第一章編制說明及依據(jù)................................................................6

§1編制依據(jù).........................................................................6

§2編制原則.........................................................................6

§3編制說明.........................................................................7

第二堂工??魂................................................................8

§1工程環(huán)境..........................................................................8

§1.1工程概述....................................................................8

§1.2周邊環(huán)境條件................................................................8

§1.3氣象條件....................................................................9

§2工程范圍.........................................................................9

§3工程設(shè)計概況.....................................................................9

§3.1基坑支護(hù)方案設(shè)計依據(jù).........................................................9

§3.2基坑支護(hù)設(shè)計方案的選取.......................................................10

§3.3鉆(沖)孔樁...................................................................10

§3.4攪拌樁施工...................................................................11

§3.5錨索.........................................................................11

§3.6錨桿及噴層施工...............................................................12

§3.7超前微型樁施工...............................................................12

§4工程地質(zhì)與水文地質(zhì)..............................................................12

§4.1工程地質(zhì)....................................................................12

§4.2水文地質(zhì)....................................................................13

§5.1施工工程量大、工期緊,資源投入大.............................................14

§5.2基坑地質(zhì)狀況復(fù)雜............................................................14

§5.3基坑攪拌樁止水為一重點.......................................................14

§5.4基坑變形監(jiān)測為一重點。.......................................................14

§5.5基坑四周管網(wǎng)多,保護(hù)及遷移為一重點。.........................................14

第三聿BI,海體鬃劃...........................................................14

§1施工總體策劃目標(biāo)................................................................14

§2施工總體安排....................................................................15

§2.1工程總體部署................................................................15

§2.1.1施工場地布置考慮...............................................................15

§2.1.2圍護(hù)結(jié)構(gòu)施工分區(qū)考慮...........................................................16

§2.1.3機(jī)械設(shè)備選擇考慮...............................................................16

§2.1.5預(yù)應(yīng)力錨索張拉時機(jī)考慮.........................................................16

§2.1.6施工臨時水電布置考慮...........................................................16

§2.2工程總體施工流程..........................................................17

§3施工準(zhǔn)備及施工總平面布置........................................................18

§3.1施工準(zhǔn)備..................................................................18

§3.2管線拆遷及保護(hù)............................................................19

§3.3施工總平面布置.............................................................19

§3.4交通疏解..................................................................21

§3.5施工總平面布置圖...........................................................21

§4現(xiàn)場管理與組織..................................................................21

§4.1現(xiàn)場項目法管理組織機(jī)構(gòu)....................................................21

§4.2項目管理機(jī)構(gòu)配置情況表.....................................................22

§4.3主要人員及部門管理職責(zé)劃分.................................................22

§4.4項目管理機(jī)構(gòu)配備情況輔助說明資料............................................23

§5相關(guān)單位協(xié)調(diào)配合措施............................................................23

§5.1與各承包商之間的接口界面協(xié)調(diào)................................................23

§5.2與監(jiān)理工程師的協(xié)調(diào)..........................................................24

§5.3與相鄰工程的協(xié)調(diào)............................................................24

§5.XX市政相關(guān)部門之間的協(xié)調(diào).....................................................24

§5.5與當(dāng)?shù)卣熬用裰g的協(xié)調(diào)..................................................24

第園量25

§1主要工程項目施工計劃進(jìn)度指標(biāo).....................................................25

§2工程施工計劃橫道圖...............................................................25

§3主要工期目標(biāo)....................................................................25

§3.1總工期......................................................................25

§3.2主要階段工期目標(biāo)............................................................25

繁5章資講劃.................................................................26

§1機(jī)械設(shè)備的投入計劃..............................................................26

§1.1主要施工機(jī)械設(shè)備、主要施工機(jī)械進(jìn)場計劃.....................................26

§1.2機(jī)械設(shè)備保證措施...........................................................27

§2勞動力的投入計劃及人員保證措施..................................................28

§2.1勞動力安排計劃..............................................................28

§2.2人員保證措施................................................................28

§3主要材料供應(yīng)計劃及材料保證措施..................................................29

§3.1主要材料進(jìn)場計劃表..........................................................29

§3.2材料保證措施................................................................29

§3工程項目資金計劃與合同用款估算計劃..............................................32

第六章美貌施工揍泰、工琶和解決為褰.................................................33

§1施工測量........................................................................33

§1.1原始數(shù)據(jù)驗算...............................................................33

§1.2平面控制布設(shè)...............................................................33

§1.3高程控制網(wǎng)布設(shè).............................................................33

