項目專項施工方案
投資總部項目
施工總承包
1#塔吊安拆方案
編制單位:中建八局第一建設(shè)有限公司
編制人:
日期:2023年7月10日
I
項目專項施工方案
目錄
1編制依據(jù)........................................................................................................................................................1
2工程概況........................................................................................................................................................3
2.1工程建設(shè)概況一覽表.........................................................................................................................3
2.2設(shè)計概況.............................................................................................................................................3
2.2.1吊裝設(shè)備選擇概況..................................................................................................................3
2.2.2塔吊基礎(chǔ)選擇概況..................................................................................................................5
2.3工程施工條件.....................................................................................................................................7
2.3.1場地氣象、水文及地質(zhì)構(gòu)造..................................................................................................7
2.3.2現(xiàn)場施工條件..........................................................................................................................9
2.4塔吊吊重分析...................................................................................................................................10
3施工安排......................................................................................................................................................12
3.1項目管理組織...................................................................................................................................12
3.2項目管理目標(biāo)...................................................................................................................................13
3.3各項資源供應(yīng)方式...........................................................................................................................13
3.4施工流水段的劃分及施工工藝流程...............................................................................................13
3.5工程施工重點和難點分析及應(yīng)對措施...........................................................................................14
4施工進(jìn)度計劃..............................................................................................................................................15
5施工準(zhǔn)備與資源配置計劃..........................................................................................................................16
5.1施工準(zhǔn)備計劃...................................................................................................................................16
5.1.1技術(shù)準(zhǔn)備................................................................................................................................16
5.1.2現(xiàn)場準(zhǔn)備................................................................................................................................17
5.2資源配置計劃...................................................................................................................................17
5.2.1勞動力配置計劃....................................................................................................................17
5.2.2工程用成品、半成品需要量計劃........................................................................................18
5.2.3施工機具配置計劃................................................................................................................18
5.2.4測量設(shè)備配置計劃................................................................................................................18
6施工方法及工藝要求..................................................................................................................................20
6.1方案及技術(shù)參數(shù)...............................................................................................................................20
6.1.11#塔吊(ZTT6517)基本性能參數(shù).......................................................................................20
6.1.21#塔吊(ZTT6517)工作半徑和起重性能表.......................................................................20
6.1.31#塔吊(ZTT6517)主要部件外型尺寸及重量...................................................................22
6.1.4輔助安裝機械的選擇............................................................................................................23
