作業(yè)。當(dāng)作業(yè)地點(diǎn)的風(fēng)力達(dá)到五級(jí)時(shí),不得吊裝受風(fēng)面積大的物件;當(dāng)風(fēng)力達(dá)到六級(jí)及以上時(shí),不得進(jìn)行起重作業(yè)。4.12.4起重作業(yè)應(yīng)符合以下規(guī)定:2 兩臺(tái)及以上起重機(jī)械抬吊同一物件。1) 宜選用額定起重量相等和相同性能的起重機(jī)械。嚴(yán)禁超負(fù)荷使用。2) 各臺(tái)起重機(jī)械所承受的載荷不得超過本身80%的額定載荷。抬吊過程中,各臺(tái)起重機(jī)的吊鉤鋼絲繩應(yīng)保持垂直,升降、行走應(yīng)
33、同步進(jìn)行。14 應(yīng)急處置方案14.1應(yīng)急保護(hù)對象:14.1.1在除氧器吊裝作業(yè)期間,如果發(fā)生人員高空墜落、高空落物傷人等人身傷害事故,應(yīng)沉著冷靜及時(shí)組織救援,將人身傷害程度降至最低。14.1.2在除氧器吊裝作業(yè)期間,如果發(fā)生機(jī)械設(shè)備事故,及時(shí)組織救援,將設(shè)備事故損失降至最低程度。14.2.應(yīng)急地點(diǎn):項(xiàng)目部應(yīng)急小組辦公室14.3應(yīng)急指揮機(jī)構(gòu)序號(hào)姓名擔(dān)任職務(wù)備注1呂從軍總指揮組織指揮應(yīng)急救援2鄧海雄副總指揮協(xié)助總指揮負(fù)責(zé)具體指揮工作3黃愛國指揮組成員組織救援人員實(shí)施事故的應(yīng)急響應(yīng)4林大亮指揮組成員組織救援人員實(shí)施事故的應(yīng)急響應(yīng)5丁慶濤救援組成員協(xié)調(diào)醫(yī)務(wù)、汽車司機(jī)等人員為主6翁慶松指揮組成員組織救援
34、人員實(shí)施事故的應(yīng)急響應(yīng)14.4應(yīng)急處置方案啟動(dòng)14.4.1應(yīng)急處置方案啟動(dòng)條件:1)在作業(yè)期間,嚴(yán)重威脅人身安全或已經(jīng)造成人身傷害的情況下。2)在作業(yè)期間,可能或已經(jīng)造成機(jī)械設(shè)備事故的情況下。14.4.2應(yīng)急處置方案啟動(dòng)步驟:1) 發(fā)生緊急情況時(shí),應(yīng)立即與應(yīng)急小組成員取得聯(lián)系。2)應(yīng)急小組成員接到通知后,立即到應(yīng)急小組辦公室集中。3)應(yīng)急小組在確認(rèn)緊急情況后,由應(yīng)急小組指揮決定是否啟動(dòng)應(yīng)急預(yù)案。4)應(yīng)急小組在指揮下組織對人員、機(jī)械設(shè)備實(shí)施救援。14.5應(yīng)急響應(yīng)網(wǎng)絡(luò)及方法步驟:14.5.1網(wǎng)絡(luò):突發(fā)事件指揮小組信息網(wǎng)絡(luò)開通判斷響應(yīng)級(jí)別人員救助應(yīng)急資源調(diào)配應(yīng)急啟動(dòng)火災(zāi)現(xiàn)場指揮救援行動(dòng)現(xiàn)場清理機(jī)械設(shè)備 善后處理應(yīng)急救援環(huán)境保護(hù)事故調(diào)查14.5.2方法步驟:1)現(xiàn)有條件組織救援,保護(hù)現(xiàn)場。2)向指揮小組成員報(bào)警。3)人員救護(hù)向醫(yī)療救護(hù)報(bào)警,報(bào)警時(shí)說明地點(diǎn),傷害程度情況,14.5.3指揮機(jī)構(gòu)職責(zé):1)負(fù)責(zé)應(yīng)急預(yù)案的制定,組建應(yīng)急救援小組,并組織實(shí)施;2)檢查督促做好重大事故的預(yù)防措施和應(yīng)急救援的準(zhǔn)備工作;3)發(fā)生重大事故時(shí),由指揮機(jī)構(gòu)發(fā)布和解除救援命令,組織救援隊(duì)實(shí)施救援行動(dòng);4)向上級(jí)匯報(bào),組織事故調(diào)查;5)總結(jié)應(yīng)急救援經(jīng)驗(yàn)、教訓(xùn)。146 附表1 除氧器吊
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲(chǔ)空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 農(nóng)村個(gè)體農(nóng)場經(jīng)營合同范本
- 包料裝修合同范本
- 人流手術(shù)合同范本
- 2024年全國特崗教師招聘考試真題
- 2024年欽州市遴選公務(wù)員考試真題
- 2024年臺(tái)州溫嶺市中醫(yī)院招聘員工筆試真題
- 出售隔斷酒柜合同范本
- 個(gè)人房屋擔(dān)保合同范本
- 光伏清洗施工合同范例
- 2024年保山市智源高級(jí)中學(xué)招聘教師考試真題
- 2025年內(nèi)蒙古呼倫貝爾農(nóng)墾拉布大林上庫力三河蘇沁農(nóng)牧場招聘115人歷年高頻重點(diǎn)模擬試卷提升(共500題附帶答案詳解)
- (2025)特種設(shè)備安全管理員考試題庫及參考答案
- 中學(xué)創(chuàng)客教育教學(xué)活動(dòng)計(jì)劃
- 2025年廣東省廣州市食品檢驗(yàn)所事業(yè)單位招聘若干人高頻重點(diǎn)提升(共500題)附帶答案詳解
- 《移動(dòng)通信市場推廣策略》課件
- 2024年湖南工業(yè)職業(yè)技術(shù)學(xué)院高職單招職業(yè)技能測驗(yàn)歷年參考題庫(頻考版)含答案解析
- 2024年湖南司法警官職業(yè)學(xué)院高職單招職業(yè)技能測驗(yàn)歷年參考題庫(頻考版)含答案解析
- 2025年國家藥品監(jiān)督管理局藥品審評中心招聘11人歷年高頻重點(diǎn)提升(共500題)附帶答案詳解
- 2024年廣東省《輔警招聘考試必刷500題》考試題庫含必背答案
- 餐飲企業(yè)牛奶產(chǎn)品推廣方案
- 2025年中國南光集團(tuán)有限公司招聘筆試參考題庫含答案解析