§1.4測量儀器配備...............................................................33

§2深層攪拌樁施工..................................................................34

§2.1概述........................................................................34

§2.2施工工藝流程................................................................34

§2.3施工方法及技術(shù)措施..........................................................35

§2.4施工質(zhì)量控制...............................................................36

§2.5質(zhì)量檢驗...................................................................37

§2.6施工中常見問題和處理.......................................................37

§3超前微型樁施工..................................................................38

§3.1概述.........................................................................38

§3.2施工工藝流程...............................................................38

§3.3施工方法及技術(shù)措施..........................................................39

§3.4工程質(zhì)量保證措施............................................................42

§4鉆(沖)孔樁工程.................................................................43

§4.1概述.......................................................................43

§4.2施工工藝流程...............................................................43

§4.3施工方法及技術(shù)措施.........................................................44

§4.4常見問題處理方案...........................................................50

§4.4.1施工法中孔壁坍塌及對策...................................................50

§4.4.2縮頸.....................................................................51

§4.4.3卡鉆.....................................................................51

§4.4.4導(dǎo)管脫落.................................................................52

§4.4.5斜孔.....................................................................52

§4.4.6掉錘.....................................................................52

§4.4.7鋼筋籠上浮...............................................................52

§4.4.8樁底沉渣量過多...........................................................53

§4.4.9導(dǎo)管進(jìn)水.................................................................53

§4.4.10斷樁....................................................................54

§5錨索施工工藝...................................................................54

§5.1概述........................................................................54

§5.2施工工藝流程...............................................................55

§5.3施工方法及技術(shù)措施.........................................................55

§5.4質(zhì)量控制...................................................................58

§5.5施工中常遇問題及處理.......................................................58

§6錨桿及噴層施工................................................................59

§6.1概述........................................................................59

§6.2施工工藝流程...............................................................60

§6.3施工方法及技術(shù)措施.........................................................60

§6.4質(zhì)量控制...................................................................62

§7基坑土石方挖運(yùn)..................................................................64

§7.1施工部署....................................................................64

§7.1.1施工準(zhǔn)備..................................................................64

§7.2土方開挖施工方法..........................................................66

§7.2367

§7.3基坑內(nèi)降排水...............................................................68

§7.4垂直運(yùn)輸工程...............................................................68

§7.4.1施工準(zhǔn)備........................................................................68

§7.4.2垂直運(yùn)輸安全管理措施............................................................68

§7.4.3技術(shù)安全規(guī)程....................................................................69

篥上章BI嬲閽asm測...........................................................71

§1施工監(jiān)測目的及意義..............................................................71

§2監(jiān)測人員架構(gòu)....................................................................71

§3監(jiān)測內(nèi)容及技術(shù)措施..............................................................71

§3.1監(jiān)測內(nèi)容....................................................................71

§3.2監(jiān)測技術(shù)措施................................................................72

第八章BIWWS...................................................................................................77

§1工期保證措施....................................................................77

§1.1工期保證總體措施...........................................................77

§1.2主要分部工程的工期保證措施.................................................78

§1.3確保關(guān)鍵工期的保證措施.....................................................78

§2技術(shù)保證措施....................................................................79

§2.1技術(shù)管理體系................................................................79

§2.2測量管理....................................................................79

§2.3試驗管理....................................................................80

§2.4施工管理....................................................................80

§3質(zhì)量保證措施....................................................................80

§3.1工程質(zhì)量的管理目標(biāo)及保證體系...............................................81

§3.2工程質(zhì)量目標(biāo)的保證體系.....................................................86

§3.3施工質(zhì)量流程控制...........................................................87

§4安全保證措施....................................................................92

§4.1安全目標(biāo)....................................................................92

§4.2安全保證體系................................................................93

§4.3安全施工保證措施............................................................93

§4.4安全施工技術(shù)性措施..........................................................94

§4.5安全施工過程控制...........................................................101

§4.6安全應(yīng)急流程控制...........................................................102

§4.7危險源辨識..................................................................105

§4.8管線保護(hù)...................................................................106

§5文明施工保證體系及措施..........................................................107

§5.1文明施工目標(biāo)...............................................................107

§5.2施工現(xiàn)場文明管理...........................................................107

§5.2.1場容場貌管理....................................................................107

§5.2.2環(huán)境綠化管理....................................................................108

§5.2.3臨時道路管理....................................................................108

§5.2.4材料堆放管理....................................................................108

§5.2.5辦公生活區(qū)管理..................................................................109