6.2施工工藝流程...................................................................................................................................27
6.3施工要點...........................................................................................................................................27
6.3.1塔吊基礎(chǔ)施工........................................................................................................................27
6.3.2汽車吊就位............................................................................................................................32
6.3.3塔吊安裝工序........................................................................................................................32
6.3.4塔吊頂升加節(jié)........................................................................................................................40
I
項目專項施工方案
6.3.5塔吊的調(diào)試及試運................................................................................................................43
6.3.6塔吊的附著安裝....................................................................................................................44
6.3.7塔機安全裝置的檢測及調(diào)試................................................................................................46
6.3.8塔吊安裝后監(jiān)測....................................................................................................................47
6.3.9塔吊拆除................................................................................................................................48
6.3.10塔吊安裝安全措施..............................................................................................................51
6.3.11塔吊頂升安全操作規(guī)程......................................................................................................52
6.4驗收標(biāo)準(zhǔn)...........................................................................................................................................53
6.5驗收程序...........................................................................................................................................55
6.6驗收內(nèi)容...........................................................................................................................................56
6.7驗收人員...........................................................................................................................................58
7各項管理計劃..............................................................................................................................................60
7.1綠色施工管理計劃...........................................................................................................................60
7.1.1綠色施工組織機構(gòu)和職責(zé)分工............................................................................................60
7.1.2綠色施工實施措施................................................................................................................60
7.1.3綠色施工評價........................................................................................................................60
7.2進(jìn)度管理計劃...................................................................................................................................61
7.2.1確定施工進(jìn)度控制點............................................................................................................61
7.2.2施工進(jìn)度管理組織機構(gòu)和職責(zé)分工....................................................................................61
7.2.3進(jìn)度管理措施........................................................................................................................61
7.3質(zhì)量管理計劃...................................................................................................................................61
7.3.1質(zhì)量控制目標(biāo)分解................................................................................................................61
7.3.2質(zhì)量管理的組織機構(gòu)和職責(zé)分工........................................................................................62
7.3.3確定質(zhì)量控制點....................................................................................................................62
7.3.4質(zhì)量保證措施........................................................................................................................62
7.4安全管理計劃...................................................................................................................................62
7.4.1職業(yè)健康安全管理分解目標(biāo)................................................................................................62
