1、 Weekly Progress Report周報(bào)Project工程名稱(chēng): Medtronic Beijing Office ProjectClient客戶(hù)名稱(chēng):MedtronicReport Number 周報(bào)編碼: Date of Issue上傳日期: 2015.11.23Reporting Period 報(bào)告節(jié)點(diǎn): 2015.11.17 2014.11.23Project start Date 工程開(kāi)工日期: 2015.11.4Actual site works commencement date 實(shí)際現(xiàn)場(chǎng)開(kāi)工日期: Scheduled date of completion竣工日期: E

2、xpected date of completion 預(yù)計(jì)竣工日期: Expected date of moving in預(yù)計(jì)客戶(hù)搬家日期: Executive SummaryA)General Progress Status: 總工程進(jìn)度Item項(xiàng)Phase 階段Actual 實(shí)際完成Scheduled 原計(jì)劃完成Remarks 備注1Design設(shè)計(jì)100%100%2Deepen design深化設(shè)計(jì)100%100%3Tender投標(biāo)100%100%4Construction施工10%15%5Ready for client move in 準(zhǔn)備客戶(hù)入住0%0%6Site Final In

3、spection & Hand Over現(xiàn)場(chǎng)交接0%0%B) Project Cost Overview:工程支出概述Item項(xiàng)Descriptions 類(lèi)型Amount (RMB) 金額Remarks 備注1Committed Contract Sum to date 合同2,580,000.00 10/152Confirmed Variation Amount簽證C)Key Issues Requiring Inputs/actions:Item項(xiàng)Key Issues重點(diǎn)問(wèn)題Remarks備注1IT service room layoutThis week2Plan for PCC

4、 areaconfirmedDetailed Progress Update細(xì)節(jié)進(jìn)度概況1.0 Progress to date:Scheduled Vs Actual 預(yù)計(jì)與實(shí)際進(jìn)度對(duì)比Work in progress as per the schedule 工程進(jìn)度與預(yù)計(jì)相同Delay in present progress but does not affect schedule 進(jìn)度延誤但不影響總的預(yù)計(jì)進(jìn)度Delay in progress (not recoverable)進(jìn)度延誤(趕不上進(jìn)度)Completed works 完工.Item項(xiàng)Packages/Activities類(lèi)別

5、Scheduled Date of Completion(dd-mm-yyyy)預(yù)計(jì)完成時(shí)間Expected/Actual Date of completion(dd-mm-yyyy)實(shí)際完成時(shí)間% of Work Completion as on Date完成進(jìn)度的百分比Status of Activities現(xiàn)場(chǎng)情況Remarks/Issue 備注/問(wèn)題1Preliminary 準(zhǔn)備工作04-1104-11100%complete2Interior works (included security system) 室內(nèi)工程(包含安保系統(tǒng))2.01Con Confirmation of la

6、yout by client客戶(hù)對(duì)圖紙確認(rèn)14-1021-10100%complete2.02Demolition work 拆除工作06-1008-10100%complete2.03Partition Work隔墻作業(yè)20-1180%Working2.04Ceiling Work 天花作業(yè)21-122.05Floor finishes地面作業(yè)26-122.06Built-in Furniture固定家具24-122.07Glazing玻璃25-112.08Electrical Work電氣工程27-1210%Working2.09A/C work 空調(diào)作業(yè)19-1230%Working2.

7、10Fire Protection work消防作業(yè)18-122.11IT room decoration part hand overIT機(jī)房裝飾與移交12-123Furniture & Chairs家具25-124IT弱電工程27-124.1Cabling Works接線作業(yè)09-124.2Testing & Commissioning測(cè)試與運(yùn)轉(zhuǎn)11-125FSB + Landlord final inspections and approvals消防驗(yàn)收與業(yè)主最后檢查并簽署報(bào)告12-015.1Inspection and approval date by FSB 消防批文

8、12-015.2Indoor Air Quality Test室內(nèi)空氣檢測(cè)12-016Moving搬遷13-016.1Moving 搬遷13-012.0 Prospect: The planned activities for next week are as follows:下周工作計(jì)劃Item項(xiàng)Activities 類(lèi)別Action By施工人員Start Date(dd-mm-yyyy)開(kāi)始日期Finish Date(dd-mm-yyyy)完成日期1Partition Work隔墻工程Main-con04-1127-112Electrical work電氣工程Main-con14-112

9、7-123A/C work暖通工程A/C unit11-1119-123.0 Risks & bottlenecks: 風(fēng)險(xiǎn)&瓶頸ItemIssues問(wèn)題Impacts (risks)影響Follow Actions解決方案1The time required of fire trial & final acceptanceMay affect the hand over to move intoTaking the process in advance to gain time4.0 Safety report: 安全報(bào)告ItemIssues問(wèn)題Impacts (risks)影響Action方案12AppendicesAppendix A - Site Progress PhotographsAppendix A Site Progress Photographs213231293

溫馨提示

  • 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
  • 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶(hù)所有。
  • 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
  • 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
  • 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶(hù)上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶(hù)上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
  • 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
  • 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶(hù)因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。

最新文檔

評(píng)論

0/150

提交評(píng)論