§5.3環(huán)境保護(hù)措施...............................................................109

§5.3.1衛(wèi)生管理措施....................................................................109

§5.3.2污染控制措施.............................................................109

§5.4突發(fā)事件處理方案...........................................................110

§5.4.1安全事故措施.............................................................110

§5.4.2治安管理措施.............................................................110

§5.4.3消防措施.................................................................111

§5.5周圍環(huán)境協(xié)調(diào)...............................................................113

§5.5.1防止擾民措施.............................................................113

§5.5.2糾紛應(yīng)急措施.............................................................113

§5.6節(jié)假日施工的保障措施......................................................114

§6成品保護(hù)保證措施...............................................................115

§6.1主要管理措施.............................................................115

§6.2技術(shù)措施...................................................................115

戮0應(yīng)急馥塞.............................................................116

§1應(yīng)急救援組織...................................................................116

§2應(yīng)急救援職責(zé)...................................................................116

§3安全應(yīng)急流程...................................................................116

§4應(yīng)急救援工作和報告程序.........................................................118

§5事故應(yīng)急救援電話...............................................................118

§6事故應(yīng)急救援材料物資...........................................................118

§7突發(fā)事故發(fā)生應(yīng)急處理方法.......................................................119

§8急救技術(shù)及常備藥品.............................................................119

§8.1急救技術(shù)..................................................................119

§8.2常備藥品..................................................................120

§9基坑坍塌事故的應(yīng)急措施.........................................................121

§10機(jī)械傷害事故的應(yīng)急措施........................................................122

§11高處墜落事故的應(yīng)急措施........................................................122

§12物體打擊事故的應(yīng)急措施........................................................123

§13觸電事故的應(yīng)急措施............................................................124

§14火災(zāi)事故的應(yīng)急措施............................................................125

§15附件...........................................................................126

§15.1附件一:施工總平面布置圖....................................................126

§15.2附件二:施工進(jìn)度計劃橫道圖..................................................126

§15.3附件三:土方分層開挖示意圖..................................................126

§15.4附件四:坡道口收口示意圖....................................................126

第一章編制說明及依據(jù)

§1編制依據(jù)

I.《碧桂園XX市花園中地塊基坑支護(hù)工程》招標(biāo)文件。

2.《碧桂園XX市花園中地塊基坑支護(hù)工程》招標(biāo)設(shè)計圖。

3.碧桂園XX市花園中地塊基坑支護(hù)工程招標(biāo)答疑紀(jì)要。

4.碧桂園XX市花園中地塊基坑支護(hù)工程現(xiàn)場調(diào)查資料。

5.國XXXX市現(xiàn)行有關(guān)法規(guī)、標(biāo)準(zhǔn)、技術(shù)規(guī)范、定額,以及特別是環(huán)境保護(hù)、水

土保持方面的政策和法規(guī)。

《混凝土結(jié)構(gòu)設(shè)計規(guī)范》(GB50010-2002)

《建筑結(jié)構(gòu)荷載規(guī)范》(GB50009-2001)

《巖土錨桿(索)技術(shù)規(guī)程》(CECS22:2005)

《地下工程防水技術(shù)規(guī)范》(GB50108-2001)

《建筑地基基礎(chǔ)設(shè)計規(guī)范》(GB50007-2002)

《建筑地基處理技術(shù)規(guī)范》(JCJ79-2002)

XX省《建筑地基基礎(chǔ)施工規(guī)范》(DBJ15)

《建筑基坑支護(hù)技術(shù)規(guī)程》(JGJ120-99)

《錨桿噴射混凝土支護(hù)技術(shù)規(guī)范》(GB50056-2001)

《鋼筋焊接及驗收規(guī)程》(JGJ18-2003)

6.我單位施工隊伍、技術(shù)裝備能力以及以往施工同類工程的實踐經(jīng)驗。

§2編制原則

1.遵循招標(biāo)文件條款,響應(yīng)招標(biāo)文件要求,確保實現(xiàn)業(yè)主要求的質(zhì)量、工期、安

全、環(huán)境保護(hù)、文明施工和造價等各方面的工程目標(biāo)。

2.指導(dǎo)思想是:施工方案可行、施工技術(shù)先進(jìn)、施工組織科學(xué)、重信譽(yù)、守合同,

優(yōu)質(zhì)、安全、按期完成。

3.嚴(yán)格執(zhí)行施工過程中涉及的相關(guān)規(guī)范、規(guī)程和技術(shù)標(biāo)準(zhǔn)。

4.貫徹執(zhí)行國家和XX市有關(guān)方面的方針政策、遵守法律法規(guī)、尊重當(dāng)?shù)氐拿耧L(fēng)