7.4.2安全管理組織機構(gòu)和職責(zé)分工............................................................................................63
7.4.3職業(yè)健康安全重大危險源....................................................................................................63
7.4.4職業(yè)健康安全資源配置計劃................................................................................................63
7.4.5安全生產(chǎn)管理制度................................................................................................................63
7.4.6安全生產(chǎn)保證措施................................................................................................................64
7.5成品保護(hù)管理計劃...........................................................................................................................64
7.5.1成品保護(hù)管理組織和職責(zé)分工............................................................................................64
7.5.2成品保護(hù)計劃及保證措施....................................................................................................65
8應(yīng)急預(yù)案......................................................................................................................................................66
8.1應(yīng)急指揮機構(gòu)及職責(zé).......................................................................................................................66
8.2事故風(fēng)險分析...................................................................................................................................67
8.3應(yīng)急救援程序...................................................................................................................................67
8.3.1預(yù)防和預(yù)警............................................................................................................................67
II
項目專項施工方案
8.3.2緊急狀況處置程序................................................................................................................67
8.4應(yīng)急處置措施...................................................................................................................................69
8.4.1應(yīng)急電話的正確使用............................................................................................................69
8.4.2高處墜落現(xiàn)場處置措施........................................................................................................70
8.4.3物體打擊現(xiàn)場處置措施........................................................................................................70
8.4.4坍塌應(yīng)急措施........................................................................................................................71
8.4.5機械傷害事故應(yīng)急措施........................................................................................................71
8.4.6觸電事故應(yīng)急措施................................................................................................................72
8.4.7管線(水管、電纜等)破壞應(yīng)急措施.................................................................................72
8.4.8暴雨應(yīng)急措施........................................................................................................................73
8.4.9火災(zāi)應(yīng)急措施........................................................................................................................73
8.4.10交通事故應(yīng)急措施..............................................................................................................74
8.5應(yīng)急物資準(zhǔn)備...................................................................................................................................74
8.6應(yīng)急響應(yīng)、響應(yīng)結(jié)束、演練...........................................................................................................75
8.6.1應(yīng)急響應(yīng)流程........................................................................................................................75
8.6.2應(yīng)急響應(yīng)結(jié)束........................................................................................................................75
8.6.3應(yīng)急預(yù)案演練........................................................................................................................76
9新型冠狀病毒感染肺炎疫情防控..............................................................................................................77
9.1防疫工作安排...................................................................................................................................77
9.1.1疫情防控工作小組................................................................................................................77