民俗。

5.重視生態(tài)環(huán)境,在施工期間及竣工后不發(fā)生水土流失,確保工程范圍外的原地

形、地貌不被破壞,道路恢復(fù)原狀。

6.重視工程范圍的工程地質(zhì)、水文地質(zhì)調(diào)查工作,建立以地質(zhì)資料為先導(dǎo)、以量

測為依據(jù)的信息化施工管理體系。

7.施組編制做到施工總體部署和分項工程施工組織相結(jié)合、重點工程和一般工

程相結(jié)合、特殊技術(shù)和普通技術(shù)相結(jié)合,總體上使施組具有重點突出、內(nèi)容全面、思

路清晰的特點。

8.充分發(fā)揮我單位專業(yè)優(yōu)勢,做到依靠科技,精心組織,合理安排,突破難點。確

保優(yōu)質(zhì)、安全、快速建成碧桂園XX市花園中地塊基坑支護(hù)工程。

§3編制說明

本施工組織設(shè)計根據(jù)既有施工條件進(jìn)行編制,主要說明如下:

1、必須保證業(yè)主按期提供場地。

2、施工場地布置及施工部署、具體施工工藝基本按投標(biāo)施工組織設(shè)計考慮實施。

3、根據(jù)施工招標(biāo)要求,本工程工期為75日歷天,施工組織計劃按此“關(guān)門工期”

考慮,對投標(biāo)時的施組安排、進(jìn)度指標(biāo)作了適當(dāng)調(diào)整。

4、根XX公司對本工程施工的項目組建的實際到位人員,調(diào)整現(xiàn)場管理組織機(jī)構(gòu)

及有關(guān)責(zé)任人,并根XX公司在進(jìn)一步研究后優(yōu)化施組進(jìn)行機(jī)械設(shè)備配備。

第二》工棚K況

§1工程環(huán)境

§1.1工程概述

工程名稱:碧桂園XX市花園中地塊基坑支護(hù)工程

建設(shè)地點:XX市禪城區(qū)嶺南大道東側(cè)

建設(shè)單位:XX市禪城區(qū)碧桂園房地產(chǎn)開發(fā)XX公司

設(shè)計單位:XX市泰基工程技術(shù)XX公司

擬建場地位于XX市禪城區(qū)嶺南大道東側(cè),交通便利。場地較大,基坑總體呈長方

型,長邊長約154.2m,短邊長約130m,周長約542.8m;現(xiàn)場地較平坦,經(jīng)現(xiàn)場實測,坑

頂絕對標(biāo)高為3.40m,相對標(biāo)高約為-L30m),基坑挖深考慮到底板墊層底(底板面相

對標(biāo)高為-9.30m,底板600厚、墊層100厚),基坑底相對標(biāo)高為TO.00m,基坑開挖深

約8.70mo

本基坑設(shè)計側(cè)壁安全等級:西側(cè)靠近嶺南大道的基坑安全等級為一級,其它區(qū)段

為二級,基坑支護(hù)結(jié)構(gòu)使用年限自支護(hù)結(jié)構(gòu)完工之日起計為1年;±0.00相當(dāng)于絕對

標(biāo)高4.700mo

§1.2周邊環(huán)境條件

基坑北側(cè):該側(cè)地下室邊線距地塊用地紅線為6.距北地塊地下室邊線約

56m,紅線外為規(guī)劃瀾石二路;

基坑?xùn)|側(cè):該側(cè)地下室邊線距地塊用地紅線為6.6m,距圍墻約9.4m,紅線外為規(guī)

劃路;

基坑南側(cè):該側(cè)地下室邊線距地塊用地紅線為5.3m,距南地塊地下室邊線約

32.8m,紅線外為規(guī)劃新民一路。該側(cè)空地擬作鋼筋堆場使用(要求距基坑邊不小于2m,

堆載小于50kPa)o

基坑西側(cè):該側(cè)地下室邊線距地塊用地紅線為6.3~9.3m,距圍墻約4.4m,圍墻外

為嶺南大道人行道。

基坑周邊管線分布詳見《周邊地下管網(wǎng)圖》。

§1.3氣象條件

根據(jù)我司查詢xx市相關(guān)氣象資料顯示,本區(qū)位于南亞熱帶季風(fēng)氣候區(qū),春秋風(fēng)和

日麗,夏炎冬暖,降水豐沛,日照充足,在季風(fēng)環(huán)流控制下,4?8月,受海洋氣流影響,

氣候炎熱,降水量大,多偏南風(fēng);每年9月至翌年3月,受大陸冷高壓影響,氣候干燥,

降水較少,多偏北風(fēng)。每年5?10月,多熱帶氣旋,中心最大風(fēng)力處達(dá)12級,甚至以上。

據(jù)XX市歷年統(tǒng)計資料,年平均氣溫21.9℃極端最高氣溫38.7℃,最低氣溫0.0℃;年

平均降水量1696.5mm,最大降水量2864.7mm,最小降水量1113.2mm,日最大降水量

284.9mm;年平均風(fēng)速1.9m/s,極大風(fēng)速35.4m/s;年平均影響佛山的熱帶氣旋3.2

個;年平均相對濕度77%。

§2工程范圍

本項目為碧桂園XX市花園中地塊基坑支護(hù)工程,基坑周長約542.8m,深度約

8.70m的基坑支護(hù)工程;

包括基坑支護(hù)(鉆(沖)孔樁、水泥攪拌樁、錨索、錨桿、腰梁、腰梁、壓頂梁、

噴錨網(wǎng)等)和土方開挖等;

施工場地布置。包括發(fā)包人提供的施工平面圖紙指定的施工臨設(shè)場地地面硬化、

臨時施工道路、施工場地排水、施工用水、施工用電;本工程所需的臨時設(shè)施搭設(shè)、

施工道路及臨時用水用電、施工排水、安全文明施工措施等;

后續(xù)施工單位進(jìn)行的施工場地及工程竣工資料交接和配合。

§3工程設(shè)計概況

§3.1基坑支護(hù)方案設(shè)計依據(jù)

1、《建筑基坑支護(hù)技術(shù)規(guī)范》(JGJ120-99);

2、《XX省建筑基坑支護(hù)工程技術(shù)規(guī)范》(DBJ/T15-20-97);

3、《混凝土結(jié)構(gòu)設(shè)計規(guī)范》(GB50010-2002);

4、《巖土錨桿〈索〉技術(shù)規(guī)程》(CECS22:2005);

5、《建筑樁基技術(shù)規(guī)范》(JGJ94-2008);

6、《建筑基坑工程監(jiān)測技術(shù)規(guī)范》(GB50497-2009);

7、《XX市禪城區(qū)東平大橋北側(cè)項目中地塊地下室?guī)r土工程勘察報告》;

8、業(yè)主提供的相關(guān)建筑結(jié)構(gòu)圖紙以及周邊環(huán)境平面圖。

§3.2基坑支護(hù)設(shè)計方案的選取

1、基坑挖深8.70m,且基坑西側(cè)緊臨已有嶺南大道,南側(cè)現(xiàn)為南地塊施工場地,北

側(cè)為施工用地,東側(cè)地下室邊線距工地圍墻約9.4m,距紅線6.6m。

2、場地較大,地質(zhì)條件起伏較大,部分區(qū)域含較厚的淤泥質(zhì)土及砂層,部分巖層埋

深較淺?;拥状蟛糠致溆趶?qiáng)風(fēng)化巖層。

根據(jù)上述場地周邊環(huán)境及地質(zhì)狀況特點,將本基坑安全等級西側(cè)靠近嶺南大道一

側(cè)定為一級,其它段定為二級?;又ёo(hù)根據(jù)各區(qū)段周邊環(huán)境、地質(zhì)條件不同及施工

工期等要求分別采用〃灌注樁+攪拌樁+一道(兩道)預(yù)應(yīng)力錨索”和〃攪拌樁+噴錨網(wǎng)〃的

支護(hù)方案。

§3.3鉆(沖)孔樁

支護(hù)樁施工說明:具體采用鉆孔、沖孔或旋挖成孔最終由甲方具體確定。

(一)、灌注樁成孔

1、灌注樁的機(jī)具選擇、護(hù)筒埋設(shè)、泥漿護(hù)壁、施工要領(lǐng)及清孔等要求應(yīng)按現(xiàn)行

規(guī)范和規(guī)程處理;

2、樁成型后必須清除孔底沉渣,清孔后沉渣厚度不得大于300,并應(yīng)立即灌注水

下碎。

(二)、灌注樁鋼筋籠制作及安裝

1、縱向受力鋼筋采用HRB400鋼筋,配筋按均勻配筋設(shè)計,配筋詳見大樣圖。保

護(hù)層厚50mm;