9.1.2成員分組及職責(zé)....................................................................................................................78
9.2物資需求準(zhǔn)備...................................................................................................................................78
9.3疫情防控實施...................................................................................................................................78
9.3.1人員進(jìn)場................................................................................................................................78
9.3.2防疫宣傳管理........................................................................................................................79
9.3.3食堂管理................................................................................................................................80
9.3.4辦公區(qū)管理............................................................................................................................80
9.3.5生活區(qū)管理............................................................................................................................81
9.3.6作業(yè)區(qū)管理............................................................................................................................81
9.3.7“三類人員”管控................................................................................................................81
9.4疫情防治措施...................................................................................................................................81
9.4.1正確佩戴口罩........................................................................................................................81
9.4.2正確洗手................................................................................................................................82
9.4.3工作環(huán)境中防護(hù)措施............................................................................................................82
9.4.4辦公場所中防護(hù)措施............................................................................................................82
9.4.5公共區(qū)域中防護(hù)措施............................................................................................................83
9.4.6施工現(xiàn)場中防護(hù)措施............................................................................................................83
9.5應(yīng)急預(yù)案...........................................................................................................................................83
9.5.1疫情防控應(yīng)急響應(yīng)流程........................................................................................................83
9.5.2疫情日報制度........................................................................................................................84
III
項目專項施工方案
9.5.3出現(xiàn)疑似或確診病例后的應(yīng)急組織....................................................................................84
9.5.4緊急通訊聯(lián)絡(luò)........................................................................................................................84
10計算書及相關(guān)圖紙....................................................................................................................................86
10.1鋼絲繩實際受力計算.....................................................................................................................86
10.2汽車吊承載力驗算.........................................................................................................................87
10.3塔機基礎(chǔ)受力計算.........................................................................................................................88
10.4塔機平面布置圖.............................................................................................................................92
10.5塔機立面圖.....................................................................................................................................93
10.650t汽車吊性能表...........................................................................................................................93
10.71#ZTT6517塔吊附著計算(詳見附件:塔機四桿附著分析報告ZTT6517)............................94
IV
項目專項施工方案
1編制依據(jù)
序號類別文件名稱編號
中華人民共和國住房
1《危險性較大的分部分項工程安全管理規(guī)定》和城鄉(xiāng)建設(shè)部令第
37號
《住房城鄉(xiāng)建設(shè)建設(shè)部辦公廳關(guān)于實施<危險性較大建辦質(zhì)(2018)31
2
分部分項工程安全管理規(guī)定>有關(guān)問題通知》號
國家行政文件
3《建設(shè)工程質(zhì)量管理條例》國務(wù)院令第279號
4《建設(shè)工程安全生產(chǎn)管理條例》國務(wù)院令第393號
5《建筑施工特種作業(yè)人員管理規(guī)定》建質(zhì)[2008]75號
6《建筑起重機械備案登記辦法》建質(zhì)[2008]76號