2、螺旋箍筋采用HPB235鋼筋,橫向加勁筋采用HRB335,縱橫鋼筋交接處焊接牢

固;

3、鋼筋籠外側(cè)需設(shè)混凝土墊塊或采用其他有效措施,以保障鋼筋保護(hù)層厚度的

準(zhǔn)確性。

(三)、灌注樁水下混凝土澆灌

1、本工程的擋土樁混凝土強(qiáng)度等級C25o水下砂的用料及配合比按現(xiàn)行規(guī)范和

規(guī)程處理;

2、本工程采用導(dǎo)管灌注水下混凝土,導(dǎo)管的構(gòu)造和使用以及灌注水下碎的施工

要領(lǐng)按現(xiàn)行規(guī)范和規(guī)程處理;

3、為確保水下混凝土的質(zhì)量,向?qū)Ч芄嘧⑺卤藭r建議采用碎輸送泵或采用其

它有效措施;

4、施工時應(yīng)按樁頂?shù)脑O(shè)計標(biāo)高掌握好混凝土的灌注量。建議灌注於完成面之標(biāo)

高比樁頂?shù)脑O(shè)計標(biāo)高高出0.8米;

5、灌注樁強(qiáng)度達(dá)到設(shè)計強(qiáng)度的70%(7天)后,方可進(jìn)行土方開挖。

§3.4攪拌樁施工

1、攪拌樁直徑為500,間距見大樣圖,樁的垂直偏差不得超過1%,樁位偏差不得

大于50mm;

2、攪拌樁施工中采用四噴四攪的施工方法,施工中參數(shù)如下:樁身強(qiáng)度2

1.OMPa;采用P.C.32.5R復(fù)合硅酸鹽水泥,每米水泥用量不少于50kg;水灰比0.45~

0.55;攪拌提升速度W0.5~0.8m/min。必須保證攪拌樁的搭接質(zhì)量,搭接時間不大于

24小時,如間歇時間過長,應(yīng)采用局部補(bǔ)樁或注漿措施;

3、基坑開挖時攪拌樁的齡期不少于15天。

§3.5錨索

1、錨索施工按《巖土錨桿(索)技術(shù)規(guī)范CECS22:2005》進(jìn)行;

2、成孔采用泥漿護(hù)壁成孔,若淤泥質(zhì)砂層較厚,泥漿護(hù)壁成孔困難時,須加套管

跟進(jìn);

3、錨索采用3~5x765鋼絞線,鋼絞線強(qiáng)度標(biāo)準(zhǔn)值為1860MPa。成孔直徑為150mm;

4、錨索長度需以入巖控制,采用一次注漿,注漿材料選用水灰比為0.5~0.55的

純水泥漿,并加入適量的早強(qiáng)劑、及膨脹劑,水泥標(biāo)號為P.C.32.5R復(fù)合硅酸鹽水泥,

注漿壓力為0.5^1.OMPa;

5、鋼絞線錨固段架線環(huán)與緊箍環(huán)每隔1m間隔設(shè)置,緊箍環(huán)系16號鐵絲繞制,不

少于兩圈,自由段每隔2m設(shè)置一道架線環(huán),以保證鋼絞線順直;

6、待砂漿注漿體、壓頂梁或腰梁達(dá)到設(shè)計強(qiáng)度的70%后(齡期約5天)方可進(jìn)行

錨索張拉;

7、錨索鎖定前先張拉至設(shè)計抗拔力的1.1倍,保持15min,然后卸荷至零,再重新

張拉至鎖定荷載預(yù)應(yīng)力進(jìn)行鎖定作業(yè)。錨索張拉荷載分級及觀測時間應(yīng)遵守規(guī)范進(jìn)

行。

8、錨索施工過程中為盡可能減少成孔對地層產(chǎn)生的影響,應(yīng)進(jìn)行跳打。

§3.6錨桿及噴層施工

1、錨桿施工按《巖土錨桿〈索〉技術(shù)規(guī)程CECS22:2005》進(jìn)行;

2、錨桿采用HRB400鋼筋,錨桿采用鉆機(jī)成孔,成孔直徑為*130mm;

3、錨桿注漿采用M20水泥砂漿,注漿壓力為0.5~1.OMPa,水泥標(biāo)號為P.C.32.5R

復(fù)合硅酸鹽水泥;