《海南省<工程質(zhì)量安全手冊(試行)>質(zhì)量檢查實
7
施細(xì)則(試行)》瓊建質(zhì)監(jiān)函〔2023〕
地方行政文件
《海南省<工程質(zhì)量安全手冊(試行)>安全檢查實456號
8
施細(xì)則(試行)》
9《鋼絲繩夾》GB/T5976-2006
10《重要用途鋼絲繩》GB8918-2006
11《塔式起重機》GB/T5031-2023
12《工程測量標(biāo)準(zhǔn)》GB50026-2023
13《塔式起重機設(shè)計規(guī)范》GB/T13752-2017
14《建筑地基基礎(chǔ)設(shè)計規(guī)范》GB50007-2011
15《塔式起重機安全規(guī)程》GB5144-2006
16《混凝土強度檢驗評定標(biāo)準(zhǔn)》GB/T50107-2010
17《混凝土結(jié)構(gòu)設(shè)計規(guī)范》(2015年版)GB50010-2010
18《建筑工程施工質(zhì)量驗收統(tǒng)一標(biāo)準(zhǔn)》GB50300-2013
19《建筑地基基礎(chǔ)工程施工質(zhì)量驗收標(biāo)準(zhǔn)》GB50202-2018
20國家行業(yè)規(guī)范《混凝土結(jié)構(gòu)工程施工質(zhì)量驗收規(guī)范》GB50204-2015
21《起重機械安全規(guī)程第1部分:總則》GB6067.1-2010
22《起重機鋼絲繩保養(yǎng)、維護(hù)、檢驗和報廢》GB/T5972-2016
23《建筑地基處理技術(shù)規(guī)范》JGJ79-2012
24《建筑地基檢測技術(shù)規(guī)范》JGJ340-2015
25《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011
26《建筑機械使用安全技術(shù)規(guī)程》JGJ33-2012
27《塔式起重機操作使用規(guī)程》JG/T100-1999
28《高空作業(yè)機械安全規(guī)則》JG5099-1998
29《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016
30《施工現(xiàn)場機械設(shè)備檢查技術(shù)規(guī)范》JGJ160-2016
31《塔式起重機混凝土基礎(chǔ)工程技術(shù)標(biāo)準(zhǔn)》JGJ/T187-2023
1
項目專項施工方案
32《建筑施工起重吊裝工程安全技術(shù)規(guī)范》JGJ276-2012
33《施工現(xiàn)場臨時用電安全技術(shù)規(guī)范》(附條文說明)JGJ46-2005
《建筑施工塔式起重機安裝、使用、拆卸安全技術(shù)
34JGJ196-2010
規(guī)程》
地方規(guī)范、標(biāo)
35《海南省建筑塔式起重機防臺風(fēng)安全技術(shù)標(biāo)準(zhǔn)》DBJ46-045-2017
準(zhǔn)
36合同《xx投資總部項目總承包合同》/
37設(shè)計文件《xx投資總部項目詳細(xì)勘察報告》/
38招投標(biāo)文件《xx投資總部項目總承包招標(biāo)文件》/
39《建筑地基與基礎(chǔ)工程施工技術(shù)標(biāo)準(zhǔn)》ZJQ08-SGJB202-2017
40《混凝土結(jié)構(gòu)工程施工技術(shù)標(biāo)準(zhǔn)》ZJQ08-SGJB204-2017
企業(yè)技術(shù)標(biāo)準(zhǔn)
41《施工組織設(shè)計編制與管理標(biāo)準(zhǔn)》ZJQ08-SGJB001-2017
42《施工技術(shù)交底編制與管理標(biāo)準(zhǔn)》ZJQ08-SGJB002-2017
43其他1#ZTT6517塔式起重機使用說明書/
2
項目專項施工方案
2工程概況
2.1工程建設(shè)概況一覽表
工程名稱工程性質(zhì)辦公及商業(yè)
建設(shè)規(guī)模2.01億工程地址
總占地面積11121㎡總建筑面積40573㎡
土方(完成褥墊層底以上15cm內(nèi)土方人工清
槽)開挖及外運、土方回填、基礎(chǔ)工程、碎
建設(shè)單位
石褥墊層;主體結(jié)構(gòu)(含人防、裝配式)及
粗裝修工程;裝配式PC預(yù)制構(gòu)件材料采購、
項目承包范圖紙設(shè)計拆分、運輸、檢驗檢測安裝驗收
圍等;室內(nèi)給排水、雨水工程,室外雨污水工
程;室內(nèi)電氣、防雷及接地工程;專業(yè)分包
代建單位工程的預(yù)留、預(yù)埋及洞口封堵工程;人防工
程(含人防設(shè)備、人防門);與主體工程不可
分割的其它附屬或零星工程
消防、通風(fēng)空調(diào)、智能化、泛光照明、弱
主要分包工
設(shè)計單位電、電梯、幕墻、防火門、泳池設(shè)備等所有
程
發(fā)包人指定分包或者獨立分包工程
勘察單位質(zhì)量海南省建設(shè)工程綠島杯
監(jiān)理單位工期498日歷天
合同要求
海南省建筑安全文明施工標(biāo)準(zhǔn)化工
總承包單位安全
地
分包單位科技/
工程主要功
國際化總部辦公區(qū)、配套服務(wù)與商業(yè)區(qū)、地下車庫(含人防)等
能或用途
2.2設(shè)計概況
2.2.1吊裝設(shè)備選擇概況
本工程占地面積為11121㎡,其中東西跨度約101m,南北跨度約112m,計劃各個施
工階段分別在場地東、西、南、北四面布置周轉(zhuǎn)材料堆放場及裝配式材料堆放場,由于場
地受限,利用場地東側(cè)地塊作為鋼筋加工及堆放場地。本項目最大吊運構(gòu)件為PC樓梯,
單個吊重約4.18噸。綜合考慮本工程的吊裝重量、吊裝位置及現(xiàn)場實際需覆蓋范圍等因素,
通過比選,辦公樓西側(cè)最終選擇江西中天機械有限公司生產(chǎn)的1臺QTP160(ZTT6517)水
平式塔機(現(xiàn)場編號為1#塔機),辦公樓東側(cè)最終選擇江西中天機械有限公司生產(chǎn)的1臺
QTP250(ZTT7023)水平式塔機(現(xiàn)場編號為2#塔機)。
3
項目專項施工方案
QTP160(ZTT6517)塔機安裝為固定基礎(chǔ)式,最大獨立高度60m,最大工作幅度可達(dá)
到65m。本項目起重臂長度選擇為65m,起重臂方向為北,初始安裝高度18m,最大安裝
自由高度48m,設(shè)置一道附墻,附墻位置為結(jié)構(gòu)6層,最終安裝使用高度57m;QTP250
(ZTT7023)塔機安裝為固定基礎(chǔ)式,最大獨立高度60m,最大工作幅度可達(dá)到70m。本
項目起重臂長度選擇為70m,起重臂方向為北,初始安裝高度24m,最大安裝自由高度
48m,設(shè)置一道附墻,附墻位置為結(jié)構(gòu)6層,最終安裝使用高度63m。兩臺塔機均隨建筑
高度增加通過頂升加節(jié)至使用高度,QTP160(ZTT6517)、QTP250(ZTT7023)工作時采用
四倍率進(jìn)行吊裝作業(yè),塔吊設(shè)計概況詳見表2.2.1-1,塔吊附墻概況詳見表2.2.1-2。
根據(jù)《海南省建筑塔式起重機防臺風(fēng)安全技術(shù)標(biāo)準(zhǔn)》中規(guī)定,特級防控區(qū)和1級防控
區(qū)內(nèi)1250kN·m以上(含)塔機、2級防控區(qū)內(nèi)3150kN·m以上(含)塔機以及最終安
裝高度達(dá)到100m以上(含)塔機的安裝(拆卸)方案應(yīng)經(jīng)專家論證。本項目地處1級防
控區(qū)內(nèi),且計劃安裝的塔機起重力矩分別為1600kN·m、2500kN·m,因此本塔機安裝方
案需進(jìn)行專家論證。
表-1塔吊設(shè)計概況表
塔機臂長初設(shè)安裝高度自由高度最終使用高度
塔機型號整機功率備注
編號幅度(m)(m)(m)
57(1+16
1#ZTT651765m45KW18(1+3節(jié))48(1+13節(jié))/
節(jié))
63(1+18
2#ZTT702370m65.5KW24(1+5節(jié))48(1+13節(jié))/
節(jié))
表2.2.1-2塔吊附墻概況表
編號1#ZTT65172#ZTT7023備注
附墻高度(m)3333/
一道附著位置9節(jié)中心(33m,6層)9節(jié)中心(33m,6層)/
最終使用高度
57(1+16節(jié))63(1+18節(jié))/
(m)
本工程選用的1#塔機ZTT6517,由江西中天廠家生產(chǎn),最大工作幅度65m,本項目使
用工作幅度65m,起重重量1.6t~8t。2#塔機ZTT7023,由江西中天廠家生產(chǎn),最大工作幅
度70m,本項目使用工作幅度70m,起重重量1.8t~10t。兩種型號設(shè)備狀況穩(wěn)定,起重性
能較好,1#ZTT6517塔吊起重性能詳見表2.2.1-3,2#ZTT7023塔吊起重性能詳見表2.2.1-4。
表2.2.1-31#ZTT6517塔吊起重性能
4
項目專項施工方案
表2.2.1-42#ZTT7023塔吊起重
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 文化場館防水修繕合同
- 汽車制造廠外墻翻新膩子施工合同
- 郊區(qū)倉庫租賃協(xié)議
- 橋梁施工平地機租賃合同
- 高速公路修建施工合同
- 電影院彩繪施工合同
- 證券交易所安保人員聘用協(xié)議
- 建筑施工合同:城市地下管網(wǎng)改造
- 城市公寓交易合同模板
- 紀(jì)念館真石漆修復(fù)合同
- 常用理療技術(shù)
- 國際商法 Part 6 Intellectual Property Law知識產(chǎn)權(quán)法教材
- 常用儀表縮寫字母
- 藍(lán)田股份會計造假案例
- 電氣倒閘操作誤操作原因及防范措施
- 江西省暴雨洪水Ⅴ區(qū)推理公式法、瞬時單位線法計算表格
- 中英文品牌(商標(biāo))授權(quán)書模板
- 分解槽、沉降槽制作安裝施工方案
- 邊坡六棱塊施工工藝及方法
- 中國古建筑行業(yè)分析報告
- 蜂產(chǎn)品訂購合同范本
評論
0/150
提交評論