4、掛網(wǎng)噴射碎:鋼筋網(wǎng)采用66@200X200,加強(qiáng)筋采用]16,鋼筋網(wǎng)[6鋼筋采用綁

扎連接,加強(qiáng)筋及加強(qiáng)筋與土釘?shù)倪B接采用焊接。噴射砂強(qiáng)度等級為C20,噴層厚度為

100mm,分兩次噴射。碎面層向上翻過基坑頂1.0m,以形成護(hù)坡,大樣圖見設(shè)計圖所示。

5、若錨桿全在雜填土或砂層中,可采用嬲C48的鋼花管代替,壁厚3.5mm。鋼花

管采用打入式,要求壓力灌注純水泥漿,水灰比為0.5飛.55,水泥標(biāo)號為P.C.32.5R復(fù)

合硅酸鹽水泥,注漿壓力為0.5~1.OMPa,注漿體強(qiáng)度為15MPa,要求每m水泥摻入量不

少于40kg。

§3.7超前微型樁施工

1、超前微型樁用鉆機(jī)成6150的孔,成孔間距如圖,成孔垂直偏差不大于現(xiàn),用

清水清孔,直到孔口返出清水后灌注純水泥漿,水灰比為0.5~0.55o

2、灌漿后在孔內(nèi)置入鋼管,然后進(jìn)行二次補(bǔ)漿,將水泥漿收縮部分填滿。

3、鋼管采用6114X3的焊管。

§4工程地質(zhì)與水文地質(zhì)

§4.1工程地質(zhì)

場地位于珠江三角洲地區(qū),屬沖積平原地貌,場地地勢較為平整,場地內(nèi)未發(fā)現(xiàn)

有影響場區(qū)穩(wěn)定性的構(gòu)造形跡等不良地質(zhì)作用,場地的區(qū)域穩(wěn)定性較好。

場地鉆孔揭露深度范圍內(nèi)第四系土層為填土、沖積土,基巖為第三系地層,巖性

為泥質(zhì)粉砂巖,自上而下敘述如下:

1、第四系人工填土層:

素填土<1〉:灰黃色,松散,主要由粘性土組成,局部夾碎磚、石塊或中細(xì)砂,欠壓

實,為新近堆填,局部孔段頂部為碎地面,局部孔段為雜填土。

2、第四系沖積層:

a.粉砂灰色,飽和,松散,分選性較好,成分以石英砂為主,含少量淤泥質(zhì)

±o平均標(biāo)貫7擊。

b.淤泥<2-2〉:深灰色,飽和,流塑,有腐殖臭味,含腐殖質(zhì),夾薄層粉細(xì)砂,局部孔

段夾腐木。平均標(biāo)貫1.3擊。

c.粉質(zhì)粘土<2-3>:灰色,灰黃色,棕紅色,可塑,局部軟塑,以粉、粘粒組成為主,

含少量砂,粘性較好,稍有光澤,韌性中等,強(qiáng)度中等,局部孔段含砂。平均標(biāo)貫7.8擊。

d.細(xì)砂<2-4>:灰黃色,飽和,稍密~中密,分選性較差,成分以石英砂為主,呈次棱

角狀,局部孔段含粘性土。平均標(biāo)貫12擊。

3、第四系殘積層:本場區(qū)缺失。

4、第三系地層,巖性為泥質(zhì)粉砂巖。

a.全風(fēng)化泥質(zhì)粉砂巖本場區(qū)缺失。

b.強(qiáng)風(fēng)化泥質(zhì)粉砂巖<4-2>:棕紅色,局部灰黃色,具原巖結(jié)構(gòu),成份、強(qiáng)度已顯著

改變,巖芯呈硬土狀、半巖半土狀、巖狀,局部孔段為強(qiáng)風(fēng)化砂巖。其巖石堅硬程度為

極軟巖,巖體完整程度為極破碎。

c.中風(fēng)化泥質(zhì)粉砂巖<4-3>:棕紅色,砂質(zhì)結(jié)構(gòu),層狀構(gòu)造,裂隙稍發(fā)育,礦物成份

以石英為主,粘土礦物次之,巖芯呈塊狀、短柱狀、局部長柱狀,敲擊聲脆。其巖石堅

硬程度為軟巖,巖體完整程度為較破碎。

d.微風(fēng)化泥質(zhì)粉砂巖<4-4〉:棕紅色,砂質(zhì)結(jié)構(gòu),層狀構(gòu)造,礦物成份以石英為主,

粘土礦物次之,巖芯呈長柱狀,局部短柱狀,敲擊聲脆。其巖石堅硬程度為較軟巖,巖體

完整程度為較破碎。

§4.2水文地質(zhì)

擬建場地地下水類型主要為孔隙水,賦存于沖積層中的潛水,其富水性和透水性

較好,受大氣降水入滲或側(cè)向補(bǔ)給,以蒸發(fā)或滲流方式進(jìn)行排泄;另一類為裂隙水,主

要賦存于風(fēng)化巖的裂隙中。地下水對碎具微腐蝕性,對鋼筋混凝土結(jié)構(gòu)中的鋼筋具微

腐蝕性,對鋼結(jié)構(gòu)有弱腐蝕性。

§5工程重點和難點分析

§5.1施工工程量大、工期緊,資源投入大

本工程基坑開挖深度達(dá)8.70m,攪拌樁15051m,鉆(沖)孔樁共290根,預(yù)應(yīng)力錨索施

工長度約10295m,錨桿施工長度4424m,具有施工深度大,資源投入多的特點,工程施工

過程中,制約因素相當(dāng)多,如施工工序間的約束、資源的組織調(diào)配、施工隊伍的協(xié)調(diào)等,

對總工期有相當(dāng)大的影響等,都可能制約施工進(jìn)度,而工程總工期要求為135天,施工工

期非常緊。

§5.2基坑地質(zhì)狀況復(fù)雜

整個場地工程地質(zhì)情況比較復(fù)雜,對土方開挖、鉆(沖)孔樁及錨索施工均帶來不

利影響。

§5.3基坑攪拌樁止水為一重點

基坑地下水位高,為保證止水效果,攪拌樁施工質(zhì)量是關(guān)鍵,在攪拌樁施工過程

中安排施工經(jīng)驗豐富的施工人員進(jìn)行全程跟蹤管理,對攪拌樁垂直度、水泥用量、搭

接質(zhì)量進(jìn)行嚴(yán)格控制。

§5.4基坑變形監(jiān)測為一重點。

本基坑開挖較深加之基坑四周環(huán)境比較復(fù)雜,為控制基坑位移,加強(qiáng)適時監(jiān)測并

將監(jiān)測數(shù)據(jù)及時反饋給監(jiān)理及設(shè)計。

§5.5基坑四周管網(wǎng)多,保護(hù)及遷移為一重點。

根據(jù)設(shè)計文件可知,基坑四周管網(wǎng)很多,尤其是基坑西側(cè)及東側(cè),部分管線及配電

房在開工前要完成遷移工作,本基坑開挖前將協(xié)調(diào)xx市政部門摸清管網(wǎng)的具體走及

埋深,對受開挖移影響的管網(wǎng)進(jìn)行遷移或做好保護(hù)措施,在管網(wǎng)位置處設(shè)置明顯的標(biāo)

/士匕、O

第三章虹總體策劃

§1施工總體策劃目標(biāo)

1、總工期與關(guān)鍵工期:嚴(yán)格按項目法進(jìn)行工程管理,抓住關(guān)鍵工期合理組織施工。

在合同工期內(nèi)完成工程的施工、驗收并清理退場完畢。

2、工程質(zhì)量:建立“TQC”全面質(zhì)量管理小組XX公司將嚴(yán)格按照國家頒發(fā)的建

筑工程各專業(yè)施工質(zhì)量驗收規(guī)范和《建筑工程施工質(zhì)量驗收統(tǒng)一標(biāo)準(zhǔn)》(GB50300-2001)

和GB/T19001-IS09001:2008質(zhì)量管理體系建立完整的工程質(zhì)量保證體系,以先進(jìn)的工

法、工藝和嚴(yán)格的管理確保工程質(zhì)量。并做到:工程質(zhì)量合格率100%。

3、安全生產(chǎn):嚴(yán)格按XX省和XX市及我集團(tuán)的有關(guān)法規(guī)、規(guī)定進(jìn)行安全生產(chǎn)管

理。杜絕重大安全事故,年輕傷率控制在1在以下。

4、文明施工:嚴(yán)格按《XX市建設(shè)工程文明施工標(biāo)準(zhǔn)》的規(guī)定執(zhí)行實施。確保文

明施工達(dá)到XX省雙優(yōu)工地標(biāo)準(zhǔn)。

§2施工總體安排

§2.1工程總體部署

針對本工程項目施工特點及重難點,我部擬從以下方面進(jìn)行控制。以保證高效、

保質(zhì)、保量、按期完成施工任務(wù)。

§2.1.1施工場地布置考慮

基坑北側(cè):該側(cè)地下室邊線距地塊用地紅線為6.

溫馨提示

  • 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
  • 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
  • 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
  • 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
  • 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
  • 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
  • 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。

最新文檔

評論

0/150

提